| 1 | Construction of 3m Span Culvert at Karisalkulam Village in Sivanthipatti Panchayat |
| 2 | Earthwork excavation in all clauses of Soils and Subsoils except hard rock requiring blasting including Shoring, Strutting and dressing the excavation upto sill level to maintain the foundation width as per the specifications SS 20B etc., complete |
| 3 | Cement concrete 1:4:8 mix using 40mm ISS HBGS metal laid in layers not more than 15cm thick inculding cost and coveyance of all materials to site, labour charges for mixing ,laying,compacting and curing etc complete., For Foundation - Base Concrete |
| 4 | Supplying and erection Centering for sides and soffits inculding necessary supports and structing for plain surfaces such as RCC Slab, Lintel, Beam, Column, Sunshade including cost and coveyance of all materials to site and all other incidental charges etc complete., |
| 5 | Below Sill Level |
| 6 | Above Sill Level |
| 7 | Cement concrete 1:3:6 mix using 40mm ISS HBGS metal laid in layers not more than 15cm thick inculding cost and coveyance of all materials to site, labour charges for mixing ,laying,compacting and curing etc complete.,Concrete Masonry - Abutment & Return wall - Below Sill level |
| 8 | Plain Cement concrete 1:2:4 mix using 20mm ISS HBGS metal laid in layers not more than 15cm thick inculding cost and coveyance of all materials to site, labour charges for mixing ,laying,compacting and curing etc complete.,Concrete Masonry -Back wall - Above Sill level |
| 9 | Reinforced cement concrete 1:1.5:3 mix using 20 mm ISS HBG metal inculding cost and coveyance of allmaterials to site, (excluding steel fabrication charges) labour charges for mixing ,laying,compacting and curing and other incidental charges as per standard specifications etc complete., |
| 10 | Supplying and fabrication of Steel Fe 415 grade required for all RCC item of works involved including fabrication and labour charges for Cutting, bending, tying, placing in position, includes overlaping length wherever required etc., complete |
| 11 | Supply and filling of Red Gravel from approved quarry for Base layer in layers not more than 15mm thick, including cost of material, labour charges for filling, levelling, sectioning and compacting etc., complete as directed by officers. |
| 12 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |