| 1 | Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 2 | Construction ofSubgrade and earthen shoulders with approved material obtained from borrow pits with all lift and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 303.1 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 3 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavatorat OMC, and compacting with smooth wheel roller to achieve the desired density,complete as per Technical Specification clause 405.(Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 4 | Providing, laying, spreading and compacting of sukrut stone stone aggregates of specific sizes(45.0-63mm) to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smoothwheel roller 80-100 kN in stages to proper grade and camber,applying and brooming ,binding materials to fill-up the interstices of coars aggrigate,watering and compacting to the required density Grading-2 as per Technical Specification clause 405.(Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 5 | Providing, laying, spreading and compacting of sukrut stone stone aggregates of specific sizes(22.4-53mm) to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smoothwheel roller 80-100 kN in stages to proper grade and camber,applying and brooming ,binding materials to fill-up the interstices of coars aggrigate,watering and compacting to the required density Grading-3 as per Technical Specification clause 405.(Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 6 | Brick edging on both side of road with first class brick 8 cm. (3”) wide 12 cm. (4.50”) deep laid with mud mortar including all materials, labour, T & P etc. complete.(Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 7 | Providing and applying primer coat with bitumen emulsion (SS-II) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 kg per sqm using mechanical means as per Technical Specification Clause 502.(Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 8 | Providing and applying tack coat with Bitumen (VG-10) usingbitumen distributor at the rate of 0.30 kg per sqm on the prepared bituminous surface cleaned with Air compresser as per Technical Specification Clause 503.(Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 9 | Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm -11.2 mm aggregates using penetration grade bitumen VG-10to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant,laying and rolling with three wheel static roller80-100 KN capacity ,finished to required level and grades to be follwed by seal coat of Type -C as per Technical Specification Clause 508.(Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 10 | Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall usingType C as per Technical Specification Clause 510(Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 11 | Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers,trimming bottom and side slopes, in accordance with equirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3(Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 12 | Concrete with 4cm. gauge brick ballast, sand of 1.25 F.M. and cement in proportion of 8:4:1 in foundation and under floorsincluding supply of all materials labour and tools and plants etc. required for proper completion for the work.(Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 13 | Brick Masonry Work in Cement Mortar 1:4 in Foundation with coarse sand complete excluding Pointing and Plastering, as per Drawing and Technical Specifications. 1300 SI. No. 305b. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 14 | Providing and laying 600 mm dia N.P-3 H.P. jointing with coller in proper position including cost of cement , jute etc. required for proper completion of work.but excluding cost of collor (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 15 | Providing and laying 350 mm dia N.P-3 H.P. jointing with coller in proper position including cost of cement , jute etc. required for proper completion of work.but excluding cost of collor (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 16 | Struck pointing with cement mortar consisting 1 part cement and 2 parts of sand of 1.25 fineness modulus including supply of all materials labour and T&P etc. required for proper completion of the work. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |