| 1 | FEXIBLE PAVEMENT WORK |
| 2 | Construction of Embankment with Material Obtained from Borrow Pits Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading toequired slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 for Rural Roads of MORD.(Mode of measurement: pre works and post works) |
| 3 | Water Bound Macadam Base Course Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening / binding materials to fill up the interstices of coarse aggregate, watering including lighting, guarding, barricading and making necessary earthen bundh of one metre width on each side and preparing the bed by necessary cutting or filling, including cost of all materials and hire and labour charges of all men and machinery and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5th Revision)(ii) Grading-1 Aggregate (63 mm to 45 mm) Using Stone Screening Type B (11.2 mm)B. Manual Means (PakurVariety) |
| 4 | Water Bound Macadam Base Course Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening / binding materials to fill up the interstices of coarse aggregate, watering including lighting, guarding, barricading andmaking necessary earthen bundh of oneetre width on each side and preparing the bed by necessary cutting or filling, including cost of all materials and hire and labour charges of all men and machinery and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H(5th Revision)(iii) Grading-2 Aggregate (53 mm to 22.4 mm) Using Stone Screening Type B (11.2 mm)B. Manual Means (PakurVariety) |
| 5 | Prime CoatProviding and applying primer coat with Cationic Bitumen Emulsion of approved grade conforming to IS: 8887-1978 and requisite quantity on prepared surface of granular base including cleaning of road surface and spraying primer using Mechanical meansncluding cost and carriage of bitumen emulsion and all other incidental costs of work complete as per Clause 502 of Specifications for Road & Bridge Works of MoRT&H(5th Revision).(i) For WBM / WMM Surface: (SS-I)(with primer @ 0.70-1.0 kg/sqm) |
| 6 | Tack CoatProviding and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming to IS: 8887-1978 on the prepared surface cleaned with Hydraulic broom, moistening the surface including cost and carriage of emulsion, hire charges ofmachinery and labour, cost of fuel and lubricants all complete as per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).(i) On Granular surfaces treated with primer (RS-I)(Using Bitumen emulsion at the rate of 0.25 to0.30 kg per sqm.) |
| 7 | Open-Graded Premix Surfacing using Bituminous (Viscosity grade Paving Bitumen / Modified bitumen) Binder and Mobile Hot Mix Plant (Light Duty) Providing, laying and rolling of Open - graded premix surfacing of 20 mm thickness composed of 13.2 mm (@ 0.018 m³ per m²) and 11.2 mm (@ 0.009 m³ per m²) size stone aggregates, including thoroughly cleaning of the surface, screening, cleaning and pre-heating stone chips and fully pre-coating the same either using viscosity grade paving bitumen or cut-back or emulsion, carrying the mixture by any suitable arrangements, laying the mixture uniformly over the surface, including line, grade and level to serve as wearing course on a previously prepared base, including mixing in Mobile Hot Mix Plant (Light Duty) and thoroughly rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades including the cost and carriage of stone chips and matrix, heating the matrix, preheating the aggregates to required temperature and including the hire charges of Mobile Hot Mix Plant (Light Duty) and other machinery, pay of operators, cost of fuel and lubricants etc. complete to be followed by seal coat of either Type A or Type B as per Technical Specification Clause 508 for Rural Roads of MORD.(Pakur Variety) |
| 8 | Seal CoatB. Providing and laying Premixed Seal Coat (Type B) with approved quality sand/grit @ 0.6 m3/ 100 m2 and bitumen binder on thoroughly cleaned black top surface coated with tack coat, including heating and mixing cleaned sand/grit (100 % passing through 2.36 mm sieve and retained on 180 micron sieve) uniformly with bitumen binder, laying and spreading the mix at an uniform rate using suitable means, brushing the surface, if necessary, to ensure uniformity, followed by rolling with power roller including the cost and carriage of binder and aggregates, cost of heating the binder and aggregates and all other incidental charges, cost of fuel and lubricants, including hire charges ofmachineries, tools & plants required for construction and quality control complete as per Clause 511 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).II By Manual Means(Pakur Variety)With Hot Bitumen Binder (@ 9.80 kg / 10 sqm.) |
| 9 | Construction of Sub Base using Local Materials, spreading in uniform layers with Motor grader on prepared surface, including screening the metal as necessary, mixing by mix in place method with Rotavator at OMC, and compacting with vibratory roller to achieve the desired density, lighting, guarding and barricading including cost andcarriage of all materials and making necessaryearthen bundh of one metre wide on each side to protect the edges complete as per Clause 401 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).(i) For Construction of Sub Base by compacting 1stclass brick aggregates (40 mm down) andsand (in proportion of 60:40). |
| 10 | RIGID PAVEMENT |
| 11 | Dismantling of StructuresDismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specifications Clause 202 for Rural Roads of MORD. (II) By Mechanical Means a) Cement Concrete |
| 12 | Box cutting or filling in Road embankment in all sorts of soil including spreading the spoils properly over the flank as necessary or on berm to approximate grade & camber and rolling the sub-grade with power roller to proper camber and grade as per direction and satisfaction of Engineer-in-charge including uprooting and removing plants and jungles when and where necessary(a) Depth up to 150 mm. |
| 13 | Box cutting or filling in Road embankment in all sorts of soil including spreading the spoils properly over the flank as necessary or on berm to approximate grade & camber and rolling the sub-grade with power roller to proper camber and grade as per direction and satisfaction of Engineer-in-charge including uprooting and removing plants and jungles when and where necessaryb)For each additional Depth of 150 mm and part thereof |
| 14 | Construction of granular sub-base by providing graded material, mixing by mix in place method with Rotavator at OMC, spreading in uniform layers with Motor grader on prepared surface in proper grade and camber, compacting with vibratory roller to achieve the desired density, including lighting, guarding, barricading, including cost of all materials, machinery, tools and plants including cost ofquality control complete as per Clause 401 ofSpecifications for Road & Bridge Works ofMoRT&H (5th Revision).(ii) Grading – II |
| 15 | Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements, in any part of foundation of bridges / culverts with graded stone chips of appropriate nominal sizes, including screening and cleaning of coarse aggregates, fine aggregate (sand) conforming to proper grading zone, both of approved quality and cement, as necessary, cost of curing with water, including cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge, cost for quality control, sampling, testing etc. including cost of formwork but excluding reinforcement complete as per drawing and technical specifications. E PCC Grade M30 I) Using concrete mixer |
| 16 | Supplying and laying Polythene Sheet (150gm / sq.m.) over damp proof course or below flooring or roof terracing or in foundation or in foundation trenches. |
| 17 | iv) Providing and filling joint sealing compound as per drawings and technical specifications with coarse sand and 6% bitumen by weight |
| 18 | CROSS -DRAINAGE WORKS (300 MM DIA HUME PIPE) |
| 19 | Excavation for StructuresEarthwork in excavation for foundation of structures upto 3 m depth as per drawing and technical specification Clause 1104 for Rural Roads of MORD including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfillingwith approved material. |
| 20 | Sand filling in foundation trenches and at the back of abutments, wing-walls etc. with good local sand free from earth in layers not exceeding 15 cm. including inundating each layer by profuse water and poking and ramming layer by layer complete includingsupply of sand. Quality of sand is to be approved by the Engineer-in-charge |
| 21 | Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements, in any part of foundation of bridges / culverts with graded stone chips of appropriate nominal sizes, including screening and cleaning of coarse aggregates, fine aggregate (sand) conforming to proper grading zone, both of approved quality and cement, as necessary, cost of curing with water, including cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge, cost for quality control, sampling, testing etc. including cost of formwork but excluding reinforcement complete as per drawing and technical specifications.(Foundation) (a) M-20 Grade P.C.C.Using concrete mixer with Pakur variety stone aggregates |
| 22 | Plain / Reinforced Cement Concrete in Sub structure with coarse aggregates of appropriate nominal size and grading, fine aggregate (sand) conforming to proper grading zone, both of approved quality, cement and water reducing admixtures, as necessary, including labour, cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete as per drawing and technical specification including the cost of necessary form work and staging complete as per drawing and technical specifications. A. PCC Grade M20 (Sub-Stucture)(i) Height upto 5mI) Using concrete Mixer |
| 23 | Bedding for Pipe i) Type A (Concrete Cradle) BeddingLaying concrete cradle bedding with M15 Grade Cement Concrete as per Clause 1105 (i) for Rural Roads of MORD.Vide pg-282/11.02(i) |
| 24 | Providing and laying reinforced cement concrete pipe NP3 with Spigot Socket as per designing single row.Providing and laying reinforced cement concrete pipe NP3 with Spigot Socket for culvert on first class bedding of granular meterial in single row including filling with cement Morter 1:2 but excluding excavation , proctection work , backfilling and masonry work in head wall and parapets including pumping out water ,lighting , barricating, protecting etc. Complete as per Clause 1101.0 of specification for Rural roads (1st revision)(E) 300 mm dia Pipe |
| 25 | FURNITURE |
| 26 | Direction and Place Identification Signs with size more than 0.9 sqm size Board. Providing and erecting direction and place identification retro- reflectorised sign as per IRC :67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing and Clause 801 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).. |
| 27 | Providing and fixing of retro- reflectorised cautionary,mandatory and informatory sign as per IRC :67 made of high intensity grade sheeting vide clause 801.3,fixed over aluminium sheeting, 1.5 mm thicksupported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means ofproperly designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing andClause 801 of Specifications for Road & Bridge Worksof MoRT&H (5th Revision).ii) 60 cm equilateral triangle |
| 28 | v) 60 cm x 45 cm rectangular |
| 29 | vi) 60 cm x 60 cm square |
| 30 | R.C. Guard postSupplying fitting and fixing R.C. guard post 1.37m long with C.C. 1:2:4 with graded stone chips of 13.2mm down casting , curing complete including cost of providing 4nos.of 12mm dia. rod of length 1.54m as main reinforcement and 6 nos. of round shaped 8mm dia rods used as binders; the placing of the first binder should be at 75mm below the top finished surface and the other 5 nos of binders should be placed at 245mm c/c ; the guard post is of octagonal section withnscribed circle of dia 24cm at the base tapering to corresponding dimensions of 16cm at the top including two coats of painting with best quality synthetic enamel paint of approved make and grade to form 6 nos. horizontal alternate bands in white/tannery yellow and black to 90 cm length standing up above ground after mendinggood damages if any during striking off shuttering,making hole in ground of 47cm depth and 30cm. minimum dia, fixing the guard posts in the same holes and repacking the earth properly so as to keep the guard posts standing properly erect in correct position true to line and length including carriage of R. C. Guard Post with due care to the site including loading into the truck and unloading at site complete in all respect.With Pakur variety stone chips |
| 31 | ADD GST @18% |
| 32 | ADD CESS @1% |