Name of Work: Repair & Maintenance of Interlocking Designer Paver Block Footpath, (Length= 93.50 M, Breadth-1.2M), at Kulik Wildlife Range, Raiganj Division.
Sl. No.
Item Description
1
Cleaning and removing conservancy garbage mixed with rubbish & other filthy materials from the road side flank, drain and compound including cutting, loading, unloading to and from truck or cart by Mathor labour & removing the same to any distance.
2
Labour for taking out old soling edging including removing debris.(a) Single flat soling.
3
Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work).(iii) With carried earth arranged by the contractor within a radius exceeding 3 km. but not exceeding 5 km. including the cost of carried earth.
4
Extra for manual compaction of earth by rammers /hand roller in 250 mm layers including watering etc. if required. (Borrow pit measurement).
5
Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns,lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor.f) 25 mm to 30 mm shuttering without staging in foundation.
6
Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement,if any, in ground floor as per relevant IS codes.Pakur variety.
7
g) Extra rate for using local sand inlieu of powered earth in Single layer soling.
8
(c) 60 mm thick interlocking designer concrete paver block M- 35 grade for light-traffic zone,commercial & office complex,tourist resort as per IS: 15658-2006 (over 20-40 mm medium sand bed on 250mm thk WBM/ WMM base course & 250 mm thk bound gnaular /granular sub-base course including cost of sand for sand bed but excluding cost of base ,sub-base course & subgrade preparation). ii) Coloured Decorative
9
Add 18% extra in respect of GST on Rs.251719.69
10
Add 1% extra in respect of Labour Welfare Cess on Rs.297029.23
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.