| 1 | Earthwork in excavation for foundation of structures upto 3 m depth as per drawing and technical specification Clause 1104 for Rural Roads of MORD including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. |
| 2 | Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. |
| 3 | a) M-15 GradeProviding and laying Design Mix concrete for Plain / Reinforced Cement Concrete in any part of foundation of bridge /culvert with graded stone chips of appropriate nominal sizes , including screening and cleaning of coarse aggregates, fine aggregate (sand) conforming to proper grading zone , both of approved quality and cement , as necessary , cost of curing with water ,including cost and carriage of all materials and includingpreparation of design mix, approval of the same by the Engineer-in charge , cost of quality control, sampling , testing etc all complete butexcluding cost of formworkandreinforcementworks. |
| 4 | a) M-20 GradeProviding and laying Design Mix concrete for Plain / Reinforced Cement Concrete in any part of foundation of bridge /culvert with graded stone chips of appropriate nominal sizes , including screening and cleaning of coarse aggregates, fine aggregate (sand) conforming to proper grading zone , both of approved quality and cement , as necessary , cost of curing with water ,including cost and carriage of all materials and includingpreparation of design mix, approval of the same by the Engineer-in charge , cost of quality control, sampling , testing etc all complete butexcluding cost of formworkandreinforcementworks. |
| 5 | Shuttering:Hire and labour charges for Shuttering with or without staging upto 4.0 m height using approved stout props with wooden planks/ply wood/steel sheet plate with required bracing for any kind of plain or reinforced concrete works in all sorts of minor structure including culvert, box culvert, crossdrain etc. The rate is inclusive of fitting, fixing andstriking out after completion of work as per specification and direction. |
| 6 | Reinforcement:Supplying, fitting and placing HYSD bar reinforcement in Bridge Super-structure including initial straightening, straightening of coils bars, removal of loose rust (if any), cutting to requisite length bending, binding with annealed wire not less than 1 mm in size and conforming to IS 280 at every intersection hooked and bent to correct shape and placed on forms etc. including cost of black annealed wire and cost of loading,unloading, carriage of all steel materials complete as per drawing and technical specifications. |
| 7 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface] (ii) With 1:4 cement mortar (b) 15 mm thick plaster |
| 8 | Neat cement punning about 1.5mm thick in wall, dado, window sill, floor etc. |
| 9 | Filling:A) Filling in foundation or plinth by silver sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand. (payment to be made on measurement of finished quantity) |
| 10 | SignBoard:Providing&fixingConcreteSignBoardasperIRC specification of size 900 x 750 x 37 mm. thick made with RCC1:1½:3withpakurvarietystonechipsreinforced withdoublelayerIRCfebric(75x75mm.mesh)and fixedwithnecessary nuts&boltsontwoRCprecast posts 100 mm. x 150 mm. of height 2.65 m. of which top 750mm.isofsection100x13mm.and1.90metre above GL & 0.75 metre below GL including digging hole, repackingthesamewithcement concrete1:3:6with jhamakhoaorwithlocalstonechipsetc.complete includingpaintingtwocoatsonbothfaceslettering signmarksetc.asperdirectionoftheEngineer-inCharge.(Therateisinclusiveofcostofreinforcement, concrete,shuttering,nuts&bolts,washeretc. complete.) |
| 11 | Adding GST @ 18% |
| 12 | Adding labour welfare Cess @ 1% |