| 1 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete.(a) Depth of excavation not exceeding 1,500 mm.Ref. Page - 1, Item 02; PWD SOR VOL-I w.e.f. 1.11.2017 |
| 2 | Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work)(a) With earth obtained from excavation of foundation.Ref. Page - 1, Item 03; PWD SOR VOL-I w.e.f. 1.11.20171/5th of Excavation |
| 3 | Earth work in filling in foundation trenches or plinth with silver sand, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work)(B) Do-by fine sandRef. Page - 1, Item 03; PWD SOR VOL-I w.e.f. 1.11.2017 |
| 4 | Supplying and laying Polythene Sheet (150gm / Sq.M) over damp proof course or below flooring or roof terracing or in foundation or in foundation trenches. Ref. Page -47, Item -3,PWD SOR Vol-I w. e. f. 1.11.2017 |
| 5 | Cement concrete with graded jhama khoa (30 mm size) excluding shutteringIn ground floor and foundation. (a) 1:3:6 proportionRef. Page - 23, Item 01,a;PWD SOR VOL-I w.e.f. 1.11.2017 |
| 6 | Brick work with 1st class bricks in cement mortar (1:6)(a)foundation and plinthRef. Page - 15, Item 8,a;PWD SOR VOL-I w.e.f. 1.11.2017 |
| 7 | 125 mm. thick brick work with 1st class bricks in cement mortar (1:4)In ground floor.Ref. Page - 16, Item 16;PWD SOR VOL-I w.e.f. 1.11.2017 |
| 8 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes.(i) Pakur VarietyRef. Page - 26, Item 10,a; PWD SOR VOL-I w.e.f. 1.11.2017 |
| 9 | Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor)(a) 25 mm to 30 mm thick wooden shuttering as per decision & direction ofEngineer-In-Charge.Ref. Page - 42, Item 36,a; PWD SOR VOL-I w.e.f. 1.11.2017 |
| 10 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction.(a) For works in foundation, basement and upto roof of ground floor/upto 4 m(i) Tor steel/Mild SteelI.II. Other thanSAIL/ TATA/RINLRef. Page - 43, Item 40,a,ii; PWD SOR VOL-I w.e.f. 1.11.2017 |
| 11 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding / staging where necessary (Ground floor).Ref. Page - 189, Item 1PWD SOR VOL-I w.e.f. 1.11.2017 |
| 12 | Neat cement punning about 1.5mm thick in wall, dado, windowsill, floor etc.NOTE:Cement 0.152 cu.m per100 sq.mrRef. Page -192, Item -15 ,PWD (W.B.), Schedule of Rates (Building)- 2017 |
| 13 | Supplying, Fitting & Fixing Factory made P.V.C. door frame of size 50 mmx47 mm with a wall thickness of 5 mm, made out of extruded 5 mm, PVC sheet miter cut at two corners and joined with two nos of 1.5 mm long brackets of 15 mm x15 mm M.S. square tube. The two vertical door profiles are to be reinforced with 19 mmx 19 mm M.S. Square tube of 19 gauge, weather seal to be provided through out the frame. The door frame shall be fixed with the wall using 65/100 mm long M.S. Screws through the frame by using P.V.C fasteners. A minimum of 4 Nos of screws to be provided for each vertical member and minimum 2 Nos for horizontal member etc. complete as per Manufacturer‟s specification and direction of Engineer-in-Charge.Ref. Page - 116, Item 7 PWD SOR VOL-I w.e.f. 1.11.2017 |
| 14 | (a) M.S.or W.I. Ornamental grill of approved design jointscontinuously welded with M.S, W.I. Flats and bars of windows,railing etc. fitted and fixed with necessary screws and lugs in groundfloor.(Add extra @ 1% for each addl. floor upto 4th floor and @ 1.25%for each addl. floor above 4th floor)(i) Grill weighing above 10 Kg./sq.mtr and up to 16 Kg./sq. mtr.Ref. Page - 104, Item 13,i; PWD SOR VOL-I w.e.f. 1.11.2017 |
| 15 | (a) Priming one coat on steel or other metal surface withsynthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc.Ref. Page - 200, Item 1PWD SOR VOL-I w.e.f. 1.11.2017 |
| 16 | (A) Painting with best quality synthetic enamelpaint of approved makeand brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary :(b) On steel or other metal surface : With super gloss (hi-gloss) -(iv) Two coats (with any shade except white)Ref. Page - 200, Item 2(b)PWD SOR VOL-I w.e.f. 1.11.2017 |
| 17 | Applying Interior grade Acrylic Primer of approved quality and brand on plastered or cencrete surface old or new surface to receive Distemper/ Acrylic emulsion paint including scraping and preparing the surface throughly, complete as per manufacturer\"s specification and as per direction of the EIC. (In Ground Floor)(a) One Coati) Water based interior grade Acrylic PrimerRef. Page - 195, Item 7,a,i; PWD SOR VOL-I w.e.f. 1.11.2017 |
| 18 | Applying Acrylic Emulsion Paint of approved make and brand on walls and ceiling including sand papering in intermediate coats including putty (to be done under specific instruction of Superintending Engineer) :(Two coats)i) Standard QualityRef. Page - 201, Item 04; PWD SOR VOL-I w.e.f. 1.11.2017 |
| 19 | Applying Exterior grade Acrylic primer of approved quality and brand on plastered or cencrete surface old or new surface to receive decorative textured (matt finish) or smooth finish acrylic exterior emulsion paint including scraping and preparing the surface throughly, complete as per manufacturer\"s specification and as per direction of the EIC.In Ground Floor:(a) One CoatRef. Page - 196, Item 8,a; PWD SOR VOL-I w.e.f. 1.11.2017 |
| 20 | Protective and Decorative Acrylic exterior emulsion paint of approved quality, as per manufacturer\"s specification and as per direction of Engineer-in-Charge to be applied over acrylic primer as required. The rate includes cost of material, labour, scaffolding and all incidental charges but excluding the cost of primer.In Ground floor (Two Coat)a) Normal Acrylic EmulsionRef. Page - 197, Item 17,a; PWD SOR VOL-I w.e.f. 1.11.2017 |
| 21 | Add 18 % GST |
| 22 | Add 1 % CESS |