| 1 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 metres:All kinds of soil : |
| 2 | Demolishing cement concrete manually/by mechanical means including disposal of material within 50 meters lead as per direction of Engineer-incharge:1:3:6 or richer mix (i/c equivalent design mix) |
| 3 | Providing and laying in position Cement concreteof specified grade excluding the cost of centering and shuttering – all work upto plinth level.1:5:10(1 cement : 5 coarse sand : 10 graded crushed stone aggregate 40 mm nominal size) |
| 4 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size |
| 5 | Cement concrete flooring 1:2:4 (1cement: 2 coarse sand: 4 graded stone aggregate) finished with a floating coat of neat cement including cement slurry and curing complete, but excluding the cost of nosing of steps etc. complete.40mm thick with 20 mm nominal size stone aggregate. |
| 6 | Providing and laying in position cement concrete of specified grade including curing butexcluding the cost of centring and shuttering. All work upto plinth level with:1:1½:3 (1 cement :1½ coarse sand: 3 graded stone aggregate 20 mm nominal size) |
| 7 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level Cold twisted bars |
| 8 | Structural steel work in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. |
| 9 | Centering and Shuttering including strutting, propping etc and removal of form work formass concrete |
| 10 | Foundations, footings, bases for columns |
| 11 | Carriage of material from source to site of work by mechanical transport including loading /unloading and stacking complete. |
| 12 | Sand for an average distance of 120 kms by M.T and 250 Mtr by H.L |
| 13 | Stone aggregate below 40 mm nominal size for anaverage distance 10kms by M.T and 250 Mtr by H.L |
| 14 | Stone for an an average distance of 05 Km by M.T and 250 Mtr by H.L |
| 15 | Disposal of Mulba for an average distance of 5 Km by M.T |