Tender For Strengthening Of Bt Road At Ward No.10 Mariyamman Kovil Street To Ward No.6 Eswaran Kovil Odai In Sendamangalm Town Panchayat.
Tender Value
Ref. Documents
Estimated cost
Bid Submission
06 Nov 2024
0 days left
EMD
65000
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
sendamangalam → Tamil Nadu
EMD Exemption
Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender For Strengthening Of Bt Road At Ward No.10 Mariyamman Kovil Street To Ward No.6 Eswaran Kovil Odai In Sendamangalm Town Panchayat.
BOQ
| Sl. No. | Item Description |
| 1 | Picking the existing surface 3 to 5 cm deep removal of picked up staff to the side berms and using the useful metal to the road hand packing to camber sectioning levelling etc.,complete as per including labour charges for picking and other tools and plants etc., complete as per standard specifications. 404 ofMORTH |
| 2 | Providing and laying U/s Gravel to the specified thick including cost and conveyance ofU/s gravel from approved quarry and stocking the same at road side to Departmental guage for premeasurement as directed by the Departmental Officers including labour charges for spreading in layers not exceeding 75 mm thick (or) as specified by the departmental officers, levelling, sectioning etc., and all other charges for tools and plants employed for the work and all other incidental charges such as barricading and providing danger lights etc., complete as per standard specification. as per clause 301 & 305 of MORTH |
| 3 | Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadamspecification including premixing the materials with waterat OMC in mechnanical mix plant carriage of mixed material by tipper to site laying inuniform layers with paver sin Sub Base/Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Rev-5 |
| 4 | Providing and laying Prime Coat over WBM/WMM surface using 7Kg of Emulsion Bitumen (SS1) per 10sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,complete as per Clause 502 of MORTH Rev-5 |
| 5 | Providing and laying Tack Coat over WBM/WMM surface (treated with primer) using 2.50Kg of Bitumen Emulsion (RS1) per 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5 |
| 6 | Providing and laying 50mm consolidated thick Dense Bituminous Macadam using 0.24cum of 26.50-13.20mm,0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below and with 53.20Kgs of VG30/VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to work site, spreading the mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted by Vibratory/Pneumatic Roller to the required density etc., including labour for attending to paver at site etc., including hire charges and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher/9m paver finisher, Vibratory/Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 505 MORTH Rev-5 |
| 7 | Providing and laying Bituminous Concrete 30mm Consolidated thick using 0.13 cum of 19.00 – 9.50mm,0.17 cum of 9.50-2.36mm and 0.26 cum of2.36 mm & below with 50.30 kgs of 60/70 Grade Bulk bitumenfor premixing per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading themix to uniform thickness of 40 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit,labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M,Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 507 of MORTH Rev-5 |
| 8 | Providing and laying of Hot applied Thermo Plastic compound of 2.5mm thick including reflectorising glass beads @ 250 gm per sqm is exclusive of surface applied glass beads as per IRC :35, the finished surface to be level uniform and free from steaks and holes etc.as per MORTH 803 Rev. 5 |
| 9 | MAINTENANCETowards the charges for routine maintenance of the road work executed under NABARD SCHEME including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost. Clearing and Grubbing by LightJungle removing and disposing of all materials such as bushes, shrubs, stumps, roots, grass, weeds, top organic soil not exceeding 150mm in thickness as rubbish including all other incidental charges etc., complete as per MORTH Specification 111, 112, 201. Upkeeping 1st year (50%) |
| 10 | Upkeeping 2nd year (60%) |
| 11 | Upkeeping 3rd year (60%) |
| 12 | Upkeeping 4th year (60%) |
| 13 | Upkeeping 5th year (60%) |
| 14 | Earth Work excavating and deposting on bank with initial lead of 10m & initial lift of 2m in Hard stiff clay, Stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS20A for making up the berms. as per clause 111, 112, 201, 202, 301 to 305 & 900 of MORTH Vth Revision [Twice in a year] Upkeeping for 1st year (40%) |
| 15 | Upkeeping for 2nd year (40%) |
| 16 | Upkeeping for 3rd year (40%) |
| 17 | Upkeeping for 4th year (40%) |
| 18 | Upkeeping for 5th year (40%) |
| 19 | Tack coat- Providing and applying tack coat with bitumen emulsion (RS-I type) using emulsion pressure distributor at the rate of 0.20 kg/sqm on the prepared bituminous/ granular surface cleaned with mechanical broom as per clause 5034 th year 3% |
| 20 | 5 th year 5% |
| 21 | Providing and laying Bituminous Concrete 30mm Consolidated thick using 0.13 cum of 19.00 – 9.50mm,0.17 cum of 9.50-2.36mm and 0.26 cum of2.36 mm & below with 50.30 kgs of 60/70 Grade Bulk bitumen cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading themix to uniform thickness of 40 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit,labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M,Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 507 of MORTH Rev-5 4 th year 3% |
| 22 | 5 th year 5% |
AI Tender Summary
Tender Timeline
Oct 29, 2024
11:30 IST
Tender Published
Tender notice published.
CompletedNov 06, 2024
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedNov 07, 2024
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender