| 1 | DETAILED ESTIMATE |
| 2 | 15.43.2:Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in-Charge:Bituminous road |
| 3 | 15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) |
| 4 | 100.1.1:Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in all kinds of soil. |
| 5 | 100.8.1:Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution tape in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals. |
| 6 | 100.9.11:Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 160 mm nominal outside diameter pipes. |
| 7 | 100.25.4:Cutting of 150mm AC pipes of all classes diametrically, the cut being diametrically perpendicular to the axis of pipe and smoothening of the cut ends etc., complete. |
| 8 | 100.98.1008:Engaging Coolie. |
| 9 | 50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete |
| 10 | 2.16.1:Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete (Measurements to be taken of the face area timbered).Depth not exceeding 1.5m |
| 11 | OD221077/2024-2025:Interconnecting the newly laid 160mm pvc pipe line with the existing pvc pipe of size 50mmto 110 mm by supplying specials all cost of materials and necessary earth work excavation in all classes of soil etc.complete as per direction of departmental officers |
| 12 | OD221079/2024-2025:Interconnection charge for connecting newly laid line160mm pvc pipe to the existing150mm AC pipe line using CID joint and suitable specials including labour charge etc complete |
| 13 | OD221078/2024-2025:Shifting Existing water connection/ street tap from old pipe line to newly laid pipe line including labour for earth work excavation,dismantling connection from old pipe line , making re connection to newly laid pipe line including cost of fitting suitable saddle clamp,bend union, elbow,coupling, reducer, barrel nipple, GM valve etc. complete and labour charges etc. complete |
| 14 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) |
| 15 | COST OF MATERIALS |
| 16 | 100.98.239:Supply of PVC Pipe, 10kg/cm2, 160mm Dia. |
| 17 | OD221076/2024-2025:SUPPLYING160MM PVC BEND(10kg/cm2)-45-DEGREE |
| 18 | OD221075/2024-2025:SUPPLYING160MM PVC BEND(10kg/cm2)-90DEGREE |
| 19 | Road restoration charge |
| 20 | 3.6:Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m |
| 21 | 4.2.A.1:Construction of granular sub-base by providing graded material, spreading in uniform layers with a motor grader on a prepared surface, mixing by mix in-place method with rotavator at OMC, and compacting with a vibratory roller to achieve the desired density, complete as per clause 401. Grading-III -For lower sub-base - Mix in Place Method |
| 22 | 4.12:Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. |
| 23 | 5.1.a:Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means. |
| 24 | 5.2.a:Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. |
| 25 | 5.2.b:Providing and applying tack coat with bitumen emulsion (RS) using emulsion pressure distributor at the rate of 0.25 - 0.30 kg per sqm on the prepared Granular Surface cleaned with mechanical broom. |
| 26 | 5.3.2.a:Providing and laying bituminous macadam with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with a bituminous binder (VG 30), transported to the site, laid over a previously prepared surface with paver finisher to the required grade, level, and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction For Grading II - (19 mm nominal size) |
| 27 | 5.6.2.a:Providing and laying bituminous concrete with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with a bituminous binder( NRMB) @ 5.4 percent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level, and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects For Grading - II (13.2 mm Nominal Size) |