| 1 | Dismantling of B.O.E. Soling/interlocking tiles including stacking of sericable material and disposal of unservicable material witrhin a lead of 50m as per direction of E/I. |
| 2 | Excavating, supplying and filling of local earth (including royalty) by mechanical transport upto a lead of 1km also including ramming and watering of the earth in layers not exceeding 20cm in trenches, plinth, sides of foundation etc complete. |
| 3 | Peovinding and laying spreading and compacting graded stone aggregate to wet mix macadam (WMM)specification etc allcom. |
| 4 | Construction of granular sub base (GSB) by providingcoarse graded material, spreading in uniform layer with mortor grader on prepared surface, mixing by mixin place method with rotovator at OMC and compacting with viberatory roller to achieve the desired density as per clause 401. |
| 5 | Providing and laying in position cement cocrete of specified grade excluding the cost of centering and shuttering - All work up to the plinth level in 1:2:4 (1 cement : 2 coarse sand (zone-iii) : 4 graded stone aggregate 200 mm nominal size |
| 6 | Additionalfor non metalic CC surface hardener etc.all complete. |
| 7 | Construction of gullypit of 0.60x0.60x0.75 m internal size with jali, labour, T&P etc, required for proper completion of work. |
| 8 | Laying cement concrete 1:5:10 in haunching S.W pipe including concrete for bedding necessary from work and curing complete (c) 200mm dia. |
| 9 | Making connection of pipe to the existing manhole/sewer line etc all complete. |
| 10 | Raising manhole by dismantling & refixing of manhole cover & frame including dimantling C.C. and C.C. work in 1:2:4 but excluding brick work which taken separately and all completion of work. |
| 11 | Brick work with common burnt clay (non modular) bricks of class-150 in foundation and plinth in cement mortar 1:4 (1 cement : 4 coarse sand) |
| 12 | 12 mm cement plaster of mix 1:3 (1 cement :3 coarse sand) finishes with a floating coat ao beat cment.(Sor-Ch no.13-6-13.9.1) |
| 13 | Construction of manhole chamber of 0.60x0.60x0.90m internal size with b/w, plaster, cover, C.I. sheet, labour T&P etc required for proper completion of work. |
| 14 | Scraping of tar road including refusal of dismantled material up to 60.0mtr distance as per directed by engg-in-charge. |
| 15 | Supply and fixing of manhole coller etc.all complete. |
| 16 | Providing and fixing of 55cm dia R.C.C. manhole cover with all charge complete. |
| 17 | Providing and laying damp proof course 40mm thick with cement concrete 1:2:4 (1cement : 2 coarse sand (zone-III) : 4graded stone aggregate) 12.5mm nominal size |
| 18 | Add 18 % G.S.T. |