| 1 | Dismantling the existing lime concrete over the cut stone roofing with standard specifications. |
| 2 | Dismantling the existing Brick / stone masonry in lime mortar walls under 3m highwith standard specifications. |
| 3 | Labour charges for Removal the Existing cut stone Structureincluding, Numberingall labour charges,hirefor all tools and plants for employed, scaffolding charges handling charges hoisting and stacking them in the places shown by the Departmental Officersetc complete.,as per standard specification. |
| 4 | Kalvari, Adhistanam, Upabeedam & Pavukkal |
| 5 | Pillar, Bothiyal & Uthiram |
| 6 | Earthwork excavation for foundation in all soils except hard rock requiring blasting to a full depth with initial lead of 10 m and lift of 2m etc., complete |
| 7 | Supplying and filling in foundation in basement with filling sand in layars of 148mm thickne well watered rammed and consolidated complyiny with relevant std specification including cost of supplying filling sand. |
| 8 | Cement concrete 1:5:10 (One of cement five of sand and ten of HBG jelly )for foundation using 40mm gauge HBG jelly inclusive of shoring strutting and baling out water where ever necessary ramming curing etc.,complete in respects complying with relevant Std, Specification. |
| 9 | Providing and laying in position, Standardised Concrete Mix M-20 Grade in accordance with IS:456-2000, using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement content of 325 kg/mᶾ and maximum water cement ratio of 0.55, including admixture (plasticiser / super plasticiser) in recommended proportions as per IS:9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability with about (5 cu.m.) 7730 kg. of 20mm machine crushed stone jelly and with about (3.3 cu.m.) 5156 kg. of 10-12mm machine crushed stone jelly and with about (4.79 cu.m.) 7670 kg. of sand, but excluding cost of reinforcement grill and fabricating charges, centering and shuttering and also including laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor/ roof slabs wherever necessary without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers.The coarse and fine aggregates to be used should comply with the requirements of IS Standards.(No separate payment will be made by the Department for the excess usage of materials). |
| 10 | Centering for sides and soffits of Rcc slabs of plain surface like lintels, beams, etc., including strutting 3M hight using MS sheets of size 90cmx60cm and BG 10 stiffened with MS angles of size 25x25x3mm laid over silver oak (C.W) joists of size 10x6.5cm (spaced at about 90cm c/c) and supported by casurina prop. 10cm to 13cm dia ( spaced of 75cm c/c) complying with standard specification and directed by the Dept, Officers. |
| 11 | Supplying fabrication and placing in position of MS or RTS bars for all RCC works including cutting bending and placing in position and also the cost of binding wire also etc., complete. |
| 12 | Random Rubble masonry work in LM 1:2Using selected stones and bond stones in foundation and basement including dewatering wherever necessary proper setting, curing etc., complete in all respectscomplying with relevant standard Specifications. |
| 13 | Supplying of cut stone for walls, Pillar , Pavukkal , Uthiram , Bodiyal and all works excluding labour charges but including cost and conveyance loding and unloding etc. complete with standard specification |
| 14 | A.Upto 5\"0\" |
| 15 | B.Above 5\"0\" upto 10\"0\" |
| 16 | Labour charges for new stone work for dressing and fixing of required faces consisting of athistanam, Pathavargam, Prasthalam etc, neatly finished and fixing in position with LM 1:1.5excluding cost and conveyance of stone from quarry but including all labour charges for tools and plants for dressing charcoal scaffolding charges handling charges hoisting and fixing in position etc complete., |
| 17 | A.Cithravanam |
| 18 | B. Padmam |
| 19 | C.Kandam |
| 20 | D.Kabothagam |
| 21 | E.Padmam Jagathi |
| 22 | F. Kumuthagam |
| 23 | G.Pattiyal |
| 24 | H.Vedhigai |
| 25 | I. Sthamabam Patham |
| 26 | J.Thadi, Kudam & Palagai |
| 27 | K.Veerakanda Pothiyal |
| 28 | L.Uthiram Kampu eluthagam |
| 29 | M.Kabothagam |
| 30 | N.Viyalavari |
| 31 | O.Pavukkal |
| 32 | P.Nilaikkal |
| 33 | Q.Ulvari |
| 34 | R.Kodungai ( Top & Bottom ) |
| 35 | S.Pillar (Thoon) |
| 36 | Labour charges for Refixing the cut stone excluding cost and conveyance of stone from quarry but including all labour charges for tools and plants for dressing charcoal scaffolding charges handling charges hoisting and fixing in position etc complete. |
| 37 | Kalvari, Adhistanam, Upabeedam & Pavukkal |
| 38 | Pillar, Bothiyal & Uthiram |
| 39 | Brick Jelly Lime Concrete 1:2:5 using 40mm brick jelly in Lime Mortar 1:2 etc, complete with standard specifications. |
| 40 | Brick work in LM 1:2 using country brick of size 83/4\"x41/4\"x2 3/4\" including cost and conveyance of all materials and labour charges and all other incidental charges etc completc complying with standard specification. |
| 41 | Providing water jetwash and appropriate methodology torestore the originnalities of the exisiting natural stone structure.etc complete.,as per standard specification. |
| 42 | Pointing the cut stone joints with Lime mortar1:1.5 20mm thick including cost of special tiles such brush and watering, curing etc complete, as per standard specifications. |
| 43 | Scaffolding charges for Vimanans andgopurams with casurina posts coconut or plamtrees wherever necessaryfor main, form work and providing with coconut keeth coverings, providing ladder arrangements, country wood pland for working, inpection etc, complete hire charges only for erection, maintainance and removing the same on completion of the work. |
| 44 | Up to 15\"ht |
| 45 | Up to 25\"ht |
| 46 | Brick masonry lime mortar 1:1.5 using Country bricks including all varivargams, moulds, sthambams, mukapathrams, koodu, nasi and all ornamental brick work complete,all pancharams, agarais, karnakoodus, etc., forming corewalls of Rajagopuram/ Vimanams complete including cost and conveyance of all materials including cement, all the labour charges including marking pathies shaping of the bricks, lifting of all the materials to requiredheights, curing and all extra for working in heights etc., complete. |
| 47 | A.Vimanam |
| 48 | Providing Vargapoochu over the corewalls of Vimanams / Gopurams, with lime mortar 1:1.5 complete including shaping the mukhapathram, mahanasi, Koodu all ornamentals works to proper shape by embedding broken bricks of shaped/chiseled bricks, rough-plasteringwith lime mortar 1:1.5 and finishing with final ornamental plastering and nayam theervani including cost and conveyance of all materials, labour therefore, lifting of materials, all working in heights, curing with water etc, complete including all extra for folding and including clearing from the vimanams/gopurams. |
| 49 | A.Vimanam -up to 15\" ht |
| 50 | B.Vimanam-up to 25\" ht |
| 51 | Painting with multicolour (Panchavarnam)good exterior emulsion paintcomplete for the Vinamans/Gopurams, inculding costand conveyence of all materials, lobour charges inculdinf Artist painter, working in heights, lifting of material, cost of brushes etc,complete-which including all extra for foldings |
| 52 | A.Vimanam -up to 15\" ht |
| 53 | B.Vimanam -up to 25\" ht |
| 54 | Flooring with cut stone slab of size 600mmX600mm and other sizes suitable for site requirement not less than 100mm thick with machine cut edges and top surface dressed as directed by the departmental officers including cost and conveyance of materials to site and lobour charges for paving and Pointing WithLime Mortor1:1.5 etc complete. |
| 55 | Innear |
| 56 | Outter |
| 57 | Providing new sudhai vigrahams in the vimanams and Rajagopurams with galvanised iron rod reinforcement of suitable dia with binding wires wherever necessary, shaping the core with broken bricks set in lime mortar 1:1.5 finishing the same with lime mortar 1:1.5bringing to the correct shape (Lakshana) in conformift with silpa sastra inclusive of special ornaments, wiapons, peedam etc., complete and providing C.M. Nayam theervai wherever necessary. inclusive of cost and conveyance of all materials, such as cement broken bricks, and G.I. rods.binding wire all labour for working in heights, curing lifiting of materials etc., complete including cement painting 2 coats over a primary coat (one vigraham is accountable with one head, 4 hands with weapons, ornamental costumes etc., as per prathima lakshans, Vigraham height is measurable from the crown top to the bottom of foot only If peetam is pt\rovided the rate with peetam may be adopted as datailed hereunder). |
| 58 | Sudhai size above1\" 0\" upto 2\" 6\" |
| 59 | Sudhai size above2\" 6\" upto 3\" 6\" |
| 60 | Weathering course concrete with broken jelly 20mm size and pure slaked lime over RCC roof slab, the proportion being 32:12.5 for required depth of 80mm for giving required slope and thickness of roof on required, well beaten with wooden beater etc, complete with standard specifications. |
| 61 | Finishing the top of roof with one course of machine pressed tiles 20cmx 20cmx20mm of approved quality laid in Lime mortar1:1.5,12mm thick mixed with water proofing compound 2% by weight of cement usedetc, complete with standard specifications. |
| 62 | Plastering with Lime Mortor1:1.5,12mm thick including cost and conveyance of all materials and all labour charges, curing etc,complete complying with standard specifications. |
| 63 | Painting two coat with approved water based Exterior Emulsion over the cement plastered wall surface, ceiling and other new surface including clearing preparing the surface curingin all floors including brushes etc., complete as per specification |
| 64 | Supplying & fixing Teak wood temple type door including all materials, labour charges for manufacturing and fixing in position including all furniture fittings etc complete with std. Specifications |
| 65 | Below 7\"ht |
| 66 | Best varnishtwo coats for wood works etc, complete complying with standard specifications. |
| 67 | Sub total |
| 68 | GST 18% |