| 1 | Box cutting or filling in Road embankment in all sorts of soil including spreading the spoils properly over the flank as necessary or on berm to approximate grade & camber and rolling the sub-grade with power roller to proper camber and grade as per direction and satisfaction of Engineer-in-charge including uprooting and removing plants and jungles when and where necessary. a) Depth up to 150 mm. |
| 2 | By Mix in Place Method :Construction of granular sub-base by providing graded material, mixing by mix in place method with Rotavator at OMC, spreading in uniform layers with Motor grader on prepared surface in proper grade and camber, compacting with vibratory roller to achieve the desired density, including lighting, guarding, barricading, including cost of all materials, machinery, tools and plants including cost of quality control complete as per Clause 401 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).Grading – Vone layer |
| 3 | By Mix in Place Method :Construction of granular sub-base by providing graded material, mixing by mix in place method with Rotavator at OMC, spreading in uniform layers with Motor grader on prepared surface in proper grade and camber, compacting with vibratory roller to achieve the desired density, including lighting, guarding, barricading, including cost of all materials, machinery, tools and plants including cost of quality control complete as per Clause 401 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). Grading – II(1 Layer Compacted Thick) |
| 4 | Cement Concrete Pavement (laying manually)Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with cement content as per IRC: 15-2011, coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batch mix plant / RMC and appropriate weigh batcher using approved mix design (as per IRC:44 2008), laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing,spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, polysulphide sealant, dowel bars, near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days, using curing compound (where specified) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501 for Rural Roads of MORD. M 20 gradeWith RMC ( P-265, item 6.02 A) |
| 5 | Providing and fixing M.S information board of 1.2m x0 .75 m size made with 1.5 mm plate welded over angle iron (40mm x40 mmx5 mm) in both sides (Side stands) and (20mm x 20mm x 3 mm )in top and bottom and diagonal bracing with MS flat( 50mm x50 mm x6 |
| 6 | Add GST,as applicable @ 18% |
| 7 | Add Labour welfare cess @ 1% |