| 1 | Providing ,Laying ,spreading and compacting stone aggregates of 63-45 mm size to water bound macadam specification including spreading in uniform thickness , hand packing ,rolling with Smooth wheel roller 80-100 KN in stages to proper grade and camber ,applying and brooming ,Stonescreening,binding materials to fill up theinterstices of coarse aggregate ,watering and compacting to the required density |
| 2 | Providing, laying, spreading and compacting stone aggregates of 22.4-53 mm sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with Smooth wheel roller 80-100 kn in stages to proper grade and camber, applying and brooming stone dust to fill up the interstices of coarse aggregate, watering and compacting to the required density grading 3 as per Technical Specification Clause 405. |
| 3 | Brick edging on both sides of the road with first class bricks 8 cm wide & 12 cm deep laid with mudmortar including labour & supply of bricks finished to required template and in proper alingment and also including dressing & ramming the excavated earth as directed by the Engineer - in -charge. |
| 4 | Providing and applying primer coat with bitumen emulsion (SS) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70kg/sqm usingmannual means . |
| 5 | Providing and applying tack coat with VG_10 using bitumen distributor at the rate of 0.25 kg per sqm on the preparedsurface cleaned with hydraulic broom .as per direction of E/I |
| 6 | Providinglaying & rolling of open graded premix carpet of 20 mm thickness composed of 13.2mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line ,grade and level to serve as wearing course on a previously prepared base including mixing in a suitable plant,laying and rolling with a three wheel 80-100 KN static roller capacity finished to required level and grades to be followed by seal coat .as per direction of E/I. |
| 7 | Providing and laying seal coat \"C\" Type sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall .as per direction of E/I |
| 8 | Earthwork in cutting or in embankment in ordinarysoil excavationto be in the from of regular pits not exceeding 1/2metre20inch in depth and earth work in embankment to bein 20cm layer including raming and dressing the surface to required the surface to required levels and slopes and also including 1.5 mrtre lift and embankment or to be deposited as spoil bankswith in 30 meter distance as directed by the Engineer in charge. |
| 9 | The routine maintenance of above road work including embankment,patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition during the entire maintenance period which begins from the actual Completion Date and ends after five years.(including cost of material T&P labour but excluding GST) for 1st year maintenance cost |
| 10 | The routine maintenance of above road work including embankment,patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition during the entire maintenance period which begins from the actual Completion Date and ends after five years.(including cost of material T&P labour but excluding GST) for 2nd year maintenance cost |
| 11 | The routine maintenance of above road work including embankment,patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition during the entire maintenance period which begins from the actual Completion Date and ends after five years.(including cost of material T&P labour but excluding GST) for 3rd year maintenance cost |
| 12 | The routine maintenance of above road work including embankment,patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition during the entire maintenance period which begins from the actual Completion Date and ends after five years.(including cost of material T&P labour but excluding GST) for 4th year maintenance cost |
| 13 | The routine maintenance of above road work including embankment,patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition during the entire maintenance period which begins from the actual Completion Date and ends after five years.(including cost of material T&P labour but excluding GST) for 5th year maintenance cost |
| 14 | Total cost of work (Item No. 1 to 8) without Maintenance cost |