| 1 | Item Description |
| 2 | Survey work |
| 3 | Earth work excavation in (Mar, Kankar and kankar mixeddry soil) in digging or in embankment including lead up to 30 mtr and lift up to 1.50 mtr. Including dressing making porfile and manual compaction but excluding mechaniclal compaction ID OR 4.12 ( 0.00 to 1.50 mtr) Above GL( machine/manual By any means) |
| 4 | Excavation in (Soft rock without Blasting) in digging or in embankment including lead up to 30 mtr and lift up to 1.50 mtr including dressing making profile and manual compaction but excluding mechanical compaction. ID SOR 4.28 (from 1.5 to Beyond 3 mtr) (machine/manual by any means) |
| 5 | Earth work in excavation in saturated soil ( excluding cost of dewatering) mar, kabar and rankar soil in foundation of wall, pier, abutment etc. with disposal with in 30 mtr lead and 1.50 mtr lift. ID SOR 4.16 (0.0 mtr to 1.5 mtr) (machine/manual ny any means) |
| 6 | Removal of slush (excluding cost of dewatering) from the bed of nala / Ponds SOR 4.17 |
| 7 | Earth work in excavation in mar kabar and rankar soil in foundation of wall, pier, abutment etc. with disposal with in 30 mtr lead and 1.50 mtr lift. ID SOR 4.14 b (0.00 mtr to 1.5 mtr) (inlet, pitlet, ramp, ghat) |
| 8 | Sand filling for foundation of inlet, oulet, ramp, ghat. |
| 9 | C.C. with 1:3:6 cement, sand and 22.4 to 50 mm stone ballast including the cost of materials labour etc. required for proper complition of works (inlet, oulet, ramp, ghat.) |
| 10 | R.C.R Stone massonery work in 1:4 cement sand mortar including the cost of material, labour etc. required for proper completion of work (inlet, oulet, ramp, ghat) |
| 11 | Supply and fixing of 1000 mm NP3 hume pipe with collar for inlet work. |
| 12 | C.C. in 1:2:4 Cement, sand and 10 to 20 mm grit including the cost of materials labours and etc. to required for proper completion of work (inlet, oulet, ramp.) |
| 13 | Plaster work in 1:3 c/s mortar 20 mm thick on stone masonery work. |
| 14 | Dry stone boulder filling in D/S & U/S in one chamber of each (Inlet,Outlet). |
| 15 | Dewartring during the work before excavation of slush/saturated soil by 8 H.P diesel pumping set. |
| 16 | Supply & fixing of citizens information board at the site. (C.I.B) |