| 1 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m.as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete Depth of excavation not exceeding 1,500 mm. |
| 2 | Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m.a) In ground floor including roof. |
| 3 | Dismantling R.C. floor, roof, beams etc. including cutting rods and removing rubbish as directed within a lead of 75 m. including stacking of steel bars.a) In ground floor including roof. |
| 4 | Brick soling with picked jhama bricks including preparation of bed as necessary with brick joints properly filled in and packed with powdered earth and including necessary cushion of similar material below the soling (and in between layers when more than one layer is used) completes as per direction Single brick flat soling (thickness 75 mm.) |
| 5 | Brick work with 1st class bricks in cement mortar (1:6) (a) In foundation and plinth. |
| 6 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course,scaffolding/staging where necessary [Excluding cost of chipping over concrete surface] (i) 20 mm thick plaster(1:6)(a) In Ground Floor |
| 7 | Neat cement punning about 1.5mm thick in wall, dado, window sill, floor etc.NOTE:Cement 0.152 cu.m per100 sq.m. |
| 8 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes.Pakur Variety. (a) In Ground Floor including roof. |
| 9 | M.S. structural works in columns, beams etc. with simple rolled structural members (e.g. joists, angle, channel sections conforming to IS: 226, IS: 808 & SP (6)- 1964 connected to one another with bracket, gussets, cleats as per design, direction of Engineer-in charge complete including cutting to requisiteshape and length, fabrication with necessary bolting, metal arc welding conforming to IS: 816- 1969 & IS: 1995 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour required for the work including all incidental chages such as electricity charges, labour insurance charges etc. For structural members of specified sections weighing less than.22.5 Kg./m. |
| 10 | Priming one coat on timber or plastered surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc. (This item is applicable to new work or old work when the original surface has been exposed by removal of old paint.) |
| 11 | Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary : (A) On steel or other metal surface :With other than hi-gloss of approved quality-(a)Two coats (with any shade except white) |
| 12 | Provide and apply shrinkage controlled polymer modified fibre reinforced cementitious repair mortar like Renderoc SP40 of Fosroc or equivalent up to 12 mm thickness by hand or spray application as per specification. |
| 13 | Supply and provide mixing polypropylene fibre like Recon fibre to be mixed with concrete and mortar @ 1.00 kg/cum. or 150 gm per cement bag (50 Kgs) as per manufactures specification. |
| 14 | Surface Dressing of the ground in any kind of soil including removing vegetation inequalities not exceeding 15 cm depth and disposal of the rubbish within a lead upto 75 m as directed. |
| 15 | Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm including watering and ramming etc. layer by layer complete. [Payment to be made on the basis of measurement of finished quantity of work] |