| 1 | Earth work Excavation and depositing on bank with initial lead and lift in all classes of soil except hard rock requiring blasting including all labour charges etc.,complete for for foundation upto 0.30 m depth |
| 2 | Earth work Excavation and depositing on bank with initial lead and lift in all classes of soil except hard rock requiring blasting including all labour charges etc.,complete for for foundation upto 0.30 m depth |
| 3 | Earth work Excavation and depositing on bank with initial lead and lift in all classes of soil except hard rock requiring blasting including all labour charges etc.,complete for for foundation upto 0.30 m depth |
| 4 | Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification. |
| 5 | Collection and supply of CARTED EARTHfrom appd quarry including cost and conveyance of all materials to site including all labour charges for fillingetc.complete, |
| 6 | Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. . |
| 7 | Brick work in cement mortar 1:5 mix using country bricks 83/4\"x41/4\"x21/4\" including cost and conveyance of all materials to site and all labour charges etc complete |
| 8 | Below Basement |
| 9 | Super Structure |
| 10 | First Floor |
| 11 | Centering below GL: Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers including conveyance of all materials to site and proper centering etc complete. |
| 12 | Grade beam |
| 13 | Column upto basement |
| 14 | Lintel and roof |
| 15 | Sunshade |
| 16 | First Floor Column |
| 17 | First Floor Lintel and roof |
| 18 | First Floor Sunshade |
| 19 | Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length, bending to shape and tying in position and forming grills for all R.C.C works |
| 20 | Reinforced cement concrete M20 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum |
| 21 | GroundFloor |
| 22 | Terrace Floor |
| 23 | First Floor |
| 24 | Supplying and fabrication of the following rolling Shutters including cost and conveyance and all charges etc compl |
| 25 | Paving the floor with kota stone slab of size 600 x 600 of 18 / 20mm (un-polished) antiskid in all floors laid in of cement mortor 1:3 (one cement three sand), 20mm thick and pointed with colour cement neatly including polishing with polishing stone and oxalic acid etc., so as to perfectly smooth and glossy and including hire charges for polishing machine and power consumption charges etc. The kota stone slabs and other materials to be used shall be got approved by the Executive Engineer concerned before use on work, etc., complete as per standard speicification. |
| 26 | Providing granolithic floor finish in cement concrete 1:2:4 mix using 10-12mmISS metal to 25mm thick including cost and conveyance of all materials to site and all labour charges for mixing, laying, curing etc complete for 10 cum |
| 27 | Paving the flooring with special type of flooring tiles (Cement based Hydraulically pressed Anti skid tiles (20mm thick) in CM 1:3, 20mm thick |
| 28 | Dadooing walls with best approved quality, colour glazed tiles of 150mm x 150mm x 6mm size set in Cement Mortar 1:2 (One Cement and Two sand) 10mm thick |
| 29 | Supplying and fixing in position best approved of BIS quality PVC rain water down fall pipes of 110mm dia., having a pressure of 4 kg. / sq.cm including cost of necessary PVC shoe, PVC bend, cast iron gratings of required diameter and special clamps, brass screws, nails, etc., and fixing of cast iron gratings at junction of parapet and the RCC roof slab |
| 30 | Provision for Shelf Arrangemet in Store,record room using Cuddapah slab |
| 31 | Provision for Galvinised color sheet -Verandah /Sitout |
| 32 | cost and supply of MS Tubular section for Truss work in sitout area |
| 33 | Supplying and fixing of M.S.grill of approved design for grill gate, grill work to doors and windows openings etc., using necessary mild steel etc., complete complying with standard specification. |
| 34 | Weathering course concrete using best quality broken brick jelly of size 20mm in pure slacked lime over the RCC roof slab in th proportion of brick jelly to lime being32:12.5 by the volume and laid over a single layer and consolidated to the required size |
| 35 | Finishing the top of the roof with one course of Machine Pressed Tiles of size 23x23x2 cm of approved quality laid in CEMENT MORTAR 1:3(One cement and three sand) 12 mm thick mixed with water proofing compound conforming to ISS by 2% weight of cement used and the joint pointed neatly to full depth of tiles with the same water proofing compound mixed with cement mortar,red oxide, etc., complete complying with standard specification |
| 36 | Supplying and Applying Two Coats of Wall Putty 3mm Tk over RCC Surface inculding cost and conveyance of all materials to site and all loboure charges etc.,complete |
| 37 | Plastering with CM 1:5,12mm thick.over the cement concrete for floor finish including curing etc., complete complying with standard specifications and as directed by the departmental officers. |
| 38 | Exterior emulsion two coatsover priming coatinculding cost and conveyance of all materials to site and all loboure charges etccomplete |
| 39 | White washing two coats using best freshly burnt shell lime in all the floors including cost of lime, Blue, Fevicol type gum, brushes,scaffolding charges etc., complete complying with standard specifications and as directed by the departmental officers. |
| 40 | Distemperingtwo coatsover priming coatinculding cost and conveyance of all materials to site and all loboure charges etccomplete |
| 41 | Painting two coats over new iron works such as steel doors, windows, ventilators, window bars, balustrades etc., withbest approved best quality of synthetic enamel paint of approved colour over the existing priming coat etc., complete |
| 42 | Supply and fixing of steel door (0.90x2.10m) |
| 43 | Supply and fixing of steel door (0.75x2.10m) |
| 44 | Supply and fixing of steel door (1.10x1.80m) |
| 45 | Supply and fixing of steel door (1.10x1.80m) |
| 46 | Supply and fixing of steel Window (1.20x1.30m) |
| 47 | Supply and fixing of steel Window (0.90x1.30m) |
| 48 | Supply and fixing of steel Window (0.45x1.30m) |
| 49 | Supply and fixing of steel Ventilator 0.90x0.60m |
| 50 | Supply and fixing of steel Ventilator 0.60x0.45m |
| 51 | Supply and Fixing of Collapsible gate including all labour charges |
| 52 | Provision for Eueopean water closet |
| 53 | Provision for Indian Type closet |
| 54 | Provision for wash basin |
| 55 | Provision for pvc nahini trap |
| 56 | Provision for pillar tap |
| 57 | Provision for angle Cock |
| 58 | Provision for angle cock two way |
| 59 | Provision for Grab bar for diabled person in toilet |
| 60 | Provision for PVC tank 1000 lit |
| 61 | Light Point/Fan Point SD25 |
| 62 | Bulk Head fitting with 40w BULB SD 81 |
| 63 | SD88 4ft 40W tube |
| 64 | SD127 TN meter board |
| 65 | SD12 concealed plug point |
| 66 | SD107 Ceiling fan 1200mm |
| 67 | PWD EARTHING |
| 68 | SERVICE CONNECTON |
| 69 | Servicve pipe |
| 70 | SD65 2x 4sqmm |
| 71 | SD66 2x 6 sqmm |
| 72 | Provision for RWH Struture |
| 73 | Provision for Name Board |
| 74 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |