Sales : +91-777 804 8217
| Sl. No. | Item Description |
| 1 | Rampur ManjhaPanchayat Piped Water Supply Scheme |
| 2 | BUILD PHASE (SL. NO. - 1.02 TO SL. NO. -1.29) |
| 3 | Supply of following sizes pipes for distribution system conforming to latest/ relevant I.S. 4984/1995 Specifications with all jointing materials and specials conforming to latest /relevant I.S. specifications including F.O.R. destination and all taxes and insurance etc. with loading unloading and Carting up to site of work also including specials for these pipes and lowering them into the trenches and laying true to alignment and gradient and jointing etc. complete (including testing of pipe lines and cutting of pipes for making up the length but excluding the cost of trenches) all complete as per instructions of Engineer -in - charge. |
| 4 | 63 mm |
| 5 | 90 mm |
| 6 | Excavation of earth for pipe line in ordinary soil (loam,clay or sand ) including lift up to 1.50 m& lead up to 50 m,refilling,watering and ramming of evcavated earth into the trenches and disposal of surplus earth up to the distance of 50 mfrom the center of the trenches. |
| 7 | Provide all materials and labour T & P etc. required for proper completion of work and construction of following chambers. |
| 8 | Sluice valve chamber masonary type |
| 9 | Provision for Inter Connections from old existing pipe line with new pipe line as per requirement & direction of Engineer Incharge Including Supply of all material, Labour T & P etc. |
| 10 | 110mm x 90mm dia or below dia |
| 11 | Dismantling and Reinstatement of the following type of road surface with old andnew materials including supply of all materials labour T&P etc. required for proper completion of the work as per instructions of Engineer-in-charge. |
| 12 | B.O.E. |
| 13 | CC road |
| 14 | Leakage Repairing of following dia /types of pipes with all materials, labour, etc complete |
| 15 | 160mm HDPE/PVC |
| 16 | 140mm HDPE/PVC |
| 17 | 110mm HDPE/PVC |
| 18 | 90mm HDPE/PVC |
| 19 | 75mm HDPE/PVC |
| 20 | 63mm HDPE/PVC |
| 21 | Repairing of house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 22 | Making house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 23 | Cleaning of water works campus with all labour T&P etc complete. |
| 24 | Repairing of existing motor pump with dismantling and lowering charge. |
| 25 | Repairing of existing Starter. |
| 26 | Supply and Installation of chlorinator system with 100 Litter Sodium Hypo cloride |
| 27 | BaburaPanchayat Piped Water Supply Scheme |
| 28 | BUILD PHASE (SL. NO. - 1.32 TO SL. NO. -1.58) |
| 29 | Leakage Repairing of following dia /types of pipes with all materials, labour, etc complete |
| 30 | 160mm HDPE/PVC |
| 31 | 140mm HDPE/PVC |
| 32 | 110mm HDPE/PVC |
| 33 | 90mm HDPE/PVC |
| 34 | Repairing of house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 35 | Cleaning of water works campus with all labour T&P etc complete. |
| 36 | Repairing of existing motor pump with dismantling and lowering charge. |
| 37 | Repairing of existing Starter. |
| 38 | Supply and Installation of chlorinator system with 100 ltr sodium hypo cloride |
| 39 | KhalishpurPanchayat Piped Water Supply Scheme |
| 40 | BUILD PHASE (SL. NO. - 1.61 TO SL. NO. -1.91) |
| 41 | Supply of following sizes pipes for distribution system conforming to latest/ relevant I.S. 4984/1995 Specifications with all jointing materials and specials conforming to latest /relevant I.S. specifications including F.O.R. destination and all taxes and insurance etc. with loading unloading and Carting up to site of work also including specials for these pipes and lowering them into the trenches and laying true to alignment and gradient and jointing etc. complete (including testing of pipe lines and cutting of pipes for making up the length but excluding the cost of trenches) all complete as per instructions of Engineer -in - charge. |
| 42 | 63 mm |
| 43 | 75 mm |
| 44 | 90 mm |
| 45 | 110 mm |
| 46 | 140 mm |
| 47 | 200 mm |
| 48 | Excavation of earth for pipe line in ordinary soil (loam,clay or sand ) including lift up to 1.50 m& lead up to 50 m,refilling,watering and ramming of evcavated earth into the trenches and disposal of surplus earth up to the distance of 50 mfrom the center of the trenches. |
| 49 | Supply of following size of C.I.D./F sluice valve and scour valves of various size given below including railway freight, insurance charge, carting, loading, unloading & stacking, etc. complete. |
| 50 | 50mm |
| 51 | Provide all materials and labour T & P etc. required for proper completion of work and construction of following chambers. |
| 52 | Sluice valve chamber surface type |
| 53 | Provision for Inter Connections from old existing pipe line with new pipe line as per requirement & direction of Engineer Incharge Including Supply of all material, Labour T & P etc. |
| 54 | 110mm x 90mm dia or below dia |
| 55 | Dismantling and Reinstatement of the following type of road surface with old andnew materials including supply of all materials labour T&P etc. required for proper completion of the work as per instructions of Engineer-in-charge. |
| 56 | B.O.E. |
| 57 | Interlocking/ stone patia |
| 58 | CC road |
| 59 | Leakage Repairing of following dia /types of pipes with all materials, labour, etc complete |
| 60 | 160mm HDPE/PVC |
| 61 | 140mm HDPE/PVC |
| 62 | 110mm HDPE/PVC |
| 63 | 90mm HDPE/PVC |
| 64 | 75mm HDPE/PVC |
| 65 | 63mm HDPE/PVC |
| 66 | Repairing of house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 67 | Making house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 68 | Cleaning of water works campus with all labour T&P etc complete. |
| 69 | Repairing of existing Starter. |
| 70 | Supply and Installation of chlorinator with 100 Litter Sodium Hypo cloride |
| 71 | Alipur madraPanchayat Piped Water Supply Scheme |
| 72 | BUILD PHASE (SL. NO. - 1.94 TO SL. NO. -2.19) |
| 73 | 110mm HDPE/PVC |
| 74 | 90mm HDPE/PVC |
| 75 | Repairing of house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 76 | Same as ITEM NO. 1.22 but for new house connections. |
| 77 | Cleaning of water works campus with all labour T&P etc complete. |
| 78 | Repairing of existing motor pump with dismantling and lowering charge. |
| 79 | Repairing of existing Starter. |
| 80 | Supply and Installation of chlorinator system with 100 Litter Sodium Hypo cloride |
| 81 | CHHAPRIPanchayat Piped Water Supply Scheme |
| 82 | BUILD PHASE (SL. NO. - 2.22 TO SL. NO. -2.47) |
| 83 | Supply of following sizes pipes for distribution system conforming to latest/ relevant I.S. 4984/1995 Specifications with all jointing materials and specials conforming to latest /relevant I.S. specifications including F.O.R. destination and all taxes and insurance etc. with loading unloading and Carting up to site of work also including specials for these pipes and lowering them into the trenches and laying true to alignment and gradient and jointing etc. complete (including testing of pipe lines and cutting of pipes for making up the length but excluding the cost of trenches) all complete as per instructions of Engineer -in - charge. |
| 84 | 63 mm |
| 85 | Excavation of earth for pipe line in ordinary soil (loam,clay or sand ) including lift up to 1.50 m& lead up to 50 m,refilling,watering and ramming of evcavated earth into the trenches and disposal of surplus earth up to the distance of 50 mfrom the center of the trenches. |
| 86 | Supply of following size of C.I.D./F sluice valve and scour valves of various size given below including railway freight, insurance charge, carting, loading, unloading & stacking, etc. complete. |
| 87 | 50mm |
| 88 | Provide all materials and labour T & P etc. required for proper completion of work and construction of following chambers. |
| 89 | Sluice valve chamber sufrace box type |
| 90 | Provision for Inter Connections from old existing pipe line with new pipe line as per requirement & direction of Engineer Incharge Including Supply of all material, Labour T & P etc. |
| 91 | 110mm x 90mm dia or below dia |
| 92 | Dismantling and Reinstatement of the following type of road surface with old andnew materials including supply of all materials labour T&P etc. required for proper completion of the work as per instructions of Engineer-in-charge. |
| 93 | B.O.E. |
| 94 | Interlocking/ stone patia |
| 95 | CC road |
| 96 | Leakage Repairing of following dia /types of pipes with all materials, labour, etc complete |
| 97 | 160mm HDPE/PVC |
| 98 | 140mm HDPE/PVC |
| 99 | 110mm HDPE/PVC |
| 100 | 90mm HDPE/PVC |
| 101 | 75mm HDPE/PVC |
| 102 | 63mm HDPE/PVC |
| 103 | Repairing of house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 104 | Making house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 105 | Cleaning of water works campus with all labour T&P etc complete. |
| 106 | Repairing of existing motor pump with dismantling and lowering charge. |
| 107 | Repairing of existing Starter. |
| 108 | Supply and Installation of chlorinator system with 100 Litter Sodium Hypo cloride |
| 109 | ChochakpurPiped Water Supply Scheme |
| 110 | BUILD PHASE (SL. NO. - 2.50 TO SL. NO. -2.75) |
| 111 | Supply of following sizes pipes for distribution system conforming to latest/ relevant I.S. 4984/1995 Specifications with all jointing materials and specials conforming to latest /relevant I.S. specifications including F.O.R. destination and all taxes and insurance etc. with loading unloading and Carting up to site of work also including specials for these pipes and lowering them into the trenches and laying true to alignment and gradient and jointing etc. complete (including testing of pipe lines and cutting of pipes for making up the length but excluding the cost of trenches) all complete as per instructions of Engineer -in - charge. |
| 112 | 90 mm HDPE PN-6, PE-100 |
| 113 | Excavation of earth for pipe line in ordinary soil (loam,clay or sand ) including lift up to 1.50 m& lead up to 50 m,refilling,watering and ramming of evcavated earth into the trenches and disposal of surplus earth up to the distance of 50 mfrom the center of the trenches. |
| 114 | Supply of following size of C.I.D./F sluice valve and scour valves of various size given below including railway freight, insurance charge, carting, loading, unloading & stacking, etc. complete. |
| 115 | 80mm |
| 116 | Provide all materials and labour T & P etc. required for proper completion of work and construction of following chambers. |
| 117 | Sluice valve chamber surface box type |
| 118 | Provision for Inter Connections from old existing pipe line with new pipe line as per requirement & direction of Engineer Incharge Including Supply of all material, Labour T & P etc. |
| 119 | 110mm x 90mm dia or below dia |
| 120 | Dismantling and Reinstatement of the following type of road surface with old andnew materials including supply of all materials labour T&P etc. required for proper completion of the work as per instructions of Engineer-in-charge. |
| 121 | B.O.E. |
| 122 | Interlocking/ stone patia |
| 123 | CC road |
| 124 | Leakage Repairing of following dia /types of pipes with all materials, labour, etc complete |
| 125 | 160mm HDPE/PVC |
| 126 | 140mm HDPE/PVC |
| 127 | 110mm HDPE/PVC |
| 128 | 90mm HDPE/PVC |
| 129 | Repairing of house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 130 | Making house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 131 | Cleaning of water works campus with all labour T&P etc complete. |
| 132 | Repairing of existing motor pump with dismantling and lowering charge. |
| 133 | Repairing of existing Starter. |
| 134 | Supply and Installation of chlorinator system with 100 Litter Sodium Hypo cloride |
| 135 | Para Piped Water Supply Scheme |
| 136 | BUILD PHASE (SL. NO. - 2.78 TO SL. NO. -3.03) |
| 137 | Supply of following sizes pipes for distribution system conforming to latest/ relevant I.S. 4984/1995 Specifications with all jointing materials and specials conforming to latest /relevant I.S. specifications including F.O.R. destination and all taxes and insurance etc. with loading unloading and Carting up to site of work also including specials for these pipes and lowering them into the trenches and laying true to alignment and gradient and jointing etc. complete (including testing of pipe lines and cutting of pipes for making up the length but excluding the cost of trenches) all complete as per instructions of Engineer -in - charge. |
| 138 | 65 mm G.I pipe Medium |
| 139 | Excavation of earth for pipe line in ordinary soil (loam,clay or sand ) including lift up to 1.50 m& lead up to 50 m,refilling,watering and ramming of evcavated earth into the trenches and disposal of surplus earth up to the distance of 50 mfrom the center of the trenches. |
| 140 | Provision for Inter Connections from old existing pipe line with new pipe line as per requirement & direction of Engineer Incharge Including Supply of all material, Labour T & P etc. |
| 141 | 110mm x 90mm dia or below dia |
| 142 | Dismantling and Reinstatement of the following type of road surface with old andnew materials including supply of all materials labour T&P etc. required for proper completion of the work as per instructions of Engineer-in-charge. |
| 143 | B.O.E. |
| 144 | Interlocking/ stone patia |
| 145 | CC road |
| 146 | Leakage Repairing of following dia /types of pipes with all materials, labour, etc complete |
| 147 | 65 mm GI pipe |
| 148 | Repairing of house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 149 | Making house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 150 | Cleaning of water works campus with all labour T&P etc complete. |
| 151 | Supply and Installation of chlorinator system with 100 Litter Sodium Hypo cloride |
| 152 | UasarahaPanchayat Piped Water Supply Scheme |
| 153 | BUILD PHASE (SL. NO. - 3.06 TO SL. NO. -3.31) |
| 154 | Leakage Repairing of following dia /types of pipes with all materials, labour, etc complete |
| 155 | 110mm HDPE/PVC |
| 156 | 90mm HDPE/PVC |
| 157 | 75mm HDPE/PVC |
| 158 | 63mm HDPE/PVC |
| 159 | Repairing of house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 160 | Making house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 161 | Cleaning of water works campus with all labour T&P etc complete. |
| 162 | Repairing of existing motor pump with dismantling and lowering charge. |
| 163 | Repairing of existing Starter. |
| 164 | Supply and Installation of chlorinator system with 100 Litter Sodium Hypo cloride |
| 165 | YusufpurPanchayat Piped Water Supply Scheme |
| 166 | BUILD PHASE (SL. NO. - 3.34 TO SL. NO. -3.59) |
| 167 | Supply of following sizes pipes for distribution system conforming to latest/ relevant I.S. 4984/1995 Specifications with all jointing materials and specials conforming to latest /relevant I.S. specifications including F.O.R. destination and all taxes and insurance etc. with loading unloading and Carting up to site of work also including specials for these pipes and lowering them into the trenches and laying true to alignment and gradient and jointing etc. complete (including testing of pipe lines and cutting of pipes for making up the length but excluding the cost of trenches) all complete as per instructions of Engineer -in - charge. |
| 168 | 90 mm |
| 169 | Excavation of earth for pipe line in ordinary soil (loam,clay or sand ) including lift up to 1.50 m& lead up to 50 m,refilling,watering and ramming of evcavated earth into the trenches and disposal of surplus earth up to the distance of 50 mfrom the center of the trenches. |
| 170 | Supply of following size of C.I.D./F sluice valve and scour valves of various size given below including railway freight, insurance charge, carting, loading, unloading & stacking, etc. complete. |
| 171 | 80mm |
| 172 | Provide all materials and labour T & P etc. required for proper completion of work and construction of following chambers. |
| 173 | Sluice valve chamber surface box type |
| 174 | Provision for Inter Connections from old existing pipe line with new pipe line as per requirement & direction of Engineer Incharge Including Supply of all material, Labour T & P etc. |
| 175 | 110mm x 90mm dia or below dia |
| 176 | Dismantling and Reinstatement of the following type of road surface with old andnew materials including supply of all materials labour T&P etc. required for proper completion of the work as per instructions of Engineer-in-charge. |
| 177 | B.O.E. |
| 178 | Interlocking/ stone patia |
| 179 | CC road |
| 180 | Leakage Repairing of following dia /types of pipes with all materials, labour, etc complete |
| 181 | 160mm HDPE/PVC |
| 182 | 140mm HDPE/PVC |
| 183 | 110mm HDPE/PVC |
| 184 | 90mm HDPE/PVC |
| 185 | Repairing of house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 186 | Making house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 187 | Cleaning of water works campus with all labour T&P etc complete. |
| 188 | Repairing of existing motor pump with dismantling and lowering charge. |
| 189 | Repairing of existing Starter. |
| 190 | Supply and Installation of chlorinator system with 100 Litter Sodium Hypo cloride |
| 191 | DullahpurPanchayat Piped Water Supply Scheme |
| 192 | BUILD PHASE (SL. NO. - 3.62 TO SL. NO. -3.87) |
| 193 | Supply of following size of C.I.D./F sluice valve and scour valves of various size given below including railway freight, insurance charge, carting, loading, unloading & stacking, etc. complete. |
| 194 | 50mm |
| 195 | Provide all materials and labour T & P etc. required for proper completion of work and construction of following chambers. |
| 196 | Sluice valve chamber masonary type |
| 197 | Provision for Inter Connections from old existing pipe line with new pipe line as per requirement & direction of Engineer Incharge Including Supply of all material, Labour T & P etc. |
| 198 | 110mm x 90mm dia or below dia |
| 199 | Leakage Repairing of following dia /types of pipes with all materials, labour, etc complete |
| 200 | 160mm HDPE/PVC |
| 201 | 140mm HDPE/PVC |
| 202 | 110mm HDPE/PVC |
| 203 | 90mm HDPE/PVC |
| 204 | 75mm HDPE/PVC |
| 205 | 63mm HDPE/PVC |
| 206 | Repairing of house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 207 | Making house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 208 | Cleaning of water works campus with all labour T&P etc complete. |
| 209 | Repairing of existing motor pump with dismantling and lowering charge. |
| 210 | Repairing of existing Starter. |
| 211 | Supply and Installation of chlorinator system with 100 Litter Sodium Hypo cloride |
| 212 | HardhanaPanchayat Piped Water Supply Scheme |
| 213 | BUILD PHASE (SL. NO. - 3.90 TO SL. NO. -4.16) |
| 214 | Leakage Repairing of following dia /types of pipes with all materials, labour, etc complete |
| 215 | 160mm HDPE/PVC |
| 216 | 140mm HDPE/PVC |
| 217 | 110mm HDPE/PVC |
| 218 | 90mm HDPE/PVC |
| 219 | 75mm HDPE/PVC |
| 220 | 63mm HDPE/PVC |
| 221 | Stand Post |
| 222 | ParaPanchayat Piped Water Supply Scheme |
| 223 | BUILD PHASE (SL. NO. - 4.19 TO SL. NO. -4.44) |
| 224 | Supply of following sizes pipes for distribution system conforming to latest/ relevant I.S. 4984/1995 Specifications with all jointing materials and specials conforming to latest /relevant I.S. specifications including F.O.R. destination and all taxes and insurance etc. with loading unloading and Carting up to site of work also including specials for these pipes and lowering them into the trenches and laying true to alignment and gradient and jointing etc. complete (including testing of pipe lines and cutting of pipes for making up the length but excluding the cost of trenches) all complete as per instructions of Engineer -in - charge. |
| 225 | 63 mm |
| 226 | Excavation of earth for pipe line in ordinary soil (loam,clay or sand ) including lift up to 1.50 m& lead up to 50 m,refilling,watering and ramming of evcavated earth into the trenches and disposal of surplus earth up to the distance of 50 mfrom the center of the trenches. |
| 227 | Supply of following size of C.I.D./F sluice valve and scour valves of various size given below including railway freight, insurance charge, carting, loading, unloading & stacking, etc. complete. |
| 228 | 50mm |
| 229 | Provide all materials and labour T & P etc. required for proper completion of work and construction of following chambers. |
| 230 | Sluice valve chamber masonary type |
| 231 | Dismantling and Reinstatement of the following type of road surface with old andnew materials including supply of all materials labour T&P etc. required for proper completion of the work as per instructions of Engineer-in-charge. |
| 232 | B.O.E. |
| 233 | Interlocking/ stone patia |
| 234 | CC road |
| 235 | Leakage Repairing of following dia /types of pipes with all materials, labour, etc complete |
| 236 | 160mm HDPE/PVC |
| 237 | 140mm HDPE/PVC |
| 238 | 110mm HDPE/PVC |
| 239 | 90mm HDPE/PVC |
| 240 | 75mm HDPE/PVC |
| 241 | 63mm HDPE/PVC |
| 242 | Repairing of house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 243 | Making house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 244 | Cleaning of water works campus with all labour T&P etc complete. |
| 245 | Supply and Installation of 3 phase Star-Delta Starter with suitable Capacity as per site Condition. |
| 246 | Supply and Installation of chlorinator system with 100 Litter Sodium Hypo cloride |
| 247 | PatnaPanchayat Piped Water Supply Scheme |
| 248 | BUILD PHASE (SL. NO. - 4.47 TO SL. NO. -4.74) |
| 249 | Supply of following sizes pipes for distribution system conforming to latest/ relevant I.S. 4984/1995 Specifications with all jointing materials and specials conforming to latest /relevant I.S. specifications including F.O.R. destination and all taxes and insurance etc. with loading unloading and Carting up to site of work also including specials for these pipes and lowering them into the trenches and laying true to alignment and gradient and jointing etc. complete (including testing of pipe lines and cutting of pipes for making up the length but excluding the cost of trenches) all complete as per instructions of Engineer -in - charge. |
| 250 | 63 mm |
| 251 | Excavation of earth for pipe line in ordinary soil (loam,clay or sand ) including lift up to 1.50 m& lead up to 50 m,refilling,watering and ramming of evcavated earth into the trenches and disposal of surplus earth up to the distance of 50 mfrom the center of the trenches. |
| 252 | Dismantling and Reinstatement of the following type of road surface with old andnew materials including supply of all materials labour T&P etc. required for proper completion of the work as per instructions of Engineer-in-charge. |
| 253 | B.O.E. |
| 254 | Leakage Repairing of following dia /types of pipes with all materials, labour, etc complete |
| 255 | 160mm HDPE/PVC |
| 256 | 140mm HDPE/PVC |
| 257 | 110mm HDPE/PVC |
| 258 | 90mm HDPE/PVC |
| 259 | Making house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 260 | Cleaning of water works campus with all labour T&P etc complete. |
| 261 | Repairing of existing Starter. |
| 262 | Solar panel |
| 263 | Repair of Existing Chlorinating plant including supply of missing parts |
| 264 | Sarauli Urf PahetiaPanchayat Piped Water Supply Scheme |
| 265 | BUILD PHASE (SL. NO. - 4.77 TO SL. NO. -5.03) |
| 266 | Leakage Repairing of following dia /types of pipes with all materials, labour, etc complete |
| 267 | 160mm HDPE/PVC |
| 268 | 140mm HDPE/PVC |
| 269 | 110mm HDPE/PVC |
| 270 | 90mm HDPE/PVC |
| 271 | Repairing of house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 272 | Cleaning of water works campus with all labour T&P etc complete. |
| 273 | Repairing of existing motor pump with dismantling and lowering charge. |
| 274 | Repairing of existing Starter. |
| 275 | Supply and Installation of chlorinator system with 100 ltr sodium hypo cloride |
| 276 | TamalpuraPanchayat Piped Water Supply Scheme |
| 277 | BUILD PHASE (SL. NO. - 5.06 TO SL. NO. -5.31) |
| 278 | Supply of following sizes pipes for distribution system conforming to latest/ relevant I.S. 4984/1995 Specifications with all jointing materials and specials conforming to latest /relevant I.S. specifications including F.O.R. destination and all taxes and insurance etc. with loading unloading and Carting up to site of work also including specials for these pipes and lowering them into the trenches and laying true to alignment and gradient and jointing etc. complete (including testing of pipe lines and cutting of pipes for making up the length but excluding the cost of trenches) all complete as per instructions of Engineer -in - charge. |
| 279 | 63 mm |
| 280 | Excavation of earth for pipe line in ordinary soil (loam,clay or sand ) including lift up to 1.50 m& lead up to 50 m,refilling,watering and ramming of evcavated earth into the trenches and disposal of surplus earth up to the distance of 50 mfrom the center of the trenches. |
| 281 | Dismantling and Reinstatement of the following type of road surface with old andnew materials including supply of all materials labour T&P etc. required for proper completion of the work as per instructions of Engineer-in-charge. |
| 282 | B.O.E. |
| 283 | Interlocking/ stone patia |
| 284 | CC road |
| 285 | Leakage Repairing of following dia /types of pipes with all materials, labour, etc complete |
| 286 | 140mm HDPE/PVC |
| 287 | 110mm HDPE/PVC |
| 288 | 90mm HDPE/PVC |
| 289 | 75mm HDPE/PVC |
| 290 | 63mm HDPE/PVC |
| 291 | Repairing of house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 292 | Making house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house with supply of 1 m above GL uPVC. pipe (15 mm) (above ground) & average 5 mtr. MDPE Pipe ( 20 mm) (below ground) including specials saddle Tapetc. of suitable size T&P etc. including excavation laying and jointing for proper completion of work as per instructions of Engineer as per (Including grauting and road restoration) |
| 293 | Cleaning of water works campus with all labour T&P etc complete. |
| 294 | Repairing of existing motor pump with dismantling and lowering charge. |
| 295 | Repairing of existing Starter. |
| 296 | Supply and Installation of chlorinator system with 100 Litter Sodium Hypo cloride |
Copyright © 2025 · All Rights Reserved. Terms of Usage | Privacy Policy