| 1 | Work of increasing the capacity of distribution transformers of different capacities and installing additional distribution transformers under the Business Plan Year 2024-25 (Part-2) under EDD-Karwi Chitrakoot. |
| 2 | 11 MTR LONG STP (Provided by the Dept.) |
| 3 | PCC POLE 8.5 MTR LONG (Provided by the Dept.) |
| 4 | LT XLPE CABLE 3.5X150SQMM (Provided by the Dept.) |
| 5 | LT XLPE CABLE 3.5X240SQMM (Provided by the Dept.) |
| 6 | 11 KV XLPE CABLE 3X185SQMM (Provided by the Dept.) |
| 7 | (3X95+1X70+1X16) SQ MM ABC (Provided by the Dept.) |
| 8 | LT AB Cable 3X.5X120 SQ MM (Provided by the Dept.) |
| 9 | 100KVA, 11/0.44 KV T/F (Provided by the Dept.) |
| 10 | 250KVA, 11/0.44 KV T/F (Provided by the Dept.) |
| 11 | 11 KV FUSE SET (Provided by the Dept.) |
| 12 | ACSR WEASEL CONDUCTOR FOR JUMPERING (Provided by the Dept.) |
| 13 | PIN INSULATOR WITH PIN(Provided by the Dept.) |
| 14 | DISC INSULATOR WITH FITHING(Provided by the Dept.) |
| 15 | DISTRIBUTION 1 PHASE (Provided by the Dept.) |
| 16 | DISTRIBUTION 3 PHASE (Provided by the Dept.) |
| 17 | STONE PAD 300X300X75 MM (Provided by the Dept.) |
| 18 | M.S. Base ANGLE 75X75X2028 MM With CLAMP andBOLT & NUT |
| 19 | M.S. TOP CHANNEL 125X65X2240MM, With CLAMP andBOLT & NUT |
| 20 | M.S. DROPPER CHANNEL 100X50X2028MM, With CLAMP andBOLT & NUT |
| 21 | EARTHING COMPLETE |
| 22 | 11 KV JOINTING KIT O/D 3X185SQMM |
| 23 | STAY SET COMPLETE (ROD+WIRE)WITH BOLT & NUT |
| 24 | I-HOOK |
| 25 | PEARCING CONNECTOR |
| 26 | LT CLAMP |
| 27 | D/POLE CLAMP |
| 28 | DEAD END CLAMP WITH NUT AND BOLT |
| 29 | CONCERETING OF POLES |
| 30 | CONCERETING OF STAY |
| 31 | Construction of new T/F Plinth Size 2x2x1.5 Mtr. including of first class brick sand cement etc. As per RESSPO manual |
| 32 | Fencing of Tranformerfor T/F including of first class brick sand cement & Iron material etc. As per RESSPO manual |
| 33 | Fixing & Commisioning of Pipe Earthing of Transformer By 2\" Dia 6 Meter length G.I. Pipe (body+netural) as per norms complete in all respect as per RESPO manual and as per direction of Engineer Incharge including the cost of labour, T&P and carrier etc. required for proper completion of work. (allmaterial shall be arranged by contractor) |