Tender For Tender For Repair/Maintenance Of 22Kv Ht Line New Kinnaur Feeder( Spur Line Ramni Bridge To Shuthanang) In E-Section Tapri, Under Electrical Sub-Division , Hpsebl, Tapri.
Tender Overview
Project Description
Tender For Repair/Maintenance Of 22Kv Ht Line New Kinnaur Feeder( Spur Line Ramni Bridge To Shuthanang) In E-Section Tapri, Under Electrical Sub-Division , Hpsebl, Tapri.
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 18-Feb-2025 | time extension | Date | 21-Feb-2025 |
BOQ
| Sl. No. | Item Description |
| 1 | Dismentalement Charges of 22kV HT line. |
| 2 | Dismentalement charges of ST poles D/Pole Str. (with complete accessories.) |
| 3 | Erection of 22kV H.T Line |
| 4 | Erection of 10mtr. Long ST pole. |
| 5 | Erection of pole.Digging of pit,(ii) Laying of RCC muff (iii) Drilling of holes in X-bracing set, X-arms (iv) Erection of pole (v) fixing of insulator,X-arm, Knee bracing set, Top Clamp (vi) fixing of Barbed wire, Danger plate (vii) filling of pit & Ramming i/c painting of pole S/Pole str. (Complete in all respect). |
| 6 | Re erection/erection of stay set (HT). |
| 7 | Digging of pit, fixing of stay rod, filling of pit, Nozzeling & Tighting.) Complete in all respect. |
| 8 | SAGGING OF ACSR CONDUCTOR 6/1/3.35mm (Single wire). |
| 9 | stringing & sagging, Binding with insulator (only). |
| 10 | Manual Carriage of material |
| 11 | For 1 KM H.T Line considering average distance from road to site of work 2.100 KM |
| 12 | Steel tubular pole. |
| 13 | Other line material. |
| 14 | MATERIAL TO BE SUPPLIED BY CONTRACTOR (Subject to the non-availability of material at Divisional Store). |
| 15 | Prov. Nuts & bolts. |
| 16 | Prov. Aluminium paint. |
| 17 | Prov. RCC Muffs 2Mtr. |
| 18 | Prov. Stay Clamp |
| 19 | Prov. Egg Insulator (HT) |
| 20 | Prov. stay Wire (7/3.15mm) |
| 21 | Prov. Disc Insulator sets on Dead End Str (Disc porcelain, BS 12KV, 90KN, including Dead End Clamps etc). |
| 22 | Prov. 22KV Pin Insulators (Porcelain,24Kv,10KN) with GI Pin. |
| 23 | Prov. Top Pole Bracket (on single pole Str.) |
| 24 | Prov. MS Angle Iron (50X50X6mm), Length: 2X950mm. |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender