| 1 | Working Charges |
| 2 | 15.43.2:Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in-Charge:Bituminous road |
| 3 | 100.1.1:Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in all kinds of soil. |
| 4 | 100.1.2:Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth exceeding 1.5m but not exceeding 3m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in all kinds of soil. |
| 5 | 100.8.1:Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution tape in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals. |
| 6 | 100.7.1:Bailing out water with 5HP engine and pump set including conveyance to the site, erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil and other stores pay of staff etc., complete. |
| 7 | 100.98.1008:Engaging Coolie. |
| 8 | 100.98.1009:Engaging Fitter ( grade 1). |
| 9 | 100.9.11:Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 160 mm nominal outside diameter pipes. |
| 10 | OD32797/2024-2025:Interconnecting the newly laid 160mm PVC pipe with existing90mm /75mm/63mm PVC pipes using 160mm PVC TEE, and suitable specials, etc.,including the cost of all labour and materials etc., complete as the direction ofdepartmental officers |
| 11 | OD32798/2024-2025:Interconnecting the existing 300mm CI pipe with newly laid 160mm PVC pipe using the specials supplied by the contractor and the charges for earth work excavation etc complete as per the direction |
| 12 | OD32804/2024-2025: Shifting water supply house connection from the existing line to the newly laid 160 mm pipe using saddle clamp,pvc MTA,elbow,etc including earth work excavation,hire charges for tools,cost of materials & Conveyance etc complete as per the direction of dept.officer |
| 13 | 100.31.2.4:Conveying and fixing C.I. sluice valves (with cap) by providing bolts, nuts, rubber insertions etc., complete, but excluding the cost of the valve (tail pieces, if required, will be paid separately): 150mm diameter, Class II. |
| 14 | 2.1.1:Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil |
| 15 | 15.60:Disposal of building rubbish/ malba/ similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved |
| 16 | 16.78.1:Construction of granular sub- base by Providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, Carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in- Charge.With Material conforming to Grade - I ( size range 75 mm to 0.075 mm) having CBR Value- 30 |
| 17 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) |
| 18 | Material charges |
| 19 | 100.98.216:Supply of PVC Pipe, 6kg/cm2, 160mm Dia. |
| 20 | 100.98.508:Supply of CI Plain End Valve Conforming to IS 14846 - 2000, Sluice Valve with Cap PN 1.6, Size 150mm. |
| 21 | OD90772/2024-2025:Supplying 160 mm CIR joint |
| 22 | OD148004/2024-2025:Solvent Cement |
| 23 | Construction of Valve Chamber |
| 24 | 15.43.2:Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in-Charge:Bituminous road |
| 25 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil |
| 26 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) |
| 27 | 5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size |
| 28 | 5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete |
| 29 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more |
| 30 | 13.7.1:12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1 cement : 3 fine sand) |