| 1 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 min width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth asdirected |
| 2 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) |
| 3 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) with 20 % boulders |
| 4 | Reinforced cement concrete work in beams, suspended floors, roofs having slope upto 15°, landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases upto five level including curing but excluding the cost of centring, shuttering, finishing and reinforcement with 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) |
| 5 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete |
| 6 | Cement concrete flooring 1:2:4 (1cement: 2 coarse sand: 4 graded stone aggregate) finished with a floating coat of neat cement including cement slurry and curing complete, but excluding the cost of nosing of steps etc. complete 40mm thick with 20 mm nominal size stone aggregate. |
| 7 | Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works. |
| 8 | Centering and shuttering including strutting, propping etc. and removal of form work for Foundations, footings, bases for columns |
| 9 | Centering and shuttering including strutting, propping etc. and removal of form work forSuspended floors, roofs, landings, balconies and access platforms |
| 10 | Centering and shuttering including strutting, propping etc. and removal of form work for Edges of slabs |
| 11 | carriage of Sand 68KM BY MT |
| 12 | carriage ofbazri6kmmt |
| 13 | carriage of stone 6KM by MT |
| 14 | ADD Cost of Display Board |