| 1 | Safe carriage, loading and unloading of following material from ESC Daliganj, Lucknow to work site/J.E. dump store. |
| 2 | 11/0.4 K.V. 250 K.V.A. Transformer. |
| 3 | S.T. Pole 9/11 Mtr. Long. |
| 4 | 11 K.V. 3X120 Sq.mm. XLPE Cable. |
| 5 | ABC (3X120+1X95+1X16 Sq.mm.) |
| 6 | L.T. 1X400 Sq.mm. Cable. |
| 7 | 11 K.V. D.O. Fuse Unit. |
| 8 | 11 K.V. Pin Insulator composite type. |
| 9 | 11 K.V. Out door type Jointing kit (3X120 Sq.mm.) |
| 10 | Fabrication, Erection of Double Pole Structure on 11 mtr. long STP with necessary clamps, accessories required including fixing of Top Channel 125X65X6 mm. (2240 mm long) 01 nos., Dropper Channel 100X50 mm. (2028 mm long) 01 Nos. with arrangment of fixing of 06 nos. 11 K.V. Pin Insulators. Cross Bracing set of MS Angle 01 Nos. Grouting of 02 Nos of STP with cement, sand and brick ballast in ratio 1:4:8 (2X0.9 Cu.Mtr)and making plinth upto the height of 300 mm from ground.Painting of poles with primer and enamel paint as per RESPO specification complete in all respect. Providing Danger board, Name plate & Barbed wire. Earthing of both the poles. |
| 11 | Erection of Single Pole structure on 11 mtr. STP with fixing of necessary clamps and other accessories required for stringing along with plinthing, grouting & earthing of STP with cement, sand and brick ballast in the ratio 1:4:8 (0.9 Cu.Mtr each)upto the height of 300 mm. from the ground level. |
| 12 | Construction of masonary plinth suitable for 250 K.V.A. Transformer of size 2X2X1.2 Mtrs with complete civil material & 02 Nos.,100X50 mm, M.S Channel 2.0 Mtr. long and M.S Bar 8/10 SWG complete in all respect as per RESPO norms. |
| 13 | Fabrication and erection of wire mesh fencing 02 Mtr. height with a gate and with retaining wall including grouting of fabricated M.S. Angle 65X65X6 mm. support (05 Nos. in a Sub-Station). Painting of fencing/support with all material as per specification/drawing complete in all respect. |
| 14 | Placing of 250 K.V.A. healthy Transformer from out side of yard to plinth with the help of crain and T & P. |
| 15 | AB Conductor Stringing & sagging of 3 phase with necessary clamps, Eye hook, Suspension clamp, A-B type connector etc. on ABC New line as per RESPO specification and direction on E/I. ABC shall be supplied by department. |
| 16 | Laying of 11 K.V. XLPE Cable 3X120 mm2 in single circuit underground as per digging of earth pit of Size 0.60x0.90 with provision of Sand filling and Cover with side brick and Top with Stone pad. (11 K.V. XLPE Cable will be provided by deptt. only) |
| 17 | Lay down the LT PVC cable of size 1X400 Sq.mm. for making the both side, connection of Transformer after fixing the necessary clamps Lugs and other material required for completion of work including carriage from store center. |
| 18 | Earthing of 11/0.4 K.V Distribution Transformer body/neutral by way of boring and lowering of ISI marked two Nos. G.I pipe 1.5\" dia 20 m deep from the ground level with solid cone at the lower end of G.I pipe. One end of G.I strip of size 50X6 mm. will be connected with neutral and body of the Transformer & other end will be clamped & welded with G.I Pipe as per UPPCL norms (All the material will be arranged by contractor at their own cost.) |
| 19 | Hoisting of 11 K.V. XLPE cable 3X120 mm2. along with 5\" dia G.I. Pipe 03 meter long with required clamp etc.(All material provided by contractor) |
| 20 | Fixing of complete DO fuse unit for suitable sizes as per RESPO specification. |
| 21 | Supply and fixing of Distribution Box (Tailess Fuse Unit) with necessary (U-type spring contact, Copper Bus bar, Back Entry, Insulator etc.) for double ckt. |
| 22 | Supply and fixing of Tailess Fuse unit |
| 23 | Note :-1- All the material provided by contractor shall be as per norms of UPPCL/RESPO.2- One carriage including loading/unloading from dump site to pit site is included in scope of work.3- During execution of work all risk will be of the contractor.4- Contractor will provide all T & P, vehicle and man power.5- All the old and used material should be taken on book.6- The quantity may be vary ±10%.7- GST will be paid extra as legally applicable.8-The work should be carried out under Additional Bussiness Plan 2024-25. |