| 1 | Excavation of Pole pit of size 2\"x2\"x1/6 of the height of thepole upto 8 mtr pole by using JCBor Manual |
| 2 | Excavation of Pole pit of size 2\"x2\"x1/6\" of the height of the pole above 8mtr by using JCBor Manual |
| 3 | Excavation of pit in Hard soil (common to all size of poles) |
| 4 | Excavation of pit in Rocky area (common to all size of poles) by blasting /Manual |
| 5 | Excavation of Staypit2\"x2\"x5\"depthby using JCB or manual |
| 6 | Excavation of Staypit2\"x2\"x5\"depthin hard rock soil |
| 7 | Erection of RCCpoles/PSC poles/Metalpoles up to8.00 M (27\" ) by using JCB or manual |
| 8 | Erection of RCCpoles/PSC poles/Metalpolesabove 8.00 M by using JCB or maual |
| 9 | Erection of metal supports above 9m/RSJ/Rail pole/Tubular poles |
| 10 | Erectionofstaysetcomplete with fixing up stay wire EYE, bow, Guy shackle, Binding etc., |
| 11 | Erectionofadditional stay in the same rod, excluding excavation of stay pit and burial of stay rod |
| 12 | Erectionofstay set complete in the rock area by blasting |
| 13 | Fixing of HT\"V\" crossarms(all types) / channelcrossarms/guardingCrossarms |
| 14 | Fixing of LT 3 phasecrossarms |
| 15 | Fixing of LT Single phase cross arms |
| 16 | Fixing of HT/LTTIFittings |
| 17 | FixingofHTpinInsulators 11 KV/ 22 KV/ 33 KV |
| 18 | FixingofHT11 KVstraindisc. |
| 19 | FixingofHT22 KV/33 KVstraindisc. |
| 20 | FixingofLTpinInsulator |
| 21 | FixingofLTshackle |
| 22 | FixingofAluminium Knob |
| 23 | Earthing of pole with pin including looping binding and burying |
| 24 | EarthingofadditionalCrossarm |
| 25 | Fixingoftopchannel 10\" centre/15\" centre |
| 26 | Fixing of bed channel |
| 27 | Fixing of centre support for bed channel |
| 28 | Fixing of belting angle |
| 29 | Erection of 11 KV AB Switch |
| 30 | Erection of 11 KV Vertical type AB Switch for single pole DT |
| 31 | Erection of 11 KV HG Fuse set |
| 32 | Erection of 11 KV Solid core HG Fuse set |
| 33 | Feeder arrangements with open type fuse units |
| 34 | Fixing of HT LAS |
| 35 | Fixing of LT LAS |
| 36 | HT Jumpering complete for Transformer DT Structure |
| 37 | HT Jumpering complete for DP Structure |
| 38 | Fixingofcrossbracing(4 nos angles) 10\" Centre/15\" centre |
| 39 | Fixing of danger board |
| 40 | Erection of Transformer centre set arrangments |
| 41 | FixingofDistributionTransformerName Board (Nameofthe22/11KV #, Name of theSS and Capacity) including Supply of board (1\" x 1.5\" x 3 mm thickness) including the cost of paint and labour charges |
| 42 | Fixing of LT Cable arrangements while erectingsingle pole DT |
| 43 | Fixing of Earth coller for earth pits |
| 44 | Erection of Aluminium bus bar pipe complete for HT bus bar arrangements for DP structure |
| 45 | Erection of Aluminium bus bar pipe complete for HT bus bar arrangements for Triple pole and four pole structure |
| 46 | Fixing of 2 Tapping cross arm per cut point upto 33 KV line including fixing of discs insulators and jumpering etc., |
| 47 | Fixing of support insulator angle and erection of 3 nos Pin insulator |
| 48 | Fixing of MCD box |
| 49 | Paving and stringing of conductors of sizes upto 7/2.59 mm ACSR or other equivalent conductor |
| 50 | Paving and stringing of conductors ofsizes upto 7/3.35mm ACSR or other equivalent conductor |
| 51 | Paving and stringing of conductors of7/4.09mm ACSR or other equivalent conductor |
| 52 | Paving and stringing of conductors of7/4.72 mm Dog Conductor or other equivalent conductor |
| 53 | Releasing and reerection (resagging) of one run of conductors of sizes upto 7/2.59 mm ACSR or other equivalent conductor |
| 54 | Releasing and reerection (resagging) of one run of conductors of sizes upto 7/3.35 mm ACSR or other equivalent conductor |
| 55 | Releasing and reerection (resagging) of one run of conductors of size7/4.09 mm ACSR or other equivalent conductor |
| 56 | Releasing and reerection (resagging) of one run of conductors of size7/4.72 mm ACSR DOG or other equivalent conductor |
| 57 | Numbering of pole by using Enamel paint including cost of paint and painting charges (Numbering in black letters with yellow base by using stencils/skilled painters. The height of lettering shall be 40 mm for numbers and 50 mm for alphabets) |
| 58 | Painting of Cement Poles by Distemper coating including cost of distemper |
| 59 | Painting of iron Poles upto 36 ft length with double coats including cost of paint |
| 60 | Painting of iron Poles upto 40 ft 200/100 length with double coats including cost of paint |
| 61 | Paintingoftopchannel |
| 62 | PaintingofABswitch |
| 63 | Paintingcross Bracing(4 Nos. Angles) both 10\" & 15\" centre |
| 64 | PaintingofDistribution Transformer of all capacities (paint supplied by the Board) including clening of DT |
| 65 | PaintingofHGfuse. |
| 66 | PaintingofHTmeteringsetand Box |
| 67 | Painting of structure materials distribution transformer with aluminium paint of structure poles and writing of transformer details (Items 1 to 6 brush to be owned by the contractor) (Paint to be supplied by Board) |
| 68 | Painting of poles and all other metal parts while erecting D.P. Structure |
| 69 | Painting of pole and all other metal parts while erecting new single pole distribution transformer Structure |
| 70 | Service connection details painting |
| 71 | Structure Concreting ,Concreting of poles with size (2\"x2\"x5\") including cost of Cement ,20 mm jelly and Sandwith a mixture of 1:2:4and plastering of concrete with ratio 1:2 |
| 72 | Sleeveconcreting with size (2\"x2\"x3\") including cost of excavation Cement ,40 mm jelly and Sandwith a mixture of 1:3:6and plastering of concrete with ratio 1:2 including materials |
| 73 | Stay concreting of Stay with Size 1.5\" X 1.5\" X 3.0\" including cost of Cement, 40mm Jelly and sand (with supply) with mixture 1:3:6 along sleeve concreting and plastering of concrete portion above the ground level with ratio 1:2. |
| 74 | Erection of DP structure with stay as per TNEB Standard including fixing of top channel, cross bracing concreting, painting, colour washing etc., With 11 KV/22 KV/33 KV AB switch using all types of poles of size 9.14m and above length |
| 75 | Erection ofDouble Pole Transformer Structure complete as per TNEB standard including painting, feeders arrangement, colour washing of RCC poles etc., Fixing of poles type to be unit HT/LT LAS and jumpering 3 nos earth pits with earth trough except erection of DT |
| 76 | (i) Erection of 11 KV Single pole Transformer Structure including erection of DT complete with centre support |
| 77 | (ii) Erection of 11 KV Single pole Transformer Structure including erection of DT complete without centre support |
| 78 | (iii) Erection of 11 KV Single pole DP structure with stay as per TNEB Standard including fixing of top channel, cross bracing concreting, painting, colour washing etc., with single earth |
| 79 | Erection of Distribution Transformer including loading of Distribution Transformer at stores and erection at structure or Upto 100 KVA Distribution transformer / Metering set. |
| 80 | Erection of Distribution Transformer including loading of Distribution Transformer at stores and erection at structure Above 100 KVA to 250 KVA |
| 81 | Erection of Distribution Transformer including loading of Distribution Transformer at stores and erection at structure 500 KVA and above |
| 82 | Failed DT replacement below 100 KVA & 100 KVA and above |
| 83 | LTsplitneutralguarding |
| 84 | Flatguardingincludingfixingof2 Nos. crossarms HTLT |
| 85 | D.O.T. Crossing |
| 86 | RailwayCrossing ( cradle guarding). |
| 87 | Earthing of poles with GI wires 4 or 6 SWG by coil earthing |
| 88 | Provision of spike including earthing arrangement |
| 89 | Pipe earthing including excavation of earth pit and fixing earth pipe 3m length |
| 90 | Replacing the corroded earth pipes of transformer structure and replacing the earth wire completely with aluminium lugs for termination |
| 91 | Replacement of corroded earth pipe |
| 92 | EarthingofD.P.complete |
| 93 | Earthing of new single pole distribution transformer structure complete |
| 94 | Loading or unloading of Distribution Transformer Upto 100 KVA |
| 95 | Loading or unloading of Distribution Transformer above 100 KVA and upto 500 KVA |
| 96 | Loading or unloading of Metering set of all ratios |
| 97 | Loading or unloading of various sizes of poles REC, RCC, PSC pole upto 8.00 m length |
| 98 | Loading or unloading of various sizes of poles All REC, RCC pole above 8.00 m length |
| 99 | Loading or unloading of various sizes of poles Metal poles all sizes |
| 100 | Loading of Conductor |
| 101 | Unloading of Conductor |
| 102 | Loading / Unloading of Iron & Steel |
| 103 | Loading / Unloading of Oil |
| 104 | Loading / Unloading of line materials |
| 105 | Loading / Unloading of 11 KV strain disc |
| 106 | Loading / Unloading of LT Pin insulator shackle, guy shackle, LT Pin, Metal parts, HT pin etc., |
| 107 | Loading / Unloading of single phase meters |
| 108 | Loading / Unloading of three phase meters |
| 109 | Loading and unloading of cementbagof50Kg. |
| 110 | Loading and Stacking of Materials |
| 111 | Transportation of all types and sizes of poles and other associated materials from Road side to pole pit and vice versa upto 0.50 KM |
| 112 | Transportation of all type of poles by bullock cart or other vehicle (for all sizes of poles including loading and unloading) For a lead upto 5 KM |
| 113 | Transportation of all type of poles by bullock cart or other vehicle (for all sizes of poles including loading and unloading) For a lead Above 5 KM of lead of every KM |
| 114 | Transport of Metal pole of all sizes by head loads in hill areas from road side to pole pit location Upto 1 KM |
| 115 | Transport of Metal pole of all sizes by head loads in hill areas from road side to pole pit location Above 1 KM per each KM |
| 116 | Transporting of conductors of all sizes from road side to pit locations upto one KM of Conductor |
| 117 | (i) Transporting of Distribution Transformer / Line materials from stores to office / site upto 10 KM distance by engaging 1 Ton capacity Minidor (Lorry) |
| 118 | (i) Transporting of Distribution Transformer / Line materials from stores to office / site ABOVE 10 KM distance by engaging 1 Ton capacity Minidor (Lorry) |
| 119 | Erectionofstreetlightservice including fixure fitting |
| 120 | Erectionofstreetlightservice |
| 121 | FixingofnewSV/MV/LEDlampfittings |
| 122 | AssistingforsurveyofHT/LT |
| 123 | Hutservicefixing |
| 124 | Agriculturalservicefixing / service |
| 125 | Breaking and ReleasingofgrillsfromRCCPSC poles |
| 126 | Releasingofsingle phaseservicewire and re-fixing. |
| 127 | Releasingof3 phaseservice wire and(upto 50 HP)re-fixing. |
| 128 | Releasingof3 phaseservice wireand(above 50 HP)re-fixing. |
| 129 | Labourchargesforalterationof Back clamps tosuitfortheworks |
| 130 | Labourchargesforalterationof Stay clamps tosuitfortheworks |
| 131 | ProvidingLTbusbararrangementin distn. Trs. Structurelocation |
| 132 | FixingofmeteronLVsideofDT |
| 133 | Erectionofconcreteearthtubto DistributionTransformerearthpipe |
| 134 | Dismantlingofdetoriatedcables/Replacementof varioussize(95,120,185 Sq.mm) from Distribution TransformerLTbushingtoLT opentypeclampandprovisionof suitable lugsatboththeends. |
| 135 | DismantlingandErectionofLTopen typefuseunitAluminium clamps |
| 136 | DismantlingofDistn. Transformerfrom structure TransportingtospecialMaintenance assistingthespecialmaintenance crewinoverhaulingandreerectionatthe structure up to 8Kms |
| 137 | DismantlingofDistn. Transformerfrom structure TransportingtospecialMaintenance assistingthespecialmaintenance crewinoverhaulingandreerectionatthe structure above 8 Kms per km |
| 138 | ReleasingofACSR/AAACconductors fromconductordrumandcoiling ACSR 7/3.35, 7/2.59, AAAC7/2.50, 7/3.15 MM (Per/Km.) |
| 139 | Tidingofserviceconnectionwitherection ofclampjumperinLow tensionsingle phase SC/line,Aerial Board, Fuse unit and looping. |
| 140 | Tidingofserviceconnectionwitherection ofclamp jumperinLowtension three phase line, Aerial Board, Fuse unit and looping. |
| 141 | Renewalofjumperfrom22/11 KVline toAB switchtoHG Fuse, HG Fuse to Distn. TransformerwithPG clamps. |
| 142 | Cutting of coconut leaves /tree branches |
| 143 | Drilling of hole in channel only 3/4\" & 1\" per hole |
| 144 | Cutting of flat |
| 145 | Cutting of channel |
| 146 | Cutting of Angle |
| 147 | Cutting of pipe |
| 148 | RSJ polecutting |
| 149 | RSJ polewelding |
| 150 | Providing of line spacers for single phase line |
| 151 | Providing of line spacers for three phase line |
| 152 | Hiring Charges for JCB |
| 153 | Clearing ofJungle |
| 154 | Clearing of scrup in Yard (DT/SS) |
| 155 | Set right of all sizes of leaning of poles |
| 156 | Erection of LT Shunt Capacitor |
| 157 | Ground patrolling of HT lines during Breakdown |
| 158 | Rectification of snapped HT line during Break down |
| 159 | Rectification of snapped LT line during Break down |
| 160 | Erection of Single phase meters |
| 161 | Erection of Three phase meters |
| 162 | Monthly Maintenance of Distribution TransformerMaintaining Transformer yard and earth pits neat and tidy, Cleaning the entire transformer including the bushings,Checking the earth connections and watering the earth pits,Checking the oil leaks and reporting if any noticed,Reconditioning the breather (by reactivating Silicagel or replacing it if necessary), Checking the LT fuses and renewing them if necessary. |
| 163 | Quarterly Maintenance - Renewing the HG fuses |
| 164 | Quarterly Maintenance - Measuring the insulation resistance and Load currents |
| 165 | Annual Maintenance of Distribution TransformerLubricating the AB switches and checking their operation, Checking the lines and earth connections of AB switch, Checking the lines and earth connections of HT and LT lightning arresters, Checking the HV and LV bushing connections |
| 166 | SS Maintenance - Complete maintenance of Power Transformer of all capacities |
| 167 | SS Maintenance - Complete maintenance ofBreaker,CT/PT for 110 KV and above |
| 168 | SS Maintenance - Complete maintenance of Breaker,CT/PT for capacity less than 110 KV |
| 169 | SS Maintenance - Complete maintenance of Centre Rotating Switch 110 KV and above |
| 170 | SS Maintenance - Complete maintenance of Centre Rotating Switch below 110 KV |
| 171 | SS Maintenance - Replacement of Clamps of all sizes |
| 172 | SS Maintenance - Complete maintenance of LAS 110 KV and above |
| 173 | SS Maintenance - Complete maintenance of LAS below 110 KV |
| 174 | SS Maintenance - Replacement of Jumpers less than 1 metre |
| 175 | SS Maintenance - Replacement of Jumpers more than 1 metre |
| 176 | SS Maintenance - Maintenance of earth pits and watering |
| 177 | SS Maintenance - Cleaning of control and relay panels (Front,Back and inside) |
| 178 | SS Maintenance - Mainenance of Capacitor Bank cell |
| 179 | SS Maintenance - Replacement of capacitor bank cell |
| 180 | SS Maintenance - Replacement of PT Insulator |
| 181 | SS Maintenance - Replacement of Female/Male contact for 110 KV |
| 182 | SS Maintenance - Replacement of Female/Male contact for less than 110 KV |
| 183 | SS Maintenance - Maintenance of Battery |
| 184 | Dismantling of RCC, REC, PSC & metal poles upto 8 mt including the closing of the pit |
| 185 | Dismantling of RCC, REC, PSC & metal pole above 8 mt including the closing of the pit |
| 186 | For breaking the mass concrete of all supports |
| 187 | Dismantling of stay set complete including stay rod |
| 188 | Dismantling of stay set complete Without stay rod |
| 189 | Dismantling of conductors of sizes upto 7/2.59 mm ACSR or other equivalent conductor |
| 190 | Dismantling of conductor ofupto 7/3.35 including transporting the conductors to the nearest road side and stocking in coils |
| 191 | Dismantling of conductors of7/4.09mm ACSR or other equivalent conductor |
| 192 | Dismantling of conductors of7/4.72 mm Dog Conductor or other equivalent conductor |
| 193 | Dismantling of Transformer structure materials complete set and transporting the same from the location to the road side |
| 194 | Dismantling of V-Cross arm / Channel Cross Arm / Guarding cross Arm |
| 195 | Dismantling of 3 Phase Cross arm |
| 196 | Dismantling of Single Phase Cross arm |
| 197 | Dismantling of HT/LT Fitting |
| 198 | Dismantling of 11KV / 22KV / 33KV Pin insulator & 11KVStrain Disc |
| 199 | Dismantling of 22KV / 33KV Strain disc |
| 200 | Dismantling of LT Pin insulator |
| 201 | Dismantling of LT Shackle with hardware |
| 202 | Dismantling of Aluminium Knob |
| 203 | Loading and unloading of HT Cable including coiling and recoiling |
| 204 | Transport of 11 KV HT cable from departmental stores to work spot by engaging private vehicle upto 5 km |
| 205 | Transport of 11 KV HT cable from departmental stores to work spot by engaging private vehicle above 5 km |
| 206 | Excavation of cable trench 0.6 meters width and 1.2 meters depth including cost of providing sign boards, danger lights indication arrangements wherever necessary all lead,lift, labour and tools and plants etc., complete. Normal Road (earth) |
| 207 | Excavation of cable trench 0.6 meters width and 1.2 meters depth including cost of providing sign boards, danger lights indication arrangements wherever necessary all lead,lift, labour and tools and plants etc., complete. Tar road |
| 208 | Excavation of cable trench 0.6 meters width and 1.2 meters depth including cost of providing sign boards, danger lights indication arrangements wherever necessary all lead,lift, labour and tools and plants etc., complete. Concrete road |
| 209 | Laying of 11 KV 3X300 sq mm XLPE cable |
| 210 | Laying of 11 KV 3X120 sq mm XLPE cable |
| 211 | Covering HT cable by cement \"V\" trough after covering the cable with good loose earth including loading, unloading and transport from stores to site and letter painting of feeding details & Cable size onthe trough |
| 212 | Refilling with excavated earth layers well consolidated as per std specification including all materials, lead, lift etc., complete. |
| 213 | Transport back any balance cable, empty drums and other materials if any by engaging private vehicle including recoiling, coiling and loading and unloading at both sides from workspot to departmental stores (minimum 2 drums) upto 5 km |
| 214 | Transport back any balance cable, empty drums and other materials if any by engaging private vehicle including recoiling, coiling and loading and unloading at both sides from workspot to departmental stores (minimum 2 drums) above 5 km |
| 215 | Loading and unloading of LT Cable including coiling and recoiling |
| 216 | Transport of LT cable from departmental stores to work spot by engaging private vehicle upto 5 km |
| 217 | Transport of LT cable from departmental stores to work spot by engaging private vehicle above 5 km |
| 218 | Excavation of cable trench 45 cm width and 75 cm depth including cost of providing sign boards, danger lights, indication arrangements wherever necessary, lead, lift, labour and tools and plants etc., complete.Normal Road (earth) |
| 219 | Excavation of cable trench 45 cm width and 75 cm depth including cost of providing sign boards, danger lights, indication arrangements wherever necessary, lead, lift, labour and tools and plants etc., complete.Tar road |
| 220 | Excavation of cable trench 45 cm width and 75 cm depth including cost of providing sign boards, danger lights, indication arrangements wherever necessary, lead, lift, labour and tools and plants etc., complete.Concrete road |
| 221 | Laying of 4 X 240 sq.mm cable |
| 222 | Laying of 4 X 120 sq.mm XPLE cable |
| 223 | Laying of 4 X 25 sq.mm cable |
| 224 | Laying of 2 X 16 sq.mm cable |
| 225 | Refilling with excavated earth layers well consolidated as per std specification including all materials, lead, lift etc., complete. |
| 226 | Laying of HT UG Cable using Trenchless technique without pipes |
| 227 | Erection of pillar box including excavation of foundation pits as per standard specification 2 Nos pillar concrete walls, coping and earthing the pillars below ground level 1 feet and above 2 feet/3 feetfrom ground level including cost of all materials, cost of labours including electrical works, transportion, lead, lift complete etc.,Mini pillar boxes for 3 feet |
| 228 | Erection of pillar box including excavation of foundation pits as per standard specification 2 Nos pillar concrete walls, coping and earthing the pillars below ground level 1 feet and above 2 feet/3 feetfrom ground level including cost of all materials, cost of labours including electrical works, transportion, lead, lift complete etc.,4/6/8 way pillar box 3 feet |
| 229 | Erection of pillar box including excavation of foundation pits as per standard specification 2 Nos pillar concrete walls, coping and earthing the pillars below ground level 1 feet and above 2 feet/3 feetfrom ground level including cost of all materials, cost of labours including electrical works, transportion, lead, lift complete etc., 4/6/8 way pillar box 4 feet |
| 230 | Cleaning, painting with Aluminium paint 2 coats & numbering pillar box with feeder details.(Estimate sanction, mandatory) including cost of all materials. 8 way pillar box |
| 231 | Cleaning, painting with Aluminium paint 2 coats & numbering pillar box with feeder details.(Estimate sanction, mandatory) including cost of all materials.6 way pillar box |
| 232 | Cleaning, painting with Aluminium paint 2 coats & numbering pillar box with feeder details.(Estimate sanction, mandatory) including cost of all materials.4 way pillar box |
| 233 | Cleaning, painting with Aluminium paint 2 coats & numbering pillar box with feeder details.(Estimate sanction, mandatory) including cost of all materials.Mini way pillar box |
| 234 | Cleaning, painting with Aluminium paint 2 coats & numbering pillar box with feeder details.(Estimate sanction, mandatory) without materials. 8 way pillar box |
| 235 | Cleaning, painting with Aluminium paint 2 coats & numbering pillar box with feeder details.(Estimate sanction, mandatory) without materials. 6 way pillar box |
| 236 | Cleaning, painting with Aluminium paint 2 coats & numbering pillar box with feeder details.(Estimate sanction, mandatory) without materials.4 way pillar box |
| 237 | Cleaning, painting with Aluminium paint 2 coats & numbering pillar box with feeder details.(Estimate sanction, mandatory) without materials. Mini way pillar box |
| 238 | Dismantling of old 5/6/8 way pillar box including associated accessories, loading on the vehicle, transporting, unloading at stores and stacking. |
| 239 | Dismantling of old mini pillar box including associated accessories, loading on the vehicle, transporting, unloading at stores and stacking. |
| 240 | Maintenance of pillars works such as replacement of damaged insulators worn out stembolts, lugs, termination of cables and dressing. 8 way pillar box |
| 241 | Maintenance of pillars works such as replacement of damaged insulators worn out stembolts, lugs, termination of cables and dressing. 6 way pillar box |
| 242 | Maintenance of pillars works such as replacement of damaged insulators worn out stembolts, lugs, termination of cables and dressing. 4 way pillar box |
| 243 | Maintenance of pillars works such as replacement of damaged insulators worn out stembolts, lugs, termination of cables and dressing. Mini pillar box |
| 244 | Earthing of Pillar boxes 8/6/4 and mini pillar boxes |
| 245 | Earth Work Exacavation to the (Cable Route) required depth, width Normal |
| 246 | Earth Work Exacavation to the (Cable Route) required depth, width Tar |
| 247 | Earth Work Exacavation to the (Cable Route) required depth, width Concrete |
| 248 | [LT Cable fault rectification works] Laying of 4 X 240 sq.mm cable |
| 249 | [LT Cable fault rectification works] Laying of 4 X 120 sq.mm XPLE cable |
| 250 | [LT Cable fault rectification works] Laying of 4 X 25 sq.mm cable |
| 251 | [LT Cable fault rectification works] Laying of 2 X 16 sq.mm cable |
| 252 | Refilling the trench cable |
| 253 | Transport of all materials to attending the fault from office to site and site to office vice versa |
| 254 | Provision of joint 240/120 Sq mm |
| 255 | Provision of joint 25/16 Sq mm |
| 256 | Earth work Excavation to the required depth, width(cable route)is 1.2m x 0.6m respectively(As per prevailingPWLC Rates)Normal |
| 257 | Earth work Excavation to the required depth, width(cable route)is 1.2m x 0.6m respectively(As per prevailingPWLC Rates)Tar |
| 258 | Earth work Excavation to the required depth, width(cable route)is 1.2m x 0.6m respectively(As per prevailingPWLC Rates)Concrete |
| 259 | Laying of HT Cable /M (As per prevailing PWLC Rate)11 KV |
| 260 | Laying of HT Cable /M (As per prevailing PWLC Rate)33 KV 1 X 630 sqmm |
| 261 | Laying of HT Cable /M (As per prevailing PWLC Rate) 33 KV 3 X 630 sqmm & 3X 400 sqmm |
| 262 | Installation of terminations by employing private jointer in the absence of company jointer (intimation to be given to company through mail/company phone Nos and record to be maintained)11 KV 120/300 sqmm Indoor/Outdoor terminations |
| 263 | Installation of terminations by employing private jointer in the absence of company jointer (intimation to be given to company through mail/company phone Nos and record to be maintained)33 KV 1x630 sqmm Indoor/Outdoor terminations |
| 264 | Installation of terminations by employing private jointer in the absence of company jointer (intimation to be given to company through mail/company phone Nos and record to be maintained) 33 KV 3x400/3x630 sqmm Indoor/Outdoor terminations |
| 265 | Installation of joint by employing private jointer in the absence of company jointer (intimation to be given to company through mail/company phone Nos and record to be maintained) LT |
| 266 | Installation of joint by employing private jointer in the absence of company jointer (intimation to be given to company through mail/company phone Nos and record to be maintained) 11 KV |
| 267 | Installation of joint by employing private jointer in the absence of company jointer (intimation to be given to company through mail/company phone Nos and record to be maintained) 33 KV(1X630Sqmm) |
| 268 | Installation of joint by employing private jointer in the absence of company jointer (intimation to be given to company through mail/company phone Nos and record to be maintained)33 KV(3x400Sqmm) |
| 269 | Refilling with M- sand over the cable and joints cost ofM- sand PWD Schedule of Rate) 11 KV |
| 270 | Refilling with M- sand over the cable and joints cost ofM- sand PWD Schedule of Rate) 33 KV |
| 271 | Refilling labour charges /mtr (As per PWLC Rate) 11 KV |
| 272 | Refilling labour charges /mtr (As per PWLC Rate) 33 KV |
| 273 | Transporting of cables and joint kits from stores to site (whichever is applicable)11 KV |
| 274 | Transporting of cables and joint kits from stores to site (whichever is applicable)33 KV |
| 275 | Transporting of cables and joint kits from office to site (whichever is applicable)11 KV |
| 276 | Transporting of cables and joint kits from office to site (whichever is applicable) 33 KV |
| 277 | Engaging JCB For Excavation of Earth and Back filling the earth after rectification of fault11 kv |
| 278 | Engaging JCB For Excavation of Earth and Back filling the earth after rectification of fault 33 kv |
| 279 | Engaging Hydraulic compressor (Tractor) for Breaking concrete/Tar Roads (Wherever Necessary) 11 kv |
| 280 | Engaging Hydraulic compressor (Tractor) for Breaking concrete/Tar Roads (Wherever Necessary) 33 kv |
| 281 | Rental for de-watering pump as per PWD schedule of Rate (Wherever necessary) 11 kv |
| 282 | Rental for de-watering pump as per PWD schedule of Rate (Wherever necessary) 33 kv |
| 283 | Engaging Labour for Manual excavation and cleaning the trench, joint pit excavation and identify the cable in addition to engaging JCB 11 kv (Rs.562/-x 2 person) |
| 284 | Engaging Labour for Manual excavation and cleaning the trench, joint pit excavation and identify the cable in addition to engaging JCB 33 kv (Rs.562/-x 3 person) |
| 285 | Concreting after rectification of fault by using PCC 1:3:6 ( If applicable, with necessary justification & certification by concern Executive Engineer For reqd length,width and depth as per site condition) 11 KV/33 KV |
| 286 | Releasing the service connection cable from OH line, cutting the service cable of required length for terminating in the newly erected pillar boxesand handing over of released cable in section storesduring OH line to UG cable conversion works / LTUG 2x16 sqmm cable |
| 287 | Releasing the service connection cable from OH line, cutting the service cable of required length for terminating in the newly erected pillar boxesand handing over of released cable in section storesduring OH line to UG cable conversion works/LTUG 4x25 sqmm cable |
| 288 | Releasing the service connection cable from OH line, cutting the service cable of required length for terminating in the newly erected pillar boxesand handing over of released cable in section storesduring OH line to UG cable conversion works/LTUG 4x120 sqmm cable |