| 1 | Carriage of materials by mechanical transport including loading, unloading and stacking: Lime, moorum, building rubbish:3 km Unit:cum ( S.l.No. : 1.1.1.3) Page No.: 62 |
| 2 | Carriage of materials by mechanical transport including loading, unloading and stacking: Steel:3 km Unit:tonne ( S.l.No. : 1.1.11.3) Page No.: 63 |
| 3 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. Unit:kg ( S.l.No. : 10.2) Page No.: 176 |
| 4 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.:In stringers, treads, landings etc. of stair cases, including use of chequered plate wherever required, all complete Unit: kg ( S.l.No. : 10.25.1 ) Page No.: 179 |
| 5 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.:In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works Unit: kg ( S.l.No. : 10.25.2) Page No.: 179 |
| 6 | Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer\"s specifications including appropriate priming coat, preparation of surface, etc. complete. :On steel work Unit:Sqm ( S.l.No. : 13.52.1) Page No.: 226 |
| 7 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade : :Two or more coats on new work. Unit:Sqm ( S.l.No. : 13.61.1) Page No.: 227 |
| 8 | Painting with aluminium paint of approved brand and manufacture to give an even shade . :Two or more coats on new work Unit:Sqm ( S.l.No. : 13.63.1) Page No.: 227 |
| 9 | Refixing old glass panes with putty and nails Unit:Sqm ( S.l.No. : 14.1) Page No.: 238 |
| 10 | Taking out wind ties from roof including cutting out rusted bolts, nuts etc. and removing materials to any distance within compound and stacking. Unit:Kg ( S.l.No. : 14.19) Page No.: 239 |
| 11 | Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates, bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50metres lead. Unit:Kg ( S.l.No. : 15.18) Page No.: 249 |
| 12 | Extra for dismantling trusses, rafters, purlins etc. of steel work for every additional span of one metre or part thereof beyond 10 metres Unit:units ( S.l.No. : 15.20) Page No.: 250 |
| 13 | Extra for dismantling trusses, rafters, purlins etc. of steel work for every additional height of one metre or part thereof beyond 5 metres. Unit:units ( S.l.No. : 15.21) Page No.: 250 |
| 14 | Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead of: :G.S. Sheet Unit:Sqm ( S.l.No. : 15.28.1) Page No.: 250 |
| 15 | Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead of: :Asbestos sheet Unit:Sqm ( S.l.No. : 15.28.2) Page No.: 250 |