| 1 | Item no. 1 Excavation for foundation/pipe trenches in earth, soils of all ltypes, sand, gravel and soft murum, including removing the excavated material upto a distance of 50 metres and lifts as below, stacking and spreading as directed, normal dewatering preparing the bed for foundation and excluding back filling etc complete (Bd-A-1/259) Lift0to1.5MMJP/DSR/2023-2024/ Page No.37 I.no. 1 |
| 2 | Item no. 2 Excavation for foundation/pipe trenches in hard murum and boulders, W.B.MN. Road including removing the excavated material upto a distance of 50 M beyond the area and lifts as below, stacking and spreading as directed by Engineer-in-charge, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete ( Bd-A-3/259) Lift 0 to 1.5 MMJP/DSR/2023-2024 Page No.:37 Item no.:3 |
| 3 | Item no. 3 Excavation for foundation/pipe trenches in soft rock and old cement and lime masonry foundation asphalt road by all means including removing the excavated material upto a distance of 50 M beyond the are and lifts as below, stacking as directed by Engineer-in-charge, normal dewatering, preparing the bed for foundation and excluding backfilling etc complete (Bd-A-4/259) Lift0to1.5MMJP/DSR/2023-2024/ Page No.37I.no. 5 |
| 4 | Item no. 4 Excavation for foundation / pipe line trenches in hard rock and concrete road by chiselling, wedging, line drilling by mechanical means other than blasting including trimming and levelling the bed, removing the excavated material upto a distance of 50 metres and lifts as below, stacking and spreading as directed, normal dewatering, preparing the bed for foundation and excluding backfilling, etc comp. Lift 0 to 1.50 M. MJP/DSR/ 2023-2024/ Page No.38 I.No.7 |
| 5 | Item no. 5 Providing and supplying Asbestos Cement Pressure pipes Manufactured and diameter in standard lengths including cost of all taxes (Central and local), insurance railway reight inspection charges, un,oading from railway wagon, loadinginto truck, transporting to departmental store/site, un,oading, stacking etc. complete. MJP/DSR/2012-2013/pageno.57 I.no.1 |
| 6 | 100 mm dia AC pipe |
| 7 | 150 mm dia AC pipe |
| 8 | 200 mm dia AC pipe |
| 9 | 250 mm dia AC pipe |
| 10 | 300 mm dia AC pipe |
| 11 | tem no. 6 Lowering laying and jointing with CiD joints AC pressure pipes and CI or MS specials of following class and diameter including conveyance from stores to site of works cost of labour and material giving satisfactory hydraulic testing etc. as per ISI code etc complete but excluding cost of CID joints nut-bolts rubber rings.MJP/DSR/2021-22/ Page No.59 I.no.4 (A) |
| 12 | 100 mm dia AC pipe |
| 13 | 150 mm dia AC pipe |
| 14 | 200 mm dia AC pipe |
| 15 | 250 mm dia AC pipe |
| 16 | 300 mm dia AC pipe |
| 17 | Item no.7Providing D.I. pipe (push on joints pressure pipes of D.I. of following class and diameters confirming to the I.S. specification inclusive cost of jointing materials ( rubber gasket of EPDM Quality) excluding GST levied by GOI & GOM in all respect including Third party inspection charges of TPI Agency approved by MJP including Transit insurance, Railway Freight, Unloading from railway wagon,Loading into Truck, Transportation to departmental store, unloading, stacking etc. completed as directed by Engineer-in-charge(IS1536/2001 for pipes and IS 158/1969 and IS 12820/1989 or latest edition/revision with amendments for Rubber Gaskets. DIK-7 grade) MJP/SSR/2023-2024/Page no.69.no.3 |
| 18 | 100 mm dia |
| 19 | 150 mm dia |
| 20 | 200 mm dia |
| 21 | 250 mm dia |
| 22 | 300 mm dia |
| 23 | tem no. 8 Lowering laying and jointing with SBR rubber gaskets C.I. & D.I. pipes of various classes with CI / MS specials of following diameters in proper position, grade and alignment as directed by Engineer-in-charge including conveyance of material from stores to site of work, excluding cost of jointing materials and rubber rings, including labur etc complete Note :- Only SBR rubber gaskets to be used as per IS-5382/12820 MJP/SSR/2021-2022/Page no.70 I.no.2 (a) |
| 24 | 100 mm dia |
| 25 | 150 mm dia |
| 26 | 200 mm dia |
| 27 | 250 mm dia |
| 28 | 300 mm dia |
| 29 | tem no. 9 Cutting and champhering of pipes of following diameters including cost of all materials and labour involved, etc. complete as directed by Engineer-in-charge (for all class of pipes )MJP/SSR/2023-24/Page no.156 I.no. 20 |
| 30 | 100 mm dia |
| 31 | 150 mm dia |
| 32 | 200 mm dia |
| 33 | 250 mm dia |
| 34 | 300 mm dia |
| 35 | tem no. 10Providing and supplying C.I.detachable joints suitable for A.C. pressure pipes manufactured as per IS-1538/1993 standard of following class and diameter including cost of all taxes (Central and local), insurance railway freight, inspection charges, unloading from railway wagon, loading into truck, trnsporting to departmental store/site,unloading, stacking and ocst of rubber rings, nut bolts, etc complete. MJP/SSR/2023-24/Page no.73Item no.13 |
| 36 | 80 mm dia CID joints |
| 37 | 100 mm dia CID joints |
| 38 | 150 mm dia CID joints |
| 39 | 200 mm dia CID joints |
| 40 | 250 mm dia CID joints |
| 41 | 300 mm dia CID joints |
| 42 | Item no. 11 Providing of C.I. Mechanical compression collar coupling suitable for C.I. spun pipes (as per IS-1536/2001) and complete with sealing rubber gasket of SBR, C.I.follower glands and M.S. nut bolts. The whole assembly should be mechanically and hydraulically tested to the provisions as laid down in IS : 1538/1993)MJP/SSR/2023-24/ Page no.161 Item no. 2 |
| 43 | 200 mm dia |
| 44 | 250 mm dia |
| 45 | 300 mm dia |
| 46 | Item no. 12 Checking Private Water connection including excavation Cost of GI specials clamp removing reconnecting water connection etc complete |
| 47 | Item no. 13 Disconnection & Repairing Private water connection and reconnecting the same etc complete. |
| 48 | Item no. 14 Making cross connection to existing distribution main of any type including excavation, breaking and removing existing pipes, lowering, laying of specials and pipes in their position, refilling, closing the water supply in that area, dewatering and restarting the water supply, etc. complete as directed by Engineer-in-charge for following diameters of existing pipe line, irrespecrtive ofdiameter of branch line. (The number of joints involved will be paid separately depending upon the nature of joints and required pipes, valves and specials will be supplied free of cost at stores.)MJP/SSR/2023-24/ Page no.58 Item no. 10 |
| 49 | 100 mm dia C/C |
| 50 | 150 mm dia C/C |
| 51 | 200 mm dia C/C |
| 52 | 250 mm dia C/C |
| 53 | 300 mm dia C/C |
| 54 | Item no. 15 Providing double flanged Sluice valves conforming to IS-2906/14846 including worm gear arrangements as per test pressure, stainless steel spindle, caps, including all taxes, transportation, etc. complete. MJP/SSR/2023-24/Page no.145 Item no. 2 (A) |
| 55 | 100 mm dia S.V. |
| 56 | 150 mm dia S.V. |
| 57 | 200 mm dia S.V. |
| 58 | 250 mm dia S.V. |
| 59 | 300 mm dia S.V. |
| 60 | Item no. 16Lowering layding and jointing in position following CIDF reflux valve, Butterflay valave and sluice valve etc complete MJP/SSR/2023-24/ Page no.148 Item no. 4 |
| 61 | 100 mm dia S.V. |
| 62 | 150 mm dia S.V. |
| 63 | 200 mm dia S.V. |
| 64 | 250 mm dia S.V. |
| 65 | 300 mm dia S.V. |
| 66 | Item no. 17Removing remaking existing cross connection including excavation broken CID joints and Tee including excavation and refilling etc completeMJP/SSR/2023-24/Page no.58 Item no. 10 |
| 67 | 100 mm dia |
| 68 | 150 mm dia |
| 69 | 200 mm dia |
| 70 | 250 mm dia |
| 71 | 300 mm dia |
| 72 | Item no. 18Removing and refixing half body sluice valve including excavation refilling cost of rubber packing, nut bolt, with gate, gland rope, repair by welding etc complete.MJP/DSR/2021-22/Page no.135 Item no. 4 |
| 73 | 80 mm dia |
| 74 | 100 mm dia |
| 75 | 150 mm dia |
| 76 | 200 mm dia |
| 77 | 250 mm dia |
| 78 | 300 mm dia |
| 79 | 350 mm dia |
| 80 | 400 mm dia |
| 81 | 450 mm dia |
| 82 | 500 mm dia |
| 83 | Item no. 19 Providing and supplying S.S. spindle rod as per standard specifications and suitable for sluice valve etc complete |
| 84 | (As Per Market rate ) |
| 85 | 80 mm dia |
| 86 | 100 mm dia |
| 87 | 150 mm dia |
| 88 | 200 mm dia |
| 89 | 250 mm dia |
| 90 | 300 mm dia |
| 91 | 350 mm dia |
| 92 | Item no. 20Providing and supplying Gun metal check nut of following diameter of sluice valve standard specification etc complete |
| 93 | (As Per Market rate ) |
| 94 | 80 mm dia |
| 95 | 100 mm dia |
| 96 | 150 mm dia |
| 97 | 200 mm dia |
| 98 | 250 mm dia |
| 99 | 300 mm dia |
| 100 | 350 mm dia |
| 101 | Item no.21Repair the gate by welding to make it in orignal position etc complete |
| 102 | 100 mm dia |
| 103 | 150 mm dia |
| 104 | 200 mm dia |
| 105 | 250 mm dia |
| 106 | 300 mm dia |
| 107 | Item no. 22Providing and Supplying M.S. Extension rod as per site requirment to fix above existing sluice valve as directed by Engineer in charge etc. Complete (As per Market rate) |
| 108 | 100 mm dia |
| 109 | 150 mm dia |
| 110 | 200 mm dia |
| 111 | Item no. 23Providing and Supplying M.S. Clamp for pipe of following diameters etc complete. (As per Market rate) |
| 112 | 80 mm dia |
| 113 | 100 mm dia |
| 114 | 150 mm dia |
| 115 | 200 mm dia |
| 116 | 250 mm dia |
| 117 | 300 mm dia |
| 118 | Item no.24Providing and supplying ISI standard C.I. flangedS&S specials including all statutory duties & taxes such as GST levied by GOI & GOM in all respect, railway freight, insurance, un,oading from railway wagon, loading into truck transport to departmental store / site, un,oading stacking etc. complete C) Plain ended / plain ended branch flanged specials. MJP/SSR/Pageno.70 Item no. 6 (C). |
| 119 | Item no.25Dismentling dead pipeline of M.S./R.C.C./C.I./P.S.C. and G.I./A.C./ P.V.C./ S.W./H.D.P.E. pipe icluding cost of necessary excavation and refilling of trenches breaking the joints, lifting he pipes and stacking to the place as directed by Engineer-in-charge with all leads and lifts including ceaning the surface, etc. complete A) MS/RCC/CI/PSC /DI pipes MJP/SSR/2021-2022/page no.61 I.no.11 (A) |
| 120 | 100 mm dia |
| 121 | 150 mm dia |
| 122 | 200 mm dia |
| 123 | 250 mm dia |
| 124 | 300 mm dia |
| 125 | Item no. 26 Dewatering the excavated trenched and pools of water in the building trenches /pipeline trenches, well works by using pumps and other devices including disposing off water to safe distance as directed by Engineer-in-charge (including cost of machinery, labour, fuel), etc complete.MJP/DSR/2021-22/Page no.45 Item no. 14 |
| 126 | Item no. 27 Providing & laying in situ cement concrete M-15/1:2:4 trap/granite/gneiss Metal for foundation & bedding including dewatering compacting & cutting etc complete. Space No.BdE-1 Page no.287 |
| 127 | Item no. 28Providing and making lead caulked koint with molten lead to Cast Iron pipes and / or specials of all classes and jointing material, labour, hydraulic testing etc.complete.MJP/DSR/2021-22/Page no.71 I.No.4 |
| 128 | 300 mm dia |
| 129 | 350 mm dia |
| 130 | 400 mm dia |
| 131 | Item no. 29Refilling the trenches with available excavated stuff with soft material first over pipeline and then hard material in 15 cm layers with all leads and lifts including consolidation, surcharging, etc complete |