| 1 | Disconnecting the LT power line from motor terminal & necessary closing of suction & delivery valves,with proper care by using the adequate manpoweras per direction of the EIC. |
| 2 | Hiring charges for transportation vehicles for 12 Hrs @ Rs 250.00 (TATA 407 or equivalent) incl. driver, helper, fuel, mobil, all complete with all materials handling accessories, all necy. Valid documents as per MV Rules and to be used from Workshop to site incl loading & unloading as per direction of EIC. |
| 3 | Dismantling top cover of Horizontal Pump upto 415V, 132 KWafter decoupling from the motor & loosening / cutting the nuts, bolts & washers incl lifting & removing volute by using overhead crane etc as per direction of the EIC |
| 4 | Lifting the pump by use of over head crane incl Dismantling bearings from DE & NDE portion of pump along with removing of spares such as bearing cove jamnut, seperator gland packing, SS sleeve stationary & rotating end ring etc to be taken out from the shaft very carefully as per direction of the EIC. |
| 5 | Dismantling & taking out carefully the impeller unit of pump from casing carefully & placing it on the working bay as per direction of EIC. |
| 6 | S & F of rubber gasket of suitable size and thickness |
| 7 | Supplying, fitting, fixing bolts with nuts, washer of length upto 75 mm and 150 mm dia. |
| 8 | Supply delivery & fixing ofNeoprene rubber bush necessary for pump & motor coupling as per direction of EIC. |
| 9 | Supplying & replacement of following consumable materials for minor maintenance of all the electro mechanical equipments |
| 10 | Supply of Grease |
| 11 | Gland packing(12/20 mm) Champion make PTFE Style No 1094. |
| 12 | Supply, Delivery of following materials as per direction of the EIC |
| 13 | A. Supply of bearing ( Bearing no-6309-2RS1/C3 make- SKF |
| 14 | Reassembling & refixing the allaccessories bearings, bearing cover, gland packing, end rings & couplings etc after replacement of electro-mechanical damage parts and of the spares mentioned above with all accessories on the impeller shaft of pump carefully with the arrangement of proper tools& tackles/ machineries, shaft and spares should be thoroughly cleaned, polished and bearings to be properly lubricated with suitable grade lubricant as per direction of the EIC. |
| 15 | Allignment of the 132 KW pump motor set after necessary adjustment for required matching of faces to the flexible coupling within allowable tolerance. |
| 16 | Manufacturing of rotating end ring having specific dimension & housing the on CI imeller after making proper grooves at certain distance on the periphery of end ring & impeller, fitted the same on impeller with the help of giving required pressure to intact with each other as per direction of EIC. The cost of damage materials is adjisted in this item. |
| 17 | a. CI316 grade rotating end ring od-268mm Id-246mm span-40mm |
| 18 | Manufacturing of SS Shaft Sleeves and key nuts for the driving end and non-driving end and machining and threaded as per sample specification 225mm long x 80 mm inner diax 120mm outer dia including necessary transportation cost as per direction of the EIC. |
| 19 | Refixing of impeller after dynamic balancing in workshop as per IS rule after dismantling the same |
| 20 | Installation, testing, checking and commissioning of Horizontal Pump motor set 415V, 132 KWincl lowering down the pump set in existing Place (well/pit) with the help of using overhead EOT crane. This item also includes the arrangement for chain pulley block, tools, trackles, sundry materials and and their all type of necessary transportation. |
| 21 | Taking out the ACB panel and thoroughinspection & take preventive care after discharging incl taking out of its housing & refitting the same & re-fixing the ACB complete and testing and commisining as per direction of E.I.C |
| 22 | Servicing & overhauling up to 800A ACB incl complete servicing of breaker, cleaning moving of fixed contact & adjustment incl mechanial lever , greasing, oiling etc. anddisconnection of the armoured cable and cleaning the surface with carbon tetra chloride making cloth, emery paper and petrolum jelly to the socket terminaland tapping with the pvc tape after attaining the desired IR value incl Replacement of 700A, 690V ACsemiconductor fuse for soft starter feeder as per direction of E.I.C. |
| 23 | Dismantling all the terminals of the motor control panel and checking all the sockets on both side of panel,starter and capacitor bank including tapping as required and re-connections of the motor starter terminals after servicing of the panel and complete testing as per direction of E.I.C. |
| 24 | Servicing and overhauling,programming if necy the Soft starter for 120-180 HP motor after opening all components, electric timer,o/c relay,semiconductor fuse etc. & fitting, fixing the same after same plate servicing and overhauling testingas required as per direction of EIC |
| 25 | Complete servicing and overhauling and necessary repairing of upto DTH 250 Amps MCCB |
| 26 | Replacement of 440V AC5 KVAR Heavy duty capacitor in the existing Capacitor panel & making connection incl Less cost of old & unserviceable Items as per direction of EIC. |
| 27 | Replacement of Under voltage relay for LT incomer II as per directon of EIC. |
| 28 | Replacement of 15A SMPS having input voltage-180-265VAC and o/p voltage 24VDC max o/p power 450W & having over voltage, overload & short ckt protection within suitable range & o.p voltage adjustment from 24-30VDC & install the same within the existing LTMCC panel by proper arrangement as per direction of EIC. (Make-Micropower/ Meanwell/ Equivalent) |
| 29 | Add : GST@ 18.00% on Rs. 378387.80 i.e Total amount over item no. 1.00 to 24.00 |
| 30 | Add CESS @ 1.00% on Rs. 446497.60 i.e Total amount over item no. 1.00 to 25.00 |