| 1 | Dismantling lime or cement mortar brick work including stacking of desmantled materials with in 50 m distance s directed by Engineer Incharge. DSR-15.7.4 |
| 2 | Dismantling lime or R.C.C. or R.B. Workincluding stacking of desmantled materials with in 60 m distance s directed by Engineer Incharge SI No.-694 |
| 3 | Dismantling lime or R.C.C. or R.B. Workincluding stacking of desmantled materials with in 60 m distance s directed by Engineer Incharge SI.No 697 |
| 4 | DismantlingDoor or Window including chaukhats with fast and iccluding stacking materials with in 60 m dSi. No 703 |
| 5 | Excavation in foundation in ordinary soil (Loam clay, or sand ) including lift upto 1.5 m & lead up to 30.0 Mtr & including filling,watering and ramming ofexcavated earth in to the trenches or in to the space between the building and the sides of foundataion trenches or in to the plinth and removal & disposal of surplus earth as directed by the Engineer- In-Charge up to a distance of 30.0 Mtr from the foundation trenches .as per SI.No 251 |
| 6 | E/W in cutting or in embankment including cartage of 5 kmlead. |
| 7 | Cement concrete work in 1:4:8 with cement coarse sand and stone ballast including all. |
| 8 | M-150 Brick work in 1:6 cement sand mortor etc all complete work in foundation uptoplinth level SI.No. 303 |
| 9 | M-150 Brick work in 1:4 cement coarse sand mortor etc all complete work in super structure SI.No. 305A |
| 10 | Reinforced Cement Concrete work with cement,approved coarse sand of 2.5 F.M and 2 cm(3/4\") gauge approved stone gritin proportion of 1:1.5:3 in coloumn in super structureupto plinth Levelexcluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I.binding wire and including necessary centering and shuttering etc.and supply of all materials, labour and T&P etc. required for proper completion of the work.including cost of Binding wire as per S.I No. 287A |
| 11 | Reinforced Cement Concrete work with cement,approved coarse sand of 2.5 F.M and 2 cm(3/4\") gauge approved stone gritin proportion of 1:1.5:3 in R.C.C. Columnexcluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I.binding wire and including necessary centering and shuttering etc.and supply of all materials, labour and T&P etc. required for proper completion of the work.including cost of Binding wire as per S.I No. 289 |
| 12 | Reinforced Cement Concrete work with cement,approved coarse sand of 2.5 F.M and 2 cm(3/4\") gauge approved stone gritin proportion of 1:1.5:3 in Rcc T Beam in super structure above Plinth Beamexcluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I.binding wire and including necessary centering and shuttering etc.and supply of all materials, labour and T&P etc. required for proper completion of the work.including cost of Binding wire as per S.I. No 285 |
| 13 | 2.5 cm thik Damp Proof course with cement and approved coarse sand 1:2 with and Including water Proofing material as ordered by the Engineer incharge in the proportion as specified by the manufactures including supply of all materials; labour and tools & plants etc required for proper curing and shuttering as necessary S.I.361. |
| 14 | Reinforced Cement Concrete work with cement,approved coarse sand of 2.5 F.M and 2 cm(3/4\") gauge approved stone gritin proportion of 1:1.5:3 in slab in super structure above Plinth Beamexcluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I.binding wire and including necessary centering and shuttering etc.and supply of all materials, labour and T&P etc. required for proper completion of the work.including cost of Binding wire as per S.I no 284 |
| 15 | Reinforced Cement Concrete work with cement,approved coarse sand of 2.5 F.M and 2 cm(3/4\") gauge approved stone gritin proportion of 1:1.5:3 in slab in super structure above Plinth Beamexcluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I.binding wire and including necessary centering and shuttering etc.and supply of all materials, labour and T&P etc. required for proper completion of the work.including cost of Binding wire as per S.I no 288 |
| 16 | Reinforced Cement Concrete work with cement,approved coarse sand of 2.5 F.M and 2 cm(3/4\") gauge approved stone gritin proportion of 1:1.5:3 in slab in super structure above Plinth Beamexcluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I.binding wire and including necessary centering and shuttering etc.and supply of all materials, labour and T&P etc. required for proper completion of the work.including cost of Binding wire as per S.I no 283 |
| 17 | M.S. (Tor Steel Plane) inPlain Work Such as RCC or RB Work includingSupply of Steel and its wastage Bend,Hooks and authorised over lapping shall be masured and Including cost of binding wire. S.I.No. 504 |
| 18 | S/f of mild steel gate/ grill ofincluding all labour material T&P |
| 19 | 12 mm thick plastering work in 1:4 cement sand mortor all complete work. SI no. 597C |
| 20 | Providing and applying White cement basedputty of average thickness 1 mm of approved brand and kajufacturer over the plastered wall surface to prepare the suurface even and smooth complete. DSR 13.80 (factor-0.728) |
| 21 | Distempringwith oil bound distemper of approved brand and manfucture and of requried shade including cost of all materials labours T&P etc.S.I. No. 649 and651. |
| 22 | Wall Painting with plastic emulsion paint of approved brand and manufacture on decortive wall surface S.I. No, 15.15+15.16 |
| 23 | Painting or varnishing on iron work in small areas or new wood work with one coat of ready mix primer. S.I No 641+642 |
| 24 | Providing and layingvitrifitd tiles on floorof 600 × 600mm size with water absorption less than 0.08% and conforming to IS 15622 of approvedmake in all colours and shade, laid on 20 mm thick cement mortar 1:4 joining with gray cement slurry @ 3.3 kg/sqm includinggrouting thejoints with white cement and matching pigments etc the tiles must be cut with the zero chipping diamond cutter only . DSR 11.41A 1.1 |
| 25 | Providing and 1st qualityceramic glazed tiles conforming to IS 15622 over 12 mm thick bed with 1:3 cementmortar. DSR 11.37A |
| 26 | Black Zebra Marble Stone Flooring with 18mm thick marble stone, as per sample of marble approfed by Engineer-in-charge over 20mm thick base of cement mortar1:4 laid and jointed with grey cement slurry including rubing and polishing complete with. DSR 11.23.4 |
| 27 | 25mm thick ccflooring for Apron |
| 28 | Providing and fixing tiled false ceiling of specified material of size 595*595in true horizontal levelsuspended on interlocking metal grid of hot dippped galvanized ateel sections consisting of main T runner with suitably spaced joints to het required lenth and of size 24*38 mm made from 0.30 mm thick steelDSR12.52.1 |
| 29 | Supply and fixing of 4.5 cm thick teak wood fully panelled fully glazed door and window shutters including supply & fixing of wooden cleats and stops and including fixing & adjustment of hinges, bolts locks, handles spring and other fittings but excluding their supply and including painting with two coats of black Japan on all iron fitting if necessary. including fixing the glass panes with putty and brad. Glass to be 4 cm thick. Fitting with nedessary swrews to be supplied by the deptt. SI no 411 |
| 30 | Alluminium Door for bathrooms and ventilators (As per market rate) |
| 31 | All assceries related to ventilators and parda |
| 32 | Providing an fixing SS (grade 304) railing made of hollow tubes ,channel,plates including all oprations and accessoriesDSR 10.28 |
| 33 | Chairs (as per market rate.) |
| 34 | table( as per market rate.) |
| 35 | Podium (as per market rate.) |
| 36 | AC 1.5 ton 5 staar (as per market rate.) |
| 37 | Celling Fan as per market rate. |
| 38 | water cooler (as per market rate.) |
| 39 | RO UV Machnic( as per market rate.) |
| 40 | ADD 8% lighting |
| 41 | Add 5% for sanitary |
| 42 | 2% cotingency charge |
| 43 | sale of materials |