| 1 | Construction of granular sub-base by providing well material, spreading in uniform layer with motor grader/tractor mounted appropriate equipment on prepared sruface, mixing by mix in place method with rortavator at OMC, and compacting with smooth wheel roller to achieve the desired density complete as per Technical specification clause 401.Including 1% Labour Cess. |
| 2 | Providing, laying, spreading and compacting stone aggregates of specific size to water bound macadam specification including spreading in uniform thickness, handpacking, rolling with smooth wheel roller 80-100 KN in stages to proper grade and camber, applying and brooming, crushible screening to fill up the interstices of coarse aggregate, watering and compacting, to the required density Grading-2 as per technical specification clause 405.Including 1% Labour Cess. |
| 3 | Providing, laying, spreading and compacting stone aggregates of specific size to water bound macadam specification including spreading in uniform thickness, handpacking, rolling with smooth wheel roller 80-100 KN in stages to proper grade and camber, applying and brooming, crushible screening to fill up the interstices of coarse aggregate, watering and compacting, to the required density Grading - 3 as per technical specification clause 405.Including 1% Labour Cess. |
| 4 | Providing and applying primer coat with bitumen emulsion (SS-2) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means as per Technical Specification Clause 502.Including 1% Labour Cess &cost of bitumen. |
| 5 | Providing and applying Tack coat with VG-10 Grade using emulsion pressure dristibutor at the rate of 0.275 Kg per Sqm on the prepared granular surface treated with primer and cleaned with hydraulic broom as per technical specification clause 503. Including 1% Labour Cess &cost of bitumen. |
| 6 | Providing, laying and rolling open-graded premix carpet of 20 mm thickness composed of 13.2 mm and 11.2 mm aggregate using VG-10 grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base by manual means , including mixing in a suitable mixol, laying and rolling with a three wheel 80-100 Kn Static roller capacity, finised to required level and grades to be followed by seal coat as per Technical Specification Clause 508.Including 1% Labour Cess &cost of bitumen. |
| 7 | Providing and laying ofseal coat by manual means with VG- 10 Bulk bitumen sealing the voids in a bituminous surface laid to the specified levels grade and cross fall using Type Cas per Technical Specification Clause 510.Including 1% Labour Cess &cost of bitumen. |
| 8 | Earth Work in road patri with ordinary soil including levelling, dressing, ramming complete work,t&p etc |
| 9 | The routine maintenance of above road work including embankment, patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition duringthe entire maintenance period which begins from the actual Completion Date and ends after five years.(including cost of material T & P labour but excluding GST) for 1st Year maintenance cost @ 0.00% of Tendered cost of Constructionas per circular No.-3689 C-OPRMC/Mool/2023-24 Dt 17.02.2024 |
| 10 | The routine maintenance of above road work including embankment, patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition duringthe entire maintenance period which begins from the actual Completion Date and ends after five years.(including cost of material T & P labour but excluding GST) for 2nd Year maintenance cost @ 0.75% of Tendered cost of Construction as per circular No.-3689 C-OPRMC/Mool/2023-24 Dt 17.02.2024 |
| 11 | The routine maintenance of above road work including embankment, patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition duringthe entire maintenance period which begins from the actual Completion Date and ends after five years.(including cost of material T & P labour but excluding GST) for 3rd Year maintenance cost @ 1.50% of Tendered cost of Construction as per circular No.-3689 C-OPRMC/Mool/2023-24 Dt 17.02.2024 |
| 12 | The routine maintenance of above road work including embankment, patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition duringthe entire maintenance period which begins from the actual Completion Date and ends after five years.(including cost of material T & P labour but excluding GST) for 4th Year maintenance cost @ 2.25% of Tendered cost of Construction as per circular No.-3689 C-OPRMC/Mool/2023-24 Dt 17.02.2024 |
| 13 | The routine maintenance of above road work including embankment, patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition duringthe entire maintenance period which begins from the actual Completion Date and ends after five years.(including cost of material T & P labour but excluding GST) for 5th Year maintenance cost @ 3.00% of Tendered cost of Construction as per circular No.-3689 C-OPRMC/Mool/2023-24 Dt 17.02.2024 |