| 1 | Safe Dragging, loading, carriage and unloading of following store materials with proper stacking from ESC Daliganj to JE dump store and JE dump store to work site within |
| 2 | 33KV3X300 SQ MM XLPE CABLESingle ckt |
| 3 | 33 KV Pin insulator |
| 4 | 33 KV GI Pin |
| 5 | 33KV3X300 SQ MM OUTDOOR |
| 6 | 33 KV ST/TH C/J KIT 3X300 SQ MM |
| 7 | STP 11 M long |
| 8 | Earthing Set Complete |
| 9 | Digging of pit in Kachcha/Pakka land in depth upto 1/6 length of pole, Dragging of STP fromnearby place. |
| 10 | Grouting of pole in ratio 1:4:8 in cement, sand and brick ballast and Construction of pole plinth 300 mm x 450 mm above ground level in 1:2:4 in cement, coarse sand and stone gritt as per RESPO norms. |
| 11 | Painting of new erected ST pole with two coat of Red oxide paint, PO red paint at top of pole 2 mtr and balance by two coats of best quality aluminium paint ISI mark as per norms. |
| 12 | Laying of single circuit 33 KV 3x300 Sq.mm XLPE Cable by Drill mathed As per RESPO Norms. (All Material will be Provided by contrcator excluding 33 KV cable) |
| 13 | Laying of 3x300 Sq. mm XLPE Cable in trench size 1.5x1.5x60 M3 |
| 14 | Laying of 3x300 Sq.mm XLPE Cable in to HDPE Pipe. (in the under ground Highway Crossing) |
| 15 | Supply of HDPE Pipe 160 mm dia. |
| 16 | Fabrication & erection of 33 KV Exposure type double polewith the provision of bus bar on 11 mtr. long ST-Pole with fixing of necessary clamps & other accesories like 02 No. Channel 100x50mm(1600mmeach),02No.Bracingangle65x65x6mm(2800mmeach)for supportingthehoistingofcableonpole,09No.Pininsulatorwithpin,Dangerboard, number platesand Barbed wire etc. Its jumpering by single core PVC Al. Cable with proper size of lug (All required materials will be provided by contractor except ST- pole, steel parts, Pin insulator with pin and PVC Al. cable) |
| 17 | Hoisting of 33 KV 3x300 Sqmm XLPE cable on D/P through GI- pipe of size 6\" dia 3 mtr long including its jumpering completewith holding clamps, PG clamps, Nut & bolts (All material will be provided by contractor) |
| 18 | Construction of Cable trench of size 1.5x1.5x60 M3as per RESPO norms with Iron angle and bracket for separation of cables and to cover trench by fixing 1.5x1.5x0.230 M3trench cover. |
| 19 | Earthing of poles with MS- Earthing rod 20x2500 mm, earth wire with nut and bolts as pernorms (All material will be provided by contractor except MS-Earthing rods). |
| 20 | High Pressure Testing of 33 KV cable. Testing equipment will be arranged by contractor. |
| 21 | Miscellaneous Item(Lug & Other Item) |