| 1 | Earth work in excavation of foundation trenches or drains in all sorts of soil (including mixed soil but excluding laterite or sand stone) including removing, spreading or stacking the spoils within a lead of 75m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. . |
| 2 | Laying 150 mm. to 200 mm. boulder soling including rough dressing hand packing and ramming down small pieces in the interstics including rolling and preparing the bed to proper level and filling up all joints with sandy clay or earth. |
| 3 | Cost of stone boulder 150 mm size delivered ans stacked at site. |
| 4 | Ordinary cement concrete(mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttring and reinforcement, if any, in ground floor as per relevant IS codes. |
| 5 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc.initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at inter-section, complete as per drawing and direction. |
| 6 | Hire and labour charge for shuttering with centreing and necessary staging up to 4 m. using approved stout props and thick hard wood planks of approved thick ness with required bracing for concrete slabs, beams, columns, lintels curved or staight including fitting fixing and striking out after complection of works. (up to roof of ground floor). |
| 7 | M.S structural work in colums, beams etc. with simple roled structural members (e.g. joints angle, channel sections conforming to IS: 226, IS: 808 & SP (6)- 1964 connected to one another with bracket, gussets, cleats as per design, direction of Engineering -in- charge complete including cutting to requisite shape and length, fabrication with necessary bolting, metal arc weldingconforming to IS: 816 - 1956 & IS :1995 using electrodes of approved make and brand conforming to IS: 814 - 1957, haulage, hoisting and erections all complete. the rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour required for the work including all incidential charges such as electricity charges, labour incurance charges etc.(Payment to be made on the basis of calculated weight of structural members only in finished work as per IS specified weight. Payment for Gusset, bracket, cleat, rivets, bolts and nuts may be make by adding the actual weight of such items with the weight of finished structural members or 7% of weight for finished structural members weitghing not less than 22.5Kg./m. or 15% of weight for finished structural members weighing less than 22.5 kg./m. may be incressed to allow for bracket, cleat, revets, bolts and nuts etc. and no seperate payment being made for these items, as per direction of Engineer-In-charge. The rates are considered for a height of erection 8m./ 2nd. floor level from level from the ground. Add 1.5% extra over the rate for each additional floor or 4m. beyond initial 8m. or part there of. |
| 8 | Supplying, fitting , fixing chain link fencing of approved quality with R.C.C. posts, wooden posts or iron posts by means of galvanised \"C\" clips to grid of horizontal stands of galvanised high tensile spring stell wire of 12 S.W.G. which have to be tensioned and fixed to the vertical posts by means of galvanised special clips, bolts and nuts etc.(Therate is exclusive of the cost of posts.). |
| 9 | M.S. works in brackets made from flats, angles, tees etc. to sizesspecialy bent, twisted, forged; making holes drilled and fitted torafter of trusses with necessary bolts, nuts, washer or screws etc.(length of straight not less than 230 mm) (To be used for repair works only) |
| 10 | Display Board |
| 11 | labour cess 1% |
| 12 | Add 18% GST |