| 1 | Construction of Approach Road, Land Development, Internal Road and Allied works at Head Work Site |
| 2 | Earth work in filling in compound, tank, low land,ditches etc. with good earth, in layers not exceeding 150 mm. including breaking clods and consolidating the same by ramming and dressing complete. (Payment will be made on profile measurement before and after the work) |
| 3 | With carried earth arranged by the contractor within a radius exceeding 3 km. but not exceeding 5 km. including the cost of carried earth. |
| 4 | Box cutting or filling in Road embankment in all sorts of soil including spreading the soils properly over the flank as necessary or on berm to approximate grade & camber and rolling the sub-grade with power roller to proper camber and grade as per direction and satisfaction of Engineer-in-charge including uprooting and removing plants and jungles when and where necessary.: Depth up to 150 mm. |
| 5 | Single brick flat soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with powdered earth or local sand. |
| 6 | Supplying and laying Polythene Sheet (150gm / sq.m.) over damp proof course or below flooring or roof terracing or in foundation or in foundation trenches. |
| 7 | Hire charges for shuttring with centering and necessary staging upto 4 m. using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beam, columns, lintles curved or straight including fitting, fixing and striking out after completion of works.(In all floors): 25mm to 30mm thick wooden shuttering as per decision and direction of Engineer-In-Charge.a) 25mm to 30mm thick wooden shuttering without staging in foundation |
| 8 | Ordinary cement concrete ( mix 1:1.5:3 ) with graded stone chips ( nominal 20 mm size) excluding shuttering and reinforcement. If any, : Pakur Variety. (Rate Analysis) |
| 9 | Road Restoration and other alied works etc….. |
| 10 | Bituminous pucca road (approx. 450mm depth) cutting by using gaiti, chisel, hammer etc. and picking up the withdrawing excavated materials and remove the same within distance of 30mtr. at least all complete for fixing/crossing all dia of pipe line as per direction of EIC. |
| 11 | Dismantling all type of plain cement concrete works, stacking serviceable materials of site and removing rubbish as directed within a lead of 75mtr. for laying all dia pipe line in ground floor, a) upto 150mm thick. |
| 12 | b) above 150 mm thickness |
| 13 | Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement, if any, in ground floor as per relevant IS codes. Pakur variety. |
| 14 | Making holes in two sides of wall of culvert/drain or any other structuresin any places for laying any dia pipe line within structures intwo sides of wall of culvert /drain /any structure at any places and mending good damages all complete as per direction of EIC. |
| 15 | Add GST 18.00 % |
| 16 | Add Labour Welfair Cess 1% |