Name of Work : Renovation of safety Railings & Jaal of Main sump by Replacement with Non-Reactive substance at Keshopur STP
Sl. No.
Item Description
1
Dismantling of old Rusted damaged MS Railing by gas Cutter/Cutting Machine/ manual labor around the open chamber wall and shift to the store yard as per direction of engineer in-charge
2
Cutting and Removing of old rusted damaged M.S jaal from the Sump cutting/opening with the gas cutter/grinder/Manual Labor and shift to the store yard as per per direction of engineer in-charge
3
Supply/Fixing of FRP Hand Railing with all accessories of size-Oval Top of size-. 75x60x4mmBase Shoe Size-100x125x100mmToe Guard-100x3mmMake- SINTEX/SUMIP/AERON
4
Supply of FRP PULTRUDED GRATING (Height 38x25x5mm) Make- SINTEX/SUMIP/AERON
5
Supply of FRP I BEAM UV Resistant. Fire Retardant, Non-Corrosive, 60% Glass GRP of Size-254 (H) x127(W) x12.7mm (Thickness) (Length-8mtr)Make- SINTEX/SUMIP/AERON
6
Providing of all required Safety Equipment\"s/Articles like Safety belts, gum boots, ladder, helmet, hand gloves etc. as per NHRC Guidelines for executing the work.
7
Making the temporary platform to make the workable space for hole grouting, Digging in the sump wall with the help of portable hydraulic machine / skilled staff & dismantle it after completion of work.
8
Dismantling the old Rusted damaged M.S platform by cutting with the help of gas cutter etc
9
Supply of SMC Cheaqured sheet anti-corrosive water resistant. UV protected, High temp resistant, conforming to UL 94 V0 Standards, ERDA Approved, Weather able, and suitable for all kinds of climatic conditions. Self-colored Fire retardant and High di-electric strength maintenance-free of size 1 Mtr. X 1 mtr. 10 mm thick.Make- SINTEX/SUMIP/AERON
10
Fixing of SMC sheet on the FRP structure.
11
Making the hole in the wall by Hydraulic machine with the help of Manual Labor by using the above temporary platform by using the all safety Equipment\"s.
12
After Digging Wall Fixing/Installation of FRP I Beam with the help of cement, concrete.
13
Making the FRP Structure on the Vacant sump space with the help of required articles Like-FRP I Beam, C Channel, FRP Angle. As per site requirements
14
Fixing/installation of grating on the FRP Structure by using the non-reactive substance by Skilled Staff
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.