| 1 | Constructionof RCC Slab Culvert @Illamthopputheru in Ganapathiagraharam Panchayat |
| 2 | Earth work excavation for foundation in all clauses of soils and sub soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and boiling out water whenever necessary et complete complying with standard specification. SS20 B |
| 3 | Supplying and filling with M-sand in layers of not more than 15 cm thick for foundation including cost and conveyance of all other charges. |
| 4 | Cement concrete 1:4:8 mix (one cement four sand and eight aggregate) using 40mm gauge handbroken granite stone jelly for foundation including dewatering if found ecessary and laid in layers of not more than 15 cm thick and compacted,etc., complete complying withstandard specfication. |
| 5 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc completefor 10 cum. |
| 6 | Reinforced cement concrete 1:1.5:3 mix using 20mmISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum |
| 7 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc completefor bed blocksfor10 cum |
| 8 | Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length, bending to shape and tying in position and forming grills for all R.C.C works |
| 9 | Supplying and erecting centeringshuttering includingnecessary supportsforplane surface infoundationandbasementandinallfloorsforR C Ccolumn footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, criticalpier etc... |
| 10 | Supplying and erecting centeringshuttering includingnecessary supportsforplane surface infoundationandbasementandinallfloorsforR C Ccolumn footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, criticalpier etc... |
| 11 | Retaining Wall |
| 12 | Earth work excavation for foundation in all clauses of soils and sub soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and boiling out water whenever necessary et complete complying with standard specification. SS20 B |
| 13 | Supplying and filling with M-sand in layers of not more than 15 cm thick for foundation including cost and conveyance of all other charges. |
| 14 | Cement concrete 1:4:8 mix (one cement four sand and eight aggregate) using 40mm gauge handbroken granite stone jelly for foundation including dewatering if found ecessary and laid in layers of not more than 15 cm thick and compacted,etc., complete complying withstandard specfication. |
| 15 | Supplying and erecting centeringshuttering includingnecessary supportsforplane surface infoundationandbasementandinallfloorsforR C Ccolumn footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, criticalpier etc... |
| 16 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc completefor 10 cum. |
| 17 | Provision For Name Board |
| 18 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |