| 1 | Clearing compound premises of shurbs, plants, jungles etc. by cutting and removing as directed (Specific permission of Engineer-in-Charge prior to execution will be necessary). |
| 2 | Dismantling of StructuresDismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specifications Clause 202 for Rural Roads of MORD.II. By mechanical means :(a)Cement Concrete: |
| 3 | Earthwork in excavation of foundation trenches of drains, in all sorts of soil (including mixed soil but excluding late-rite or sand stone) including removing, spreading or stacking the spoils within a lead of 75 m, as directed. The item includes necessary trimming the sides of trenches, leveling, dressing and ramming the bottom, bailing out water etc. as required complete.(a) Depth of excavation not exceeding 1,500 mm. |
| 4 | Supplying, spreading and compacting fine Sand to required thickness, in layers not exceeding 150 mm to proper gradient and camber, inundating each layer by water and packing and ramming layer by layer to achieve desired compaction, including lighting, guarding, barricading and making adequate earthen bundh where necessary, curing with water as per direction, mending cracks and depressions by ramming wherever necessary. |
| 5 | Supplying, spreading and consolidating Stone Dust to a depth of 100 mm and above at desired density and C.B.R. as per Specification with power roller to proper gradient and camber including watering as necessary, and lighting, guarding, barricading and making adequate earthen bundh where necessary to protect the edges and curing with water for 2 to 3 days, mending cracks and depressions by rolling where necessary including all incidental charges of roller, cost of fuel & lubricants complete as per specification. |
| 6 | Single brick flat soling of picked jhama bricks including ramming and dressing bed to proper level, and filling joints with local sand |
| 7 | \"Supplying and laying Polythene Sheet (150gm / sq.m.) over damp proof course or below flooring or roof terracing or in foundation or in foundation trenches. |
| 8 | Hire & labour charges for shuttering with centering and necessary staging up to 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs. Beams, columns , lintels curved or straight including fitting, fixing and striking out after completion of works (up to roof of ground floor) (a) 25 mm to 30 mm thick shuttering without staging in foundation |
| 9 | Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement,if any, in ground floor as per relevant IS codes.a) Pakur Variety |
| 10 | Supplying and laying in the specified pattern of Interlocking Concrete Block Pavement (ICBP) with concrete blocks (with concrete grade as specified as per Table 1 of IS 15658:2006) manufactured in steel mould clamped to a vibrating table by hydraulic pressure(as per cl no. 6.30 of IRC : SP: 63(2018) from BIS license manufacturer with spacer nib (small producing profiles on the vertical face of a paver block used as a device for keeping minimum joint gap in between the paving blocks as per cl. no.3.26 of IS:156358) and of specified size and shape with aspect ratio (The ratio of length to thickness of a paver block as per cl. no. 3.3 of IS:15658 ) as per table 2 of IS:15658 with flexural strength/breaking load as per annexure G of IS: 15658 on the prepared base course of specified CBR as per table 1 of IRC SP63 (2018)or else as mentioned in design and drawing with a cushion of compacted bedding sand of 25-35mm thick (grading of the bedding sand as per clause6.5.1 of IRC:SP-63) and filling up the gaps in between paver blocks with joint filling sand (the grading of the joint filling sand will be as per clause 6.5.2 of I(RC SP 63) and completing the edges with cut blocks as per cl no 8.7 of IRC SP-63(2018) with proper confinement of bedding and joint filling sand compaction, levelling and filling up of the edge gap.60 mm thick. (i) Grey |
| 11 | Supplying& laying 20 mm designer chequered tiles of any shade and of approved quality as per IS: 1237: 1980 laid in patterns as directed in pavement, footpath including necessary underlay 25 mm thick average cement mortar (1:3) complete in all respect with all labour and materials [using cement slurry @ 4.4 kg/Sq.m at back side of tiles. Cement of mortar & slurry will be supplied by the Department. Border concrete if necessary to be paid separately]. |
| 12 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction.(a) For works in foundation, basement and up to roof of ground floor/up to 4 m(i) Tor steel/Mild SteelI. SAIL/ TATA/RINL |
| 13 | \"Providing and laying Pre-cast cement concrete road channel of size 200 x 250 x 100 of concrete M-25 Grade without reinforcement, setting in position at size after preparing the bed and sloper by 50 mm. stone dust as per specification & direction of EIC including filling of joints with 10 mm. thick cement mortar (1:4) and curing the mortar joints for at least 3 days including cost & carriage of all materials complete. |
| 14 | Providing and fixing at or near ground level precast cement concrete in kerbs (size: 410 mm x 310 mm x width 150 mm at bottom with circular nosing at top) (Nano kerb) of cement concreat M25 Grade without reinforcement, fixing as per approved pattern and setting in position at site after preparing the bed grade and slopes by laying Cement concrete with jhama khoa (1:4:8) as per specification and direction of Engineer-in- Charge including filling of joints with 10 mm thick cement morter (3:1) and back filling the vertical piece properly with earth duly compacted and curing the morter joints for atleast 3 days including cost and carriage of all materials complete. |
| 15 | Supplying, fitting and fixing in position reinforced cement polymer concrete manhole /gully pit cover with matching frame. As per I.S- 12592(M.D)(i) 25 MT load bearing capacity round manhole cover provided with two lifter hooks fitted with matching frame of sizecover: 680 mm X 90 mm,Frame: 800 mm X 165 mm,opening: 500mm,Weight: 196 kg (approx) |
| 16 | Supplying, fitting and fixing PVC pipes of approved make of Schedule 80 (medium duty) conforming to ASTMD - 1785 and threaded to match with GI Pipes as per IS : 1239 (Part - I). with all necessary accessories, specials viz. socket, bend, tee, union, cross, elbo, nipple, longscrew,reducing socket, reducing tee, short piece etc. fitted with holder bats clamps, including cutting pipes, making threads,fitting, fixing etc. complete in all respect including cost of all necessary fittings as required,jointing materials and two coats of painting with approved paint in any position above ground. (Payment will be made on the centre line measurements of total pipe line including all specials. No separate payment will be made for accesories, specials. Payment for painting will be made seperately)(i) 100 mm dia |
| 17 | Removal ofearth from the working site and disposal of the same beyond the compound , in conformity with the Municipal / Corporation rules for such disposal , loading into truck and cleaning the site in all respect as per direction of Engineer in charge. |
| 18 | G.S.T. @ 18% on Rs. 1862978.24 |
| 19 | Cess @ 1% on Rs. 1862978.24NOTE : 1) RATE TO BE QUOTED UPTO TWO DIGITS AFTER DECIMAL POINT. QUOTED RATE MAY BE ROUNDED UP TO TWO DIGITS AFTER DECIMAL POINT IF ANY BIDDER QUOTES MORE THAN TWO DIGITS AFTER DECIMAL POINT WHILE PREPARING COMPARATIVE STATEMENT. |