| 1 | Part-A (Supply of Material)Tailless unit of Reputed Make/Brand for 100 KVA T/F |
| 2 | Tailless unit of Reputed Make/Brand for 160 KVA T/F |
| 3 | Tailless unit of Reputed Make/Brand for 250 KVA T/F |
| 4 | Tailless unit of Reputed Make/Brand for 400 KVA T/F |
| 5 | Tailless unit of Reputed Make/Brand for 630 KVA T/F |
| 6 | Alu. Lug 240 sqmm of Reputed Make/Brand |
| 7 | Alu. Lug 400 sqmm of Reputed Make/Brand |
| 8 | Alu. Lug 630 sqmm of Reputed Make/Brand |
| 9 | Alu. Lug 1000 sqmm of Reputed Make/Brand |
| 10 | Part-B (Erection work)Cartiage ofLT XLPE Cable 1x240 sqmm/LT XLPE Cable 1x400 sqmm/LT XLPE Cable 1x630 sqmm/LT XLPE Cable 1x1000 sqmm from store center agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-50Kms.) |
| 11 | Cartiage of Line Material from Store Center Agra to work of site through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.) Various type of material as- LT Fuse set/11 KV Fuse Set, Nut & Bolt of required size and other line material, if required in Estimate/Package. |
| 12 | Laying of LT XLPE Cable 240 sqmm as per RESPO Norms anddirection by supervising by Engineer. |
| 13 | Laying of LT XLPE Cable 1x400 sqmm as per RESPO Norms anddirection by supervising by Engineer. |
| 14 | Laying of LT XLPE Cable 1x630 sqmm as per RESPO Norms anddirection by supervising by Engineer. |
| 15 | Laying of LT XLPE Cable 1x1000 sqmm as per RESPO Norms anddirection by supervising by Engineer. |
| 16 | Installation of Tailless Unit on various capacity of Distribution T/F as per RESPO Norms & Direction by superivising Engineer. |
| 17 | Installation of LT Fuse set as per RESPO norms and direction by superivising Engineer. |
| 18 | Installation of 11 KV Fuse set as per RESPO norms and direction by superivising Engineer. (each set = 03 Nos) |
| 19 | Fixing of Alu. Lug 240 sqmm as per RESPO Norms anddirection by supervising by Engineer. |
| 20 | Fixing of Alu. Lug 400 sqmm as per RESPO Norms anddirection by supervising by Engineer. |
| 21 | Fixing of Alu. Lug 630 sqmm as per RESPO Norms anddirection by supervising by Engineer. |
| 22 | Fixing of Alu. Lug 1000 sqmm as per RESPO Norms anddirection by supervising by Engineer. |
| 23 | Fixing of Nut & bolt on various type of material as per RESPO mannual norms and direction by superivising Engineer. |
| 24 | Chemical Earthing of Various Capacity distribution T/F including all required materials as per RESPO Manual & as per direction by supervising engineer including the costof arrangment of labour, T&P carrier etc required for proper completion of work at contractor cost. |
| 25 | Concreting work of tell less unit as per RESPO Manual and as per direction by superivising Engineer including the costof arrangment of labour, T&P carrier etc required for proper completion of work. |