| 1 | Working Charges_ New Baby Well_for 500mm Intake Pipe |
| 2 | 100.52.S.1:Sub Data for providing Earth filled cement bags including cutting of the Earth, filling, conveying and placing in position. |
| 3 | 100.52.S.3:Sub Data for Supplying, conveying and covering using best quality polythene sheet on bund to protect bund from seasonal changes. |
| 4 | 100.52.S.4:Sub Data for Conveying and providing bamboo poles for reinforcing the temporary bund including the cost materials and labour charges etc. complete. |
| 5 | 100.3.1.11:Earthwork in open well excavation (in or under water) for wells of diameter up to 2.50m in all kinds of soil and conveying and depositing the spoil within initial lead of 50m and lift up to 1.5m including neat banking. |
| 6 | 100.7.1:Bailing out water with 5HP engine and pump set including conveyance to the site, erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil and other stores pay of staff etc., complete. |
| 7 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) |
| 8 | OD205728/2022-2023:DOWEL BARS - Supplying and providing MS dowel bars of size 12 mm dia (200 mm minimum inserted into rock ) including drilling holes of 16 mm dia to a depth of 0.3m in rock and filling the gap with cement grout( 0.10kg/each) etc. complete. |
| 9 | 5.7:Reinforced cement concrete work in well - steining excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand (Zone - III) : 3 graded stone aggregate 20 mm nominal size) |
| 10 | 5.9.12:Centering and shuttering including strutting, etc. and removal of form for:Well steining |
| 11 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more |
| 12 | 10.25.2:Item Shifted to Sub head 14 as item 14.73Item Shifted to head 14 as item 14.74Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works |
| 13 | 13.65.1:Painting with black anti- corrosive bitumastic paint of approved brand and manufacture to give an even shade:Two or more coats on new work |
| 14 | 100.52.S.5:Sub Data for Dismantling the sand / earth filled cement bag from the foundation site of bund, apron on both sides, counter wall and removing the sand/earth from the bag and disposing the damaged cement bags properly as per the direction of the department officers including all cost of labour charges etc complete. |
| 15 | Restoring Existing Baby Well_near 250mm AC Intake pipe |
| 16 | OD262019/2023-2024:Dismantling damaged pre cast RCC rings of size 1.5m inside dia. from existing baby well one by one using tripod and pulley carefully without damaging existing intake pipe and stacking same near existing pump house including head load, including all labour, machineries etc. and as per the direction of departmental officers. |
| 17 | 100.3.1.12:Earthwork in open well excavation (in or under water) for wells of diameter up to 2.50m in all kinds of soil and conveying and depositing the spoil within initial lead of 50m and lift from 1.5m to 3.0m including neat banking. |
| 18 | 100.7.1:Bailing out water with 5HP engine and pump set including conveyance to the site, erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil and other stores pay of staff etc., complete. |
| 19 | OD262512/2023-2024:Providing and placing in position precast reinforced cement concrete ring units, circular shapein 1:11/2:3 ( 1 cement : 1 1/2 coarse sand : 3 graded stone aggregate 10 mm nominal size), including flush or deep ruled pointing at joints in cement mortar 1:2 (1 cement : 2 Fine sand), making necessary holes of required sizes for carrying through service lines, weep holes etc., providing steel hooks for lifting etc, form work in precasting, handling, hoisting, centering and erection complete. including the cost of reinforcementand as per the direction of deptl. officers. |