| 1 | Erection Part of 11/0.4 KV, 100 KVA Transformer |
| 2 | Erection of 100 kva S/Stn. Str.:-Digging of Pit for Steel Pole and earthing, drilling of holes in X-arm, preparation of plate form str. Member CI,AI i.e X-arml, Knee bracing set, erection of D-pole, errection of plate form, erection of x-Arm, drop out, fuse unit, linghting arrestor, MCCB Switch of LT Box, Energy Meter, Erection of T/F, and earthing conn. to T/F G.O Switch lightning etc. erection of Stay Set, Erection of Jumper, Pipe earthing, Erection of LT cable, barbed wire and painting, 3 Nos. earthing to S/Stn. by prov. 50Kg Salt charcole in each earthing i/c construction of trench for earthing as per REC Board Standard complete in all respect. (Erection of 100 kva) |
| 3 | Providing and laying PCC Pit for Substation Earthing Cement Concrete 1:2:4 ( 1 cement : 2 sand : 4 graded stone aggregate 20mm nominal size) and 12mm Plastering, curing complete including cost of others material to used, Covered with Fiber cover complete in all respect Size (0.30 X 0.30x 0.50Mtr.) |
| 4 | Providing and layingCement Concrete 1:2:4 ( 1 cement : 2 sand : 4 graded stone aggregate 20mm nominal size) and curing complete including cost of form work and others material to used. Size (2.00x2.00x1.10 Mtr.) above ground level ) under ground deep 0.75 mtr) |
| 5 | Prov. & erection of Chain link fencing angle iron, Gate etc. for transformer fencing. |
| 6 | Prov. Filling of concrete in RCC muffs complete in all respect. |
| 7 | Supply Part of 11/0.4 KV, 100 KVA Transformer |
| 8 | Prov. Distribution Transformer (Ordinary), 11/0.4 kV,100 KVA |
| 9 | Prov. Steel Tubular Poles (9 m, Working Load > 200 kgf/m²) |
| 10 | Prov. RCC Muffs (2 Nos. Supply by HPSEBL) |
| 11 | Prov. X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] for incomer line |
| 12 | Prov. MS Angle Iron (50X50x6 mm), Length : 2800 mm x 1 Nos for LA. |
| 13 | Prov. X-Arm: [Channel Iron (75x40x6 mm), Length : 2800 mm X 4 Nos] for supporting DO fuse unit & GO switch |
| 14 | Transformer Belting & Knee Bracing |
| 15 | Prov. X-Arm [Channel Iron (100x50x6 mm), Length : 2800 mm x 2 Nos for Transformer Bed] |
| 16 | Prov. X-Arm [Channel Iron (100x50x6 mm), Length : 460 mm x 2 Nos for supporting main channel of Transformer] |
| 17 | Prov. MS Angle Iron (50X50x6 mm), Length : 2800 mm x 2 Nos |
| 18 | Prov. MS Angle Iron (35X35x5 mm), Length : 460 mm x 2 Nos |
| 19 | Prov. MS Angle Iron (50X50x6 mm), Length: 950 mm x(2 Nos for Bed Knee Bracing) |
| 20 | Transformer L.T Distribution Box and GO Switch fixing Assembly |
| 21 | Prov. MS Angle Iron (50X50x6 mm), Length : 2800 mm x 2 Nos |
| 22 | Prov. MS Angle Iron (50X50x6 mm), Length : 450 mm x 1 No. |
| 23 | Prov. GO Switch Handle supporting : [Channel Iron (75x40x6mm), Length: 460 mm |
| 24 | Prov. GO AB Switch Unit (11kV, 400A, 100 KA) Tripple Pole O/d Type |
| 25 | Prov. D.O Fuse Unit |
| 26 | Prov. Surge Arrester, 9 kV Station Class(Porcelain Type) |
| 27 | Prov. Discs insulator sets (comprising 1 No. Disc: ^^(Porcelain, BS, 12 kV, 90 kN) including Dead End Clamps etc.) |
| 28 | Prov. Stay set complete |
| 29 | Prov. Stay Wire (7/3.15 mm) (7.0 kg Per Stay Set) |
| 30 | Prov. Pipe Earthing Set |
| 31 | Prov. 6 SWG GI wire For Earthing |
| 32 | Prov. LT Distribution Panel Box with MS Sheet of 1.6 mm ( 900x800x200 mm ) cubide Box complete with stand etc and Al Busbar (25x6mm)inside .painted /powder coated after primar coating MCCB 160 amp 3P 35kA , ICS =100 % ICU, Kit-Kit 200 Amp for 100 KVA DTR |
| 33 | Prov. Half Clamp (M.S. Flat 50X6 mm) |
| 34 | Prov. Full Clamp (M.S. Flat 50X6 mm) |
| 35 | Prov. Nuts and Bolts of Various Sizes (Galvanised / Coated) [Preferably 16 mm Φ or more(with flat and spring washers)] |
| 36 | Prov. Aluminium Thimble (16 Nos. Supply by HPSEBL) |
| 37 | Prov. Copper Thimble 200 Amp |
| 38 | Prov. Danger Plate(1 No. Supply by HPSEBL) |
| 39 | Prov. Barbed Wire |
| 40 | Prov. LT Cable 3.5 X 120 mm² 1.1 kV XLPE Cable Unarmoured |
| 41 | Prov. LT Cable 3.5 X 185 mm² 1.1 kV XLPE Cable Unarmoured |
| 42 | Prov. LT Cable 3.5 X 300 mm² 1.1 kV XLPE Cable Unarmoured |
| 43 | Prov. Energy Meter 3-ɸ, 4 wire CT operated Static Tri- Vector meter with Box(CT-100/5A) Accuracy Class: 0.5S, Category-C, DLMS Compliant for 100 KVA Transformer |
| 44 | Prov. Aluminium Paint. |
| 45 | Prov. Red Oxide |
| 46 | Transportation and Loading of S/Stn. complete and allied materials on truck at Divisional Store and same material unloading at road head of site of work and Manual Carriage Of DTR and allied Material For Average Distance From Road To Site Of Work .(If required as per site). |