Tender For Shifting Of 33 Kv, 11 Kv,Lt Line And Distribution Transformer Under Deposit Scheme 2025-26 Under Electricity Distribution Division-Nautanwa
Tender Value
Ref. Documents
Estimated cost
Bid Submission
12 May 2025
0 days left
EMD
16700
Bank guarantee accepted
Document Fee
3540
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
nautanwa → Uttar Pradesh
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender For Shifting Of 33 Kv, 11 Kv,Lt Line And Distribution Transformer Under Deposit Scheme 2025-26 Under Electricity Distribution Division-Nautanwa
BOQ
| Sl. No. | Item Description |
| 1 | Workfor Shifting of 33 KV, 11 KV,LT Line and Distribution Transformer Under Deposit Scheme 2025-26 |
| 2 | Loading, unloading and carriage ofMaterialfrom Electricity Store Center Maharajganj to work site |
| 3 | ST Pole (11 Mtr long) |
| 4 | PCC 9 Mtr |
| 5 | PCC 8.5 Mtr |
| 6 | 33 KV ‘XLPE’ Cable 3x300mm² |
| 7 | 33 KV ‘XLPE’ C/J Kit 3x300mm² indoor/Outdoor |
| 8 | 11 KV XLPEcable 3x120 sqmm |
| 9 | 11 KV XLPEcable 3x70 sqmm |
| 10 | I/D & O/D Cable Jointing Kit for 3x120 sqmm |
| 11 | I/D & O/D Cable Jointing Kit for 3x70 sqmm |
| 12 | M. S. Angle Iron 65x65x6mm Bracing with Clamp |
| 13 | ACSR Dog conductor |
| 14 | GI Pipe 6\" Dia |
| 15 | 33 KV Pin Insulator |
| 16 | 33 KV Pin with nut |
| 17 | 33 KV Disc insulator |
| 18 | 33 KV Disc fitting |
| 19 | ACSRWeasel Conductor |
| 20 | 11 KV. pin insulator with pin |
| 21 | 11 KV. Disc Insulator with disc fitting |
| 22 | 11 KV. V-type X-arm |
| 23 | Stay complete |
| 24 | Earthing complete |
| 25 | The excavaton of foundation pit in mix soil/ normal soil/ soft soil & hard rock as per site condtion and its back filling and leveling etc. The size of the pit will be (750 x 450) mm and having depth of 1/6th of the full length of the support of 8.5 Mtr. PCC pole as per drawing. |
| 26 | Erection of 8.5 Mtr. Single PCC Pole with all ffittings as per specification. |
| 27 | Erection of 8.5 Mtr. Double PCC Pole with all ffittings as per specification. |
| 28 | Grouting of 8.5 Mtr. PCC with material as per specification. |
| 29 | The excavaton of foundation pit in mix soil/ normal soil/ soft soil & hard rock as per site condtion and its back filling and leveling etc. The size of the pit will be (750 x 450) mm and having depth of 1/6th of the full length of the support of 9 Mtr. PCC pole as per drawing. |
| 30 | Erection of 9 Mtr. Single PCC Pole with all ffittings as per specification. |
| 31 | Erection of 9 Mtr. Double PCC Pole with all ffittings as per specification. |
| 32 | Grouting of 9 Mtr. PCC with material as per specification. |
| 33 | The excavaton of foundation pit in mix soil/ normal soil/ soft soil & hard rock as per site condtion and its back filling and leveling etc. The size of the pit will be (750 x 450) mm and having depth of 1/6th of the full length of the support of 11 Mtr. ST pole as per drawing. |
| 34 | Erection of 11 Mtr. Single ST Pole with all ffittings as per specification. |
| 35 | Grouting of 11 Mtr.STPole with material as per specification. |
| 36 | Construction of Plinth for 11 Mtr.STPole with material as per specification. |
| 37 | Earthing of pole with MS Earthing Rod of 20 x 2500 mm and6 SWG GI wirenut, bolt & washer. |
| 38 | Erection ofStay set complete |
| 39 | Concerting of Stay with material as per specification. |
| 40 | Unloading of 25 KVADistribution Tranformer on erected 8.5 Mtr. Double PCC Pole |
| 41 | Installation of 25 KVADistribution Tranformer on erected 8.5 Mtr. Double PCC Pole |
| 42 | Earthing of25 KVA Distribution Tranformer Neutral and Body by M.S. Earthing rod with 6 SWG G.I. wire with Nut, bolt and washer. |
| 43 | H.T. Side connection of 25 KVA Distribution Tranformer and L.T. side connection with cable and aluminum lug. |
| 44 | Unloading of 63 KVADistribution Tranformer on erected 8.5 Mtr. Double PCC Pole |
| 45 | Installation of 63 KVADistribution Tranformer on erected 8.5 Mtr. Double PCC Pole |
| 46 | Earthing of63 KVA Distribution Tranformer Neutral and Body by M.S. Earthing rod with 6 SWG G.I. wire with Nut, bolt and washer. |
| 47 | H.T. Side connection of 63 KVA Distribution Tranformer and L.T. side connection with cable and aluminum lug. |
| 48 | Unloading of 100 KVADistribution Tranformer on erected 8.5 Mtr. Double PCC Pole |
| 49 | Installation of 100 KVADistribution Tranformer on erected 8.5 Mtr. Double PCC Pole |
| 50 | Earthing of100 KVA Distribution Tranformer Neutral and Body by M.S. Earthing rod with 6 SWG G.I. wire with Nut, bolt and washer. |
| 51 | H.T. Side connection of 100 KVA Distribution Tranformer and L.T. side connection with cable and aluminum lug. |
| 52 | Unloading of 250 KVADistribution Tranformer from old Plinth |
| 53 | Mounting of 250 KVADistribution Tranformer from old Plinth to new Plinth |
| 54 | H.T. Side connection of 250 KVA Distribution Tranformer and L.T. side connection with cable and aluminum lug. |
| 55 | Unloading of 400 KVADistribution Tranformer from old Plinth |
| 56 | Mounting of 400 KVADistribution Tranformer from old Plinth to new Plinth |
| 57 | H.T. Side connection of 400 KVA Distribution Tranformer and L.T. side connection with cable and aluminum lug. |
| 58 | Laying and sagging ofACSR Weseal Conductorwith binding of conductor on insulator. |
| 59 | Laying and sagging ofACSR Dog Conductorwith binding of conductor on insulator. |
| 60 | Cutting of Tree Branch |
| 61 | Providing and Installation of L.T. Cable 3.5 x 70 sqmm |
| 62 | Providing and Installation of V- Cross Arm Clamp 11 KV |
| 63 | Providing and Installation of F Brecket |
| 64 | Providing and Installation of F Brecket Clamp |
| 65 | Providing and Installation of Top Channel |
| 66 | Providing and Installation of LT. Clamp with nut & bolts |
| 67 | Providing and Installation of LT. sackle insulator 100x115 mm. |
| 68 | Providing and Installation of Droper Channel |
| 69 | Providing and Installation of T-Off Channel |
| 70 | Providing and Installation of Top, Droper, T-Off Channel Clamp |
| 71 | Providing and Installation of Transformer Base |
| 72 | Providing and Installation of Nut & Bolt |
| 73 | Providing and Installation of PG Clamp |
| 74 | Providing and Installation of X Bresinh Angal (Cross) |
| 75 | Providing and Installation of Gaurding Angle |
| 76 | Providing and Installation of Gaurding Angle Clamp |
| 77 | Providing and Installation of Eye Bolt |
| 78 | Providing and Installation of Danger Bord |
| 79 | Providing and Installation of Barbed Wire |
| 80 | Providing and Installation of Stone Pad |
| 81 | Carriage of dismentling materials form site to domp store |
| 82 | Dismentalling of PCC 8.5Mtr |
| 83 | Dismentalling of PCC 9 Mtr |
| 84 | Dismentalling of STP 11 Mtr |
| 85 | Reconnection & Disconnection of consumer cables |
| 86 | Cable laying along with digging, bricks and sand |
| 87 | Shifing of 25 KVA T/F |
| 88 | Shifing of 63 KVA T/F |
| 89 | Shifing of 100 KVA T/F |
| 90 | Shifing of 250 KVA T/F |
| 91 | Shifing of 400 KVA T/F |
| 92 | Making Plinth of 250KVA T/F & 400 KVA |
| 93 | Fencing of 250KVA T/F & 400 KVA |
| 94 | Earthing of T/F (B+N) |
AI Tender Summary
Tender Timeline
May 06, 2025
11:30 IST
Tender Published
Tender notice published.
CompletedMay 12, 2025
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedMay 12, 2025
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender