| 1 | Earth works in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lifts, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil |
| 2 | Excavating, supplying, stacking and filling of local earth (including royalty) by mechanical transport up to a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in foundation trenches, plinth, sides of foundation etc. complete for all lift |
| 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level: 1:3:6 (1 cement: 3 coarse sand (zone-iii) derived from natural sources: 6 graded stone aggregate 20 mm nominal size derived from natural sources). Cement Make: Ultratech/Birla/Bangur/Shree Cement |
| 4 | Making plinth protection 50mm thick of cement concrete 1:3:6 (1 cement : 3 coarse sand (zone- iii) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) over 75mm thick bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including necessary excavation, levelling & dressing & finishing the top smooth. Cement Make: Ultratech/Birla/Bangur/Shree Cement |
| 5 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to and above plinth level: 1:1.5:3 (1 cement: 1.5 coarse sand (zone-iii) derived from natural sources: 3 graded stone aggregate 20 mm nominal size derived from natural sources). Cement Make: Ultratech/Birla/Bangur/Shree Cement |
| 6 | Centering and shuttering including strutting, propping etc. and removal of form for |
| 7 | Foundations, footings, bases for columns |
| 8 | Columns, piers, abutments, pillars, posts and struts |
| 9 | Steel reinforcement for RCC work including straightening, cutting, bending, placing in position and binding all complete up to plinth level. Thermo-mechanically treated bars of grade fe-500D or more. Make: Apollo/Jindal/Sail/Tata/Jsw |
| 10 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. Make: Apollo/Tata/Jindal/Sail |
| 11 | Finishing walls with Acrylic Smooth exterior paint of required shade: New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm). Make: Asian Paints or equivalent products of other brands like Berger/Nerolac/dulux) |
| 12 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade: Two or more coats on new work. Make: Asian Paints or equivalent products of other brands like Berger/Nerolac/dulux) |
| 13 | Dismantling aluminium/ Gypsum partitions, doors, windows, fixed glazing and false ceiling including disposal of unserviceable material and stacking of serviceable material within 50 meters lead as directed by Engineer-in-charge |