| 1 | Carriage of 8.5 mtr PCC Pole Orai Store to Various Places. |
| 2 | Carriage of 9/11 mtr PCC/STP Pole Orai Store to Various Places. |
| 3 | Carriage of Line Material |
| 4 | Erection of New Pole in place of damage 8.5 meter PCC Single Pole |
| 5 | Erection of New Pole in place of damage 9/11 meter PCC/STP Single Pole |
| 6 | Erection of New Pole in place of damage 8.5 meter PCC double Pole |
| 7 | Erection of New Pole in place of damage 9/11 meter PCC/STP double Pole |
| 8 | Erection of connecting, tightening and sagging damage weasel conductor. |
| 9 | Erection of connecting, tightening and sagging damage Dog conductor. |
| 10 | Erection of connecting, tightening and sagging damage ABC conductor. |
| 11 | Erection of Straightening a bent single pole |
| 12 | Erection of Straightening a bent double pole |
| 13 | Nozzling of stay |
| 14 | Complete work of stay erection |
| 15 | Grouting of Pole |
| 16 | Cutting and Shortening of Tree Branches |
| 17 | Erection of removing 25/63/100 Kva T/F from damage double pole and mounting it on double pole |
| 18 | Petrolling the lines, removing branches from the lines and removing faults |
| 19 | Repair of damaged guarding at road crossing and line crossing |
| 20 | Erection of filling 11 Kv damage cable box |
| 21 | Erection of filling 33 Kv damage cable box |
| 22 | Replacement of damage 11 Kv cable |
| 23 | Replacement of damage 33 Kv cable |
| 24 | Erection of All Earthing work |
| 25 | Carriage of old line material various site to orai store |
| 26 | Re-sagging of lines that have become loose due to damage |
| 27 | Erection of opening material form damage single and double pole |