| 1 | Earth work excavation for foundation and depositing on bank with in the initial lead of 10m and a lift of 2m in hard stiff clay, stiff block cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders etc. complete. complying with std. specifications.SS 20 B |
| 2 | Plain Cement Concrete 1:4:8 Mix (one part cement, Four part sand and Eight part of aggregate) using 40mm size ISS HBG metal machine crushed from approved quarry including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete. Complying with std. specifications.Supplying and erecting centering for sides and soffits including supports and struttingupto 3.00m heightfor plane surface such as RCC Slab, Rectangular Beams, Tee (or) ELL Beams, Lintel Bed Block, Slabs, Landing Slabs, Beams Canopy, Side Slab (or) Square (or) Round columns etc., as detailed below with all cross branching using M.S. Sheets of size 80cm x 60cm and B.G. 10 stiffened with welded M.S. Angles of size 25 x 25 x 3mm for boarding laid over silver oak or country wood joints of 10cm to 30cm to dia spaced at 75cm c/c etc., complete complying with standard specifications as directed by departmental officers etc., complete. |
| 3 | Below 1m |
| 4 | Slab |
| 5 | Plain Cement Concrete 1:2:4 Mix (one part cement, two part sand and four part of aggregate) using 20mm size ISS HBG metal machine crushed from approved quarry including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete. Complying with std. specifications.complete. |
| 6 | Finishing the top of flooring with granolithic floor finish in cement concrete 1:2:4 mix using 10-12mm ISS metal to 25mm thick including cost and conveyance of all materials to site and all labour charges for mixing, laying, curing etc complete |
| 7 | Supplying fabricating and placing in position of steel rods using TMT. or Ribbed Tor Steel including cost of binding wire, cost of labour charges for fabrication and placing in positionetc. Complete. Complying with std. specifications. |
| 8 | Reinforced Cement Concrete 1:1½:3 Mix (One part cement, one and half part sand and three part of aggregate)using 20mm size ISS HBG metal machine crushed from approved quarry including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing but excluding cost of reinforcement etc.Complete with std.Specifications. |
| 9 | Providing and laying Well Gravel to the specified thick including cost and conveyance ofWellgravel from approved quarry and stocking the same at road side to Departmental gauge for premeasurement as directed by the Departmental Officers including labour charges for spreading in layers not exceeding 75 mm thick (or) as specified by the departmental officers, leveling, sectioning etc., and all other charges for tools and plants employed for the work and all other incidental charges such as barricading and providing danger lights etc., complete as per standard specification. as per clause 301 & 305 of MORTH |
| 10 | Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadamspecification including premixing the materials with water at OMC in mechanical mix plant carriage of mixed material by tipper to site laying in uniform layers with paver sin Sub Base/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Rev-5 |
| 11 | Providing and laying Prime Coat over WMM surface using 7Kg of Emulsion Bitumen (SS1) per 10sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,complete as per Clause 502 of MORTH Rev-5 |
| 12 | Providing and laying Tack Coat over WMM surface (treated with primer) using 2.50Kg of Bitumen Emulsion (RS1) per 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5 |
| 13 | Providing and laying Premix Carpet with Seal Coat Type \"A\" for 20mm thickness using 0.18 cum of 13.20 mm IRC size HBG metal and 0.09 cum of 11.20 mm IRCsize HBG metal with 14.60 kg of the 60/70 Graded Bulk Bitumen for premixing 10 Sq.m ofPremix Carpet and 0.09 cum of6.70 mm IRC size HBG metal with 9.80 Kg of 60/70 Graded Bulk Bitumen for Seal Coat Type \"A\" per 10 sq.m including cost and conveyance of materials to the work site and stacking heating the bitumen in bitumen boiler heating the aggregates and mixing the with bitumen in mini not mix plant to premix carpet only rolling by 80 – 100 KN power roller for premix carper application of bitumen for seal coat over premix carpet etc., including hire charges for spreading seal coat separately over premix carpet etc., including hire charges and fuel charges and fuel chargers for Mini Hot Mix Plant bitumen boiler, power roller and all other tools and plant employed etc., complete. |