| 1 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per Technical Specification Clause 405) |
| 2 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405) |
| 3 | Collectionof 13.2-10 mm. sizestone grit from approvedquarry including cost of material, royality, cartage upto site, loading-unloading , stacking and all taxes such as octroi,toll tax etc including allLabour, T&P etc. required for proper completion of work As per direction of engineer-in-charge. at Departmental Hot Mix Plant |
| 4 | Collectionof 6 mm. below sizestone grit from approvedquarry including cost of material, royality, cartage upto site, loading-unloading , stacking and all taxes such as octroi,toll tax etc including allLabour, T&P etc. required for proper completion of work As per direction of engineer-in-charge.at Departmental Hot Mix Plant |
| 5 | Providing and laying of 20 mm thick open graded P.C. and seal coat with graded approved coarse aggregate, Fine aggregate, filler and Bitumen as per MORD / P.W.D. specification including heating Bitumen to required temperature, cleaning the surface, laying Tack coat and providing labour at H.M.P. with paver. The cost of labour, T&P etc. complete but excluding the cost of material required for proper completion of work (Labour only) by Deptt. Plant only. |
| 6 | Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads transporting to site spreading grading to required slope and compacted to meet requirement of table 300.2 with lead upto 1000m as per technical specification clause 303.1 |
| 7 | Construction of unreinforced, dowel jointed at expension and construction joint only, plain cement concrete pavement thickness as design, over a prepare subbase, 43 grade cement for any other type as per clause 1501.2.2 M30 (grade), coarse and fine aggregates confirming to IS383, maximum size of coarse aggregate not exceeding 25mm, mixed in a concrete mixer of not less then 0.2cum capacity and appropriate weight batcher using approved mix desing, laid in approved fixed side from work (steel channel, laying and fixing of 125micron thick polythene film, wedges, steel plates including levelling the form work as per drawing), spreading the concrete with shovels rakes, compacted using needle, screed and plate vibrator and finished in continous opreation including provision of contraction and expansion, construction joint, applying debonding strips, primer, sealant, dowel bars, near approches to bridge,/culvert and construction joints, admixtures as approved curing of concrete slabs for 14 days curing compound (where specified) and water finishing to line and grade as per drawing and techenical specification clause 1501 |
| 8 | Excavation for roadway in soil using manual means for carrying of cut earth to embankment site with a lift upto 1.5m and lead upto 50m as per technical specitication clause 302.3 |
| 9 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 (1:3:6) |
| 10 | Brick masonry work in cement mortar in foundation complete excluding pointing and plastering as per drawing and technical specifications Clauses 600, 1202 & 1203 (1:4) |
| 11 | Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification Clauses 613.4 & 1204 |
| 12 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 (1:2:4) |