Road Transport and Highways Government Departments Closing in 0 days TDR #48704625

Maintenance Of Road Work T04-Nh-39 To Saikotjang Block: Kangpokpidistrict: Senapati State: Manipur

Issued by Government Departments · Imphal West, Manipur
Tender Value
3.70 Crore
Estimated cost
Bid Submission
18 Jun 2025
0 days left
EMD
7.42 Lakhs
Bank guarantee accepted
Document Fee
20000
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Imphal West → Manipur
EMD Exemption
Not Available
Quantity
Not Available

Project Description

maintenance of road work T04-Nh-39 To Saikotjang Block: Kangpokpidistrict: Senapati State: Manipur

Corrigendum

Sr No Corrigendum Date Corrigendum Type New Submission Date
1 12-Jun-2025 Corrigendum 4 Date 18-Jun-2025
2 06-May-2025 Corrigendum for MN06519 Date 27-May-2025
3 27-May-2025 Corrigendum 2 Date 03-Jun-2025
4 03-Jun-2025 Corrigendum 3 Date 12-Jun-2025

BOQ

Name of Work: T04-NH-39 to Saikotjang Block: KangpokpiDistrict: Senapati State: Manipur
Sl. No. Item Description
1A. PAVEMENT WORKS
2Clearing and Grubbing Road Land.Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201.(I) By Manual Means(B) In area of thorny jungle
3Construction of Embankment with Material Obtained from Borrow PitsConstruction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5Private Land
4Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 m Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3
5Scarifying Existing Bituminous Surface to a Depth of 150 mm by Mechanical MeansScarifying the existing bituminous road surface to a depth of 150 mm and disposal of scarified material with a lift upto 3 m and lead upto 1000 m as per Technical Specification Clause 301.4.
6Construction of Subgrade and Earthen ShouldersConstruction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1.(i) Private Land
7Cement Treated Granular Sub BaseProviding laying and spreading granulated material on a prepared sub-grade pulverising adding the designed quantitity of cement,to the spread granulated material mixing in place with rotavator grading with the mortar grader and compacting with smooth wheel roller 80-100 kN at OMC to achieve the desired unconfined compressive strength and to form a layer of sub- base/base as per Technical Specifications Clauses 404.3 and 410.4.2.
8Considering 55% for Re-use of Existing Materials
945% for fresh Materials
10Cement Treated Granular BaseProviding laying and spreading granulated material on a prepared sub-grade pulverising adding the designed quantitity of cement,to the spread granulated material mixing in place with rotavator grading with the mortar grader and compacting with smooth wheel roller 80-100 kN at OMC to achieve the desired unconfined compressive strength and to form a layer of sub- base/base as per Technical Specifications Clauses 404.3 and 410.4.2.
11Prime Coat :Low porosityProviding and applying primer coat with bitumen emulsion (CSS-1) on prepared surface of granular base/WBM/WMM including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
12Tack CoatProviding and applying tack coat with Bitumen emulsion (RS-1)using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
13Mix Seal SurfacingProviding, laying and rolling of close-graded premix surfacing material of 25 mm thickness composed of 11.2 mm to 0.9 mm (Type-A) or 13.2 mm to 0.9 mm (Type-B) aggregates using penetration grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 8-10 kN static roller and finishing to required level and grades as per TechnicalSpecification Clause 509.By Mechanical Means, Type A, Bitumen (S-90)
14Dismantle of Existing Cross Drainage Structure: 2 no\"s,Slab Culvert:H P Culvert: 3 no\"s
15Dismantling of StructuresDismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.II By Mechanical Means(A) Cement Concrete
16(B) Reinforced cement concrete
17Dismantle of existing structureDismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.Manual Means(B) Cement Concrete
18Dismantling Brick/Tile WorkDismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of brick masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202.(B) Cement mortar
19Removing all types of Hume pipes and stacking within a lead of 1000 m including Earthwork and Dismantling of Masonry Works as per Technical Specification Clause 202.Above 600 mm to 900 mm dia Hume pipe
20B.ROAD FURNITURE WORKS
21Providing and Fixing \"Logo\" of PMGSY ProjectProviding and fixing of typical PMGSY informatory sign board with Logo as per MORD specifications and drawing. Three MS Plates of 1.6 mm thick, top and middle plate duly welded with MS flat iron 25mm x 5m size on back on edges. The lower plate will be welded with MS angle iron frame of 25mm x 25mm x 5mm. The angle iron frame of the lower most plate and flat iron frame of middle plate will be welded to 2 nos. 75mm x 75 mm of 12 SWG sheet tubes posts duly embedded in cement concrete M-15 grade blocks of 450mm x 450mm x 600mm, 600mm below ground level. The top most diamond plate will be welded to middle plate by 47mm x 47mm of 12 SWG steel plate tube. All M.S. will be stove enameled on both sides. Lettering and printing arrows, border etc. will be painted with ready mixed synthetic enamel paint of superior quality in required shade and colour. All sections of framed posts and steel tube will be painted with primer and two coats of epoxy paint as per drawing Clause 1701 and Annexure 1700.1
22Providing and Fixing Title information Board of PMGSY Project (RCC)Providing and fixing of typical PMGSY Citizen information sign board as per MORD specifications and drawing including painting and lettering and fixing in ground 600mm x 600mm x 750mm CCincluding painting two course and lettering.Providing & Fixing Up-gradation Board
23Providing and Fixing Title information Board of PMGSY Project (RCC)Providing and fixing of typical PMGSY Maintenance information sign board as per MORD specifications and drawing including painting and lettering and fixing in ground 600mm x 600mm x 750mm CCincluding painting two course and lettering.
24Reinforced cement concrete M15grade kilometre stone/local stone of standard design as per IRC:8 fixing in position including painting and printing, etc. as per drawing and Technical Specification Clause 1703(i) 5th Kilometre Stone (precast)
25(ii) Ordinary Kilometer stone (precast)
26(iii) 200m Stone (precast)
27Construction of Job pillars as per Fig. 1600.1 (d) and Technical Specification Clause 1602.4
28Painting lines, Dashes, Arrows, etc. on Road in Two Coats on New WorkPainting lines, dashes, arrows, etc. on roads in two coatson new work with ready mixed road marking paint conforming to IS:164 on bituminous/concrete surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control as per drawing and Technical Specification Clause 1702
29Traffic SignsProviding and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3 fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per drawings and Technical Specification Clause 801(ii) 600mm equilateral triangle
30(iii) 600mm circular
31Rumble StripsProvision of 15 nos.rumble strips covered with premix bituminous carpet,15.2 mm high at centre,250mm wide placed at 1m centre to centre at approved location to control speed, marked with white strips of road marking paint.The rate per sqm of premix carpet and road marking may be adopted from Chapters 5&10 respectively for the quantities calculated from approved drawings.
32C. DRAINAGE WORKS
33Construction of unlined surface drain of average cross-sectional area 0.4 sqm in ordinary rock to specified lines, grades, levels and dimensions as per approved design and Technical Specification Clause 307. Excavated material to be used in embankment at site.(B) Mechanical MeansExcavation for Structures
34D.PROTECTION WORKS (Gabian wall 2.70- 90.00m)
35Excavation for StructuresEarthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material.Ordinary rock (not requiring blasting)Upto 3 m depth
36Providing and laying filter material underneath pitching in slopes complete as per drawing and technical specifications Clause 1302
37Providing and laying of boulder apron laid in wire crates with 4 mm dia Black Anealed wire conforming to IS:280 and IS:4826 in 100 mm x 100 mm mesh (woven diagonally) including 10 per cent extra for laps and joints laid with stone boulders weighing not less than 25 kg each as per drawing and technical specifications Clause 1301
381000 mm HUME PIPE (HP Culvert - 3 no\"s)
39Excavation for StructuresEarthwork in excavation for foundation of structures upto 3 m depth as per drawing and technical specification Clause 1104 includding setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.
40Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling course below open foundation of Head walls as per drawings & Technical Specification Clause 1109
41Bedding for PipeType B(First Class) BeddingLaying (First Class) bedding on well compacted sand, moorum or approved granular material as per Clause 1105
42Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single RowProviding and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding (B) 1000 mm dia Pipe
43Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203P.C.C. grade M 20Nominal mix (1:2:4)
44Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204P.C.C. grade M 20Nominal mix (1:2:4)
45Slab culvert 1.5m (2 nos)
46Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitablematerial.
47Ordinary soil upto 3 m depth
48Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 Nominal mix 1:3:6
49Providing concrete for plain / reinforced concrete in foundations complete as perdrawings and technical specifications Clauses 802, 803, 1202 & 1203PCC Grade M 20Nominial mix (1:2:4) (Hand mixed)
50Providing concrete for plain / reinforced concrete in substructure complete as perdrawings and technical specifications Clauses 802, 804, 805, 806, 1202 & 1204PCC Grade M 20Nominial mix (1:2:4)
51Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
52Providing and laying reinforced cement concrete in superstructure as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5RCC Grade M 20(i) Nominal Mix 1 : 2 : 4
53Providing and laying reinforced cement concrete in superstructure as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5RCC Grade M 20(i) Nominal Mix 1 : 2 : 4
54Supplying, fitting and placing TMT bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202
55Supplying, fitting and placing with MS bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202
56Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with smallersize towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical specificationClause 1204.3.8
57Providing and laying curtain walls complete as per drawing and technical specification Clause 1304Cement concrete grade M 10
58Fillling in foundation trenches as per drawing and technical specification Clause 305.3.9 Sand filling
59Filler JointProviding and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply supported spans, covered with sealant complete as per drawing and technical specifications
60Slab culvert 2 m( 1nos)
61Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitablematerial.
62Ordinary soil upto 3 m depth
63Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 Nominal mix 1:3:6
64Providing concrete for plain / reinforced concrete in foundations complete as perdrawings and technical specifications Clauses 802, 803, 1202 & 1203PCC Grade M 20Nominial mix (1:2:4) (Hand mixed)
65Providing concrete for plain / reinforced concrete in substructure complete as perdrawings and technical specifications Clauses 802, 804, 805, 806, 1202 & 1204PCC Grade M 20Nominial mix (1:2:4)
66Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing andtechnical specification Clauses 614, 709, 1204.3.7
67Providing and laying reinforced cement concrete in superstructure as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5RCC Grade M 20(i) Nominal Mix 1 : 2 : 4
68Providing PCC M-20 architectural coping on the top of wing wall, return wall etc. complete as per drawing and technical specification Clauses 615, 710and 1204.3.11
69Supplying, fitting and placing TMT bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202
70Supplying, fitting and placing with MS bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202
71Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with smallersize towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical specificationClause 1204.3.8
72Providing and laying curtain walls complete as per drawing and technical specification Clause 1304Cement concrete grade M 10
73Fillling in foundation trenches as per drawing and technical specification Clause 305.3.9 Sand filling
74Filler JointProviding and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply supported spans, covered with sealant complete as per drawing and technical specifications
75SLAB CULVERT 4m(no)
76Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitablematerial.
77Ordinary soil upto 3 m depth
78Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 Nominal mix 1:3:6 [Hand Mixing]
79Providing concrete for plain / reinforced concrete in foundations complete as perdrawings and technical specifications Clauses 802, 803, 1202 & 1203PCC Grade M 20Nominial mix (1:2:4)
80Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
81Providing and laying reinforced cement concrete in superstructure as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5. R.C.C grade M 20 For design mix RCC M 20
82Providing PCC M-20 architectural coping on the top of wing wall, return wall etc. complete as per drawing and technical specification Clauses 615, 710and 1204.3.11
83Supplying, fitting and placing TMT bar reinforcement (Fe 415) in substructure complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202
84Supplying, fitting, and placing TMT bar reinforcement in superstructure complete as per drawing and technical specifications Clauses 1002, 1010 and 1202
85Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with smallersize towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical specificationClause 1204.3.8
86Providing and laying curtain walls complete as per drawing and technical specification Clause 1304Cement concrete grade M 10
87Filling in foundation trenches as per drawing and technical specification Clause 305.3.9 Sand filling
88Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply supported spans, covered with sealant complete as per drawing and technical specifications
89Routine Maintenance Component for 5 (Five) years after Construction (Not To Be Quoted Yearwise)
901st Year in INR -₹ 406000
912nd Year in INR-₹ 608000
923rd Year in INR -₹ 811000
934th Year in INR -₹ 1014000
945th Year in INR -₹ 1217000

AI Tender Summary

OUR REF NO 48704625
AUTHORITY Government Departments
TENDER VALUE 3.70 Crore
LAST DATE 18-06-2025
Authority
Authority Name State Rural Roads Development Agency
Work Description maintenance of road work T04-Nh-39 To Saikotjang Block: Kangpokpidistrict: Senapati State: Manipur
Basic Detail
Tender No N0 5/16/2024-MSRRDA/E-TENDER/
Bidding Type Tender
Location
City Imphal West
State Manipur
Key Dates
Publish Date 12 Jun 2025
Submission Date 18 Jun 2025
Open Date 19 Jun 2025
Finance
Tender Value 3.70 Crore
Tender Fee 20000
EMD 7.42 Lakhs
Exemption Not Available
Document List
Tendernotice_2.pdf
BOQ_216188.xls
Tendernotice_1.pdf
9616e9aa-33c3-4c6b-8afa-e603b9048da4.html

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Jun 12, 2025
11:30 IST

Tender Published

Tender notice published.

Completed
Jun 18, 2025
18:00 IST

Corrigendum-1 Issued

Clarifications on tender conditions and amendments issued.

Completed
May 27, 2025
18:00 IST

Corrigendum-2 Issued

Clarifications on tender conditions and amendments issued.

Completed
Jun 03, 2025
18:00 IST

Corrigendum-3 Issued

Clarifications on tender conditions and amendments issued.

Completed
Jun 12, 2025
18:00 IST

Corrigendum-4 Issued

Clarifications on tender conditions and amendments issued.

Completed
Jun 18, 2025
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Completed
Jun 19, 2025

Bid Opening Date

Technical bids will be opened and evaluated.

Completed

Tender Documents

Download All (ZIP) ↓
pdf

Tendernotice_2.pdf

xls

BOQ_216188.xls

pdf

Tendernotice_1.pdf

html

9616e9aa-33c3-4c6b-8afa-e603b9048da4.html

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

TenderDetail
Loading tenders