| 1 | Detail of Work |
| 2 | Safe cartage of ST poles 11 Mtr. from ESC, SRE/JE store to site of workincluding loading & unloading at both ends.(Dist.Up to 40 Km.) |
| 3 | Safely cartage of other complete line material(Except ST Poles/11 KV XLPE cable) from ESC, SRE/ JE store to site of workincluding loading, unloading at both ends.( Dist.UPto 40 Km.) |
| 4 | Safely cartage of11 KV XLPE cable size 3x120sq mm from ESC, SRE/ JE store to site of workincluding loading, unloading at both ends.( Dist.UP to 40 Km.) |
| 5 | Erection of double Pole on ST poles11 Mtr Longwith complete fitting with all accessories complete. |
| 6 | Fixing of 11 KV stay rods by digging of pits in block of 600X600X300 mm. &withnozzling of stay wire 7/10 SWG and fitting the same on the pole |
| 7 | Concreting of stay rod inratio 1:4:8 with Ist class brick ballast with cement, sand |
| 8 | Earthing of poles by earthing rod with GI wire. |
| 9 | Providing and Fixing of Stone Ped 300x300x75 |
| 10 | Providing ofAll type MS Clamp for ST poles with nuts bolts made of new MS flat iron 50x5 mm. |
| 11 | Providing ofnuts & bolts of various sizes. |
| 12 | Providingof11 KV cable terminationskit out doorof size3X120 sq mm. |
| 13 | Providing of HDPE Pipe 160mmdia |
| 14 | Providing of G.I. Pipe 100mm 4\"\" dia Class B |
| 15 | Removal of oldweaselconductorfrom the Existing 11KV lines with making roll of conductor and shifting the same to ESC, SRE/J.E store including loading and unloading at both ends. |
| 16 | Providing and fixing of Number plate with clamp on the each pole. |
| 17 | Providing and Fixing 11 KV Danger board with clamp nuts & bolts. for ST Poles made of3mm thick foam sheet (8\" X 6\") with |
| 18 | Providing and fixing of GI barbed wire on the each pole. |
| 19 | Providing ofRed oxide Paints (British/Asian/enamel paint) |
| 20 | Providingof Alluminium Paint (British/Asian/enamel paint) |
| 21 | Painting ofST poles 11 Mtr, SP-55with 2 coats of synthetic enamel paint after one coat of ready mix primer as well as rubbing/cleaning of surface as required for proper completion of work. and remaining by Aluminium paint including all channels/clamps etc. |
| 22 | Drilling of earthunder Road crossing1.5 mtr. Deepand laying of 2 No. Parreral HDPE pipe 160 mm dia on 0.5 meter distance by drill machine/JCB machine/ labour. |
| 23 | Laying of11 KV XLPE cable 3X120sq mm in the2 No. Parreral HDPE pipe 160 mm dia on 0.5 meter distance. |
| 24 | Fixing & Making of 11 KV Cable Heat shrinkable terminationskits of size 3x120 sq mm of outdoor. |
| 25 | Fixing of G.I. pipe 100mm 4\"\" dia 3.5 mtr. long at the both side of double pole. |
| 26 | Hanging ofcable onD/Pafter Fixing of outdoor terminations kits work as per site condition with jumpring complete. |
| 27 | Fabrication charges of Angle & Channal |
| 28 | Concreting of ST poles SP-55, 11 Mtr.long with cement concreting in bolck of 600X600X1500 MM. in ratio 1:4:8 with cement, sand and brick ballast size 1\"\"x1.5\"\" with plinth. |
| 29 | Dismantling of existingPCC poleafter opening of complete accessories. |