| 1 | Providing, lowering, laying and jointing in trenches, standard lengths HDPEISI marked Pipes as per IS-4984: 1995 (amended upto date)with necessary jointing material like mechanical connectors, i.e. thread/ insert joint/ quick release coupler joint/ compression fitting joint or flanged joint and specials jointing pipe by butt fusion/ electro fusion welding method, including all taxes , transportation and freight charges, inspection charges, loading/ unloading charges, stacking of pipes, including cost of labour and material, specials (Tee, bend etc.), satisfactory hydraulic testing, disinfection etc. complete as per technical specifications and direction of Engineer-in-charge of following class and diameter. (excluding earth work) Note : Providing and fixing of all requisite specials as per drawing, design and layout are inclusive in RM measurement of the item and shall not be paid separately.Supply up to 110 mm dia. in coil & above 110 mm dia straight length in 6 M. |
| 2 | HDPE PE-80PN-6 |
| 3 | 75 mm |
| 4 | 90mm |
| 5 | 110mm |
| 6 | Providing, lowering, laying and jointing in trenches, standard lengths HDPEISI marked Pipes as per IS-4984: 1995 (amended up to date)with necessary jointing material like mechanical connectors, i.e. thread/ insert joint/ quick release coupler joint/ compression fitting joint or flanged joint and specials jointing pipe by butt fusion/ electro fusion welding method, including all taxes , transportation and freight charges, inspection charges, loading/ unloading charges, stacking of pipes, including cost of labour and material, specials (Tee, bend etc.), satisfactory hydraulic testing, disinfection, commissioning etc. complete as per technical specifications and direction of Engineer-in-charge of following class and diameter. (excluding earth work). Note : Providing and fixing of all requisite specials as per drawing, design and layout are inclusive in RM measurement of the item and shall not be paid separately.Supply of pipe shall be in straight length in 6/12 M. |
| 7 | HDPE PE-80PN-6 |
| 8 | 125mm |
| 9 | 140mm |
| 10 | Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in trenches of required width and gradient for laying and jointing of pipe line including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5 Mtr. including taking out the excavated soil, and then returning the soil as required in layers not exceeding 20cm in depth including consolidating each deposited layer by ramming, watering etc. and disposal of surplus excavated soil as directed within a lead of 50 Mtr. including required all safety provisions etc.: |
| 11 | All kind of Soil |
| 12 | Ordinary rock |
| 13 | Hard rock (requiring blasting) |
| 14 | Hard rock(blasting prohibited) |
| 15 | Dismantling of cement concrete pavement for pipe line line and chambers by mechanical means using pneumatic tools, cutting the peripheral edge by CC cutter, breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials up to a lead of 1000 meters. Measurement for dismantled trench to be madeas per standard trench width specified in tender document and no extra payment shall be made be made for trench width more than specified, re-handling of material/earth to complete the tasks as per technical specification and scope of work. |
| 16 | Providing and laying in position cement concrete in specified grade over prepared base course complete including finishing, curing, all material, labour, machinery, lighting, guarding for road restoration work in trenches of pipe line and chamber work. Measurement for CC work to be madeas per standard trench width specified in tender document and no extra payment shall be made be made for trench width more than specified,complete work as per technical specification and scope of work. |
| 17 | M20 grade Nominal Mix1: 1.5: 3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20mm nominal size). |
| 18 | Plain cement concrete pavementof M-30 Grade |
| 19 | Providing,lowering, aligning,fixingin positionin pipeline,CID/FSluicevalvesstraight and pocket less body passage of approved make of following Pressure rating & dia complete, confirfing to IS:14846 (amended up to date) and of following specifications: Body, Bonnet, Wedge, Gland, Thrust Plate, Cap & Hand wheel of Grey cast iron of IS:210/ FG200Stem - SS 304 ,Body Seat ring, Wedge facing ring & Bushes - LTB2/ SS, Face to face dimensions as per IS 14846/2000 (amended up to date) ,Epoxy ( Non-Toxic- suitable for drinking water) applied inside and outside,Flanges Drilled as per IS 1538. Nut-Bolt confirming to IS:1363 and IS: 1367/ CS/ galvanised steelInsersion rubber of black EPDM 6mm thick . Sluice valves including all jointing & jointing material, labour, testing and commissioning along with pipe line as per Technical Specifications and as per direction of Engineer-in-charge. Note: Rates are exclusive of tail piece/ dismantling joints and earth work. |
| 20 | Manually operated class PN 1.0 |
| 21 | 80mm |
| 22 | 100mm |
| 23 | 125mm |
| 24 | Work of Inter Connection in AC/PVC/HDPE pipe line up to 1.5 mtr depth by digging out suitable size of pit at site of work including dewatering and providing adequate safety arrangement at site, cutting of existing pipeline, jointing of Tee (complete) and other specials to make inter connection repair leak proof and then refilling ofexcavated trench / Pit / Road shall be done Properly I.e. after a layer of 20 cm. with proper watering and ramming in layers , for entire job contractor will use his own T&P & labour and will arrange transportation of material required from Store.(Material such as Tee/ Tee Clamp/rubber sheet/ CID joints required for inter connection shall be provided by the department free of cost). |
| 25 | In all type Soil |
| 26 | 80 mm to 110 mm |
| 27 | 125 mm to 165 mm |
| 28 | Work of Inter Connection in CI/DI/MS pipe line up to 1.5 mtr depth by digging out suitable size of pit at site of work including dewatering and providing adequate safety arrangement at site, cutting of existing pipeline, jointing of Tee (complete) and other specials to make inter connection repair leak proof and then refilling ofexcavated trench / Pit / Road shall be done Properly I.e. after a layer of 20 cm. with proper watering and ramming in layers , for entire job contractor will use his own T&P & labour and will arrange transportation of material required from Store. (Material such as Tee/ Tee Clamp/rubber sheet/ CID joints required for inter connection shall be provided by the department free of cost). |
| 29 | In all type Soil |
| 30 | 80 mm to 100 mm |
| 31 | 125 mm to 150 mm |