| 1 | Carriage offollowing Materialfrom store center or from any other place to the respective site of work Distence up to 75 km through the Kachha Pacca road including the work of its loading & unloading at the respective ends also including the work of its dragging etc. and also including the cost of labour, T & P and carrier etc. required for proper completion of work. |
| 2 | 8.5 Mtr PCC Pole |
| 3 | 11 Mtr STP |
| 4 | 13 Mtr STP |
| 5 | 400 KVA DT |
| 6 | ABC Cable for different size |
| 7 | 63/25 KVA DT |
| 8 | 100 KVA DT |
| 9 | Different Line Material ( Conductor, X-Arm,Channel, Insulator , G.I. Wire , Stay wire & Rod, Earth Rod , DB BOX etc.) |
| 10 | Supply & Erection of Following Material : |
| 11 | Suspension Clamp with N&B |
| 12 | Dead End Clamp with N&B |
| 13 | Piercing Connectors |
| 14 | Stay Insulator |
| 15 | Different Size Alluminum Lug |
| 16 | Eye-Hook clamp with N&B |
| 17 | DP Clamp with N&B |
| 18 | PG Clamp with N&B |
| 19 | X-Arm Holding Clamp with N&B |
| 20 | F- Clamp with N&B |
| 21 | Stone Pad |
| 22 | Anti Climbing Device as per RESPO Norms ( with Barbed wire ) |
| 23 | Danger Board as per RESPO Norms. |
| 24 | Erection of Following Materialincluding the work of complete H.T. fittings as per RESPO manual and as per direction of engineer Incharge including the cost of labour, T & P and carrier etc. required for proper completion of work. (With proper Earthing.) |
| 25 | Single Pole Structure of 8.5 Mtr PCC Pole |
| 26 | Double Pole Structure of 8.5 Mtr PCC Pole |
| 27 | Single Pole Structure of 11 Mtr STP Pole |
| 28 | Double Pole Structure of 11 Mtr STP Pole |
| 29 | Single Pole Structure of 13Mtr STP Pole |
| 30 | Double Pole Structure of 13 Mtr STP Pole |
| 31 | Stay Set |
| 32 | Laying of 11 KV XLPE Cable (Different Size ) inside HDPE pipe while using HDD Method . |
| 33 | Laying of 11 KV XLPE Cable (Different Size ) inside open trench( Sand & Brick will be provided by contractor ) . |
| 34 | Stringing of LT ABC ( Different size) as per RESPO Norms. |
| 35 | Installation of DB Box as per RESPO Norms. |
| 36 | Laying, Sagging, Stringing, Binding and Jumpering etc. of Weasal/Racoon /DOG conductor on the newly erected pole/ old poleas per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T & P, carries etc. required for proper completion of work. |
| 37 | Grouting of Pole as per RESPO Norms ( Cement, Sand , Blast Stone with the ration 1:4:8 will be provided by contractor ) |
| 38 | Grouting of Stay SET( Cement, Sand , Blast Stone with the ration 1:4:8 will be provided by contractor ) |
| 39 | Construction of Plinth for 400/250 KVA DT as per RESPO norms. |
| 40 | Mounting & Installation of 400/250 KVA D.T. as per RESPO noms . |
| 41 | Mounting & Installation of 100 /63/25 KVA D.T. as per RESPO noms . |
| 42 | Construction of Fencing with the help of MS Mesh & MS Angel for 400/250 kva DT as per RESPO Nnorms ( All required material will be provided by contractor along with fabrication work . ) |
| 43 | Earthing of Newely Installed D.T. with Earth Rod . |
| 44 | Chemical Earthing of Newely Installed D.T. ( All required material will be provided by contractor ) . |
| 45 | Guarding between two poles like single / double / Tri / Four Poles etc. to guard LT / 11 Kv / 33 KVLine, Road / River crossing ect. With G.I. wire 6 SWG and G.I. wire 8 SWGincluding fixing of guarding channel with clamp and Nut & Bolts etc. As per relevent drawing . |
| 46 | Dismantling of existing 33KV/11 KV / L.T. line and removal of all accessories & fittings from poles, re-rolling of conductor and proper stacking and Cartage of dismantled conductor & accessories from site of work to DVVNL, Store. |
| 47 | Dismentlling of Old 11 KV VCB from Control Room and shifting it to Outside control room in Substation premises. |
| 48 | Mounting & Installation of 11 KV Incomer Feeder with proper Earthing of Pannel |
| 49 | Re-Sagging of Old 11 KV / LT Line |
| 50 | Straightening of tilted Single Pole ( PCC & STP ) |
| 51 | Re-Nozaling of Old Stay Set. |
| 52 | Replacement of Damaged X-Arm / T-off Channel |
| 53 | Trimming of tree branches for clearing way of Electric Line . |