Tender For Flood Restoration Of Road Work -Pkg.No.Rj-06-02/ Roopbas-Uchchain/Flood Restoration/2024-25 Under Division Bayana
Tender Overview
Project Description
Tender For Flood Restoration of road work -Pkg.No.Rj-06-02/ Roopbas-Uchchain/Flood Restoration/2024-25 Under Division Bayana
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 29-Oct-2024 | Date Corrigendum | Date | 13-Nov-2024 |
| 2 | 06-Nov-2024 | pre meeting | Other | 13-Nov-2024 |
BOQ
| Sl. No. | Item Description |
| 1 | Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 1000 metres, scaking serviceable and unserviceable materials separately as per MoRTH specification claue : 202 by Mechanical mean:Bitumenious course |
| 2 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 3 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 4 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 5 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 6 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 7 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 8 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 9 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 10 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 11 | Clearing and grubbing road land including uprooting rank vegetation, grass, bush, shrubs, saplings and trees of girth upto 300mm, removal of stumps, disposal of unserviceable material and stacking of serviceable material upto 1000 m from road boundry as per MoRTH Specification : 201 By Mechanical Means In area of light jungle |
| 12 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 13 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 14 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 15 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 16 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 17 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 18 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 19 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 20 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 21 | Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead as per Technical Specification Clause 301.5 with lead upto - 50mtr |
| 22 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 23 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 24 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 25 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 26 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 27 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 28 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 29 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 30 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 31 | Providing and laying granular sub-base material having P.I.not more than 6, including compacted thickness and consolidation by 8-10 tonne power roller at OMC to achieve desired density to required camber and grade including cost of water and hire charges of machinery, including T&P and all lead of material from quarry (compacted thickness to be measured). Grading as per MoRTH specification : Grading as per MoRTH specification : Table 400-1,400-2 with CBR value not less than 30. To achieve 95% Proctor density |
| 32 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 33 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 34 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 35 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 36 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 37 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 38 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 39 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 40 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 41 | Providing, laying, spreadingand compactingstone aggregate of specific size as per table400-6 &400-7 to Water Bound Macadam specification including spreading in uniform thickness, hand packing, rolling with power roller 8-10 tonnes, in stages to proper grade and camber, applying and brooming requisite type of Stone screeningto fill-up the interstices of coarse aggregates, watering (with water browser) and rolling, making necessary earthenbund toprotect edegs,lighting, guarding,barricading and maintenance of diversion etc. [MoRTH specification:Clause 404] (bymanualmeans) with all leads (compacted thickness as specified to be measured) Grading no.2 (63-45mm) crusher broken |
| 42 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 43 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 44 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 45 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 46 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 47 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 48 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 49 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 50 | Providing, laying, spreadingand compactingstone aggregate of specific size as per table400-6 &400-7 to Water Bound Macadam specification including spreading in uniform thickness, hand packing, rolling with power roller 8-10 tonnes, in stages to proper grade and camber, applying and brooming requisite type of Stone screeningto fill-up the interstices of coarse aggregates, watering (with water browser) and rolling, making necessary earthenbund toprotect edegs,lighting, guarding,barricading and maintenance of diversion etc. [MoRTH specification:Clause 404] (bymanualmeans) with all leads (compacted thickness as specified to be measured) Grading no.3 (53-22.4 mm) crusher broken |
| 51 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 52 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 53 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 54 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 55 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 56 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 57 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 58 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 59 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 60 | Providing and applying primer coat over prepared surface or granular base with bitumen emulsion as per IS: 8887 & manufacturer’s specifications @ 7.5 kg /10 sqm with a self propelled or towed bitumen pressure sprayer equipped for spraying the material uniformly at specified rates and temperatures including cleaning of road surface as per MoRTH specification CIause- 502,112 |
| 61 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 62 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 63 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 64 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 65 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 66 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 67 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 68 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 69 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 70 | Providing and applying tack coat with bitumen emulsion on the prepared surface including cleaning as per IS : 8887 & manufacturer’s specifications @ 2.75 kg /10sqm with a self propelled or towed bitumen pressure sprayer equipped for spraying the material uniformly at specified rates and temperatures as per MoRTH specification CI.503,112 |
| 71 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 72 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 73 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 74 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 75 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 76 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 77 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 78 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 79 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 80 | Providing andlayingopengraded premix carpet 20 mm thick (compacted) on prepared surface in a single course as wearing course, aggregates as per Table 500-23, heating bituminous binder @ 14.6 Kg/10 Sqm. and aggregates in Hot Mix Plant (including cost of antistripping compound, wherever required),transporting the mixed material with tipper and laying with paver finisher to the required level and grade, rolling with power roller 8 - 10 tonne but excluding cost of tack and seal coat with lead for mix of material 1 km. (MoRTH Specification : Clause 511,112) with all lead In Hot Mix Plant 40-60 TPH, including loading of aggregates with F.E loader. with bitumen grade 60/70 |
| 81 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 82 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 83 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 84 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 85 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 86 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 87 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 88 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 89 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 90 | Add extra for adding Shreaded Plastic Waste as per Guidelines envisaged in IRC : SP:98-2013 over item of Open Graded Premix Carpet @ 8% of the quantity of Bitumen by Weight including mixing of aggregate and plastic waste in Hot Mix Plant ( The Bitumen content will be as per respective Clause of Morth Specifications), |
| 91 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 92 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 93 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 94 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 95 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 96 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 97 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 98 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 99 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 100 | Providing and applying premixed seal coat type \"B\" comprising of thin application of fine aggregate (0.06 Cum. per 10 Sqm) premix with 6.8 Kg. per 10 sqm bitumen binder (including cost of antistripping compound, wherever required)inmini hot mix plant 6-10 TPH and laying and rolling with power roller 8-10 tonne including all lead of mix material [MORTH Specification : Clause 513] with all lead with bitumen grade 60/70 |
| 101 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 102 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 103 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 104 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 105 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 106 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 107 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 108 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 109 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 110 | Construction of dry lean cement concrete sub- base over a prepared sub - grade with coarse and fine aggregate conforming to IS : 383, the size ofcoarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15 : 1, aggregate gradation after blending to be as per Table 600 -1, cement content not to be less than 150 Kg/Cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at7 days, mixed in a batching plant as per mix design, transported to site, laid with a hydrostatic paver with electronic sensor, compacting with 8 -10 tonne vibratory roller, finishing and curing complete as per MoRTHspecification |
| 111 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 112 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 113 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 114 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 115 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 116 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 117 | Construction of un-reinforced, without dowel bar, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per clause 1501.2.2 M30 (Grade), Coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with sholves, rakes, compacted using needle, screed and plate vibrators and finished in continous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, near approaches to bridge / culvert and construction joints, admixtures as approved, curing of concrete slabs for 14 days,using curing compound and water finishing to lines and grade as per drawing and MoRD specification clause 1501 including vaccum dewatering process with all required equipments. cement concrete M 30 grade |
| 118 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 119 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 120 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 121 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 122 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 123 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 124 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 125 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 126 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 127 | Dismantling upto 1.5m in foundation and/or 1.5m above ground level including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material, and stacking serviceable material withina lead of 1000m. [MoRTH Spe |
| 128 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 129 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 130 | Providing, laying & fixing in position RCC spun or hume pipes ISI marked with proper jointing in required slope packed in the gasket of hume or spun yarn and neatly finished with rich grout of cement moratar 1:3 or having flexible rubber ring joint made with prefectly air and water tight including testing of joints as per MoRTH Specfication : Clause : 1000 & 2900 NP - 3300 mm dia |
| 131 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 132 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 133 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 134 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 135 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 136 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 137 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 138 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 139 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 140 | Earth work in excavation including stacking/ disposal of surplus earth with all lifts and lead upto 1000 meters exclusive of compensation of earth (MoRTH specification Clause 301 to 305). In ordInary soil mechanically by power shovel including mechanical loading and carriage upto 1 km by tipper/dumper |
| 141 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 142 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 143 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 144 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 145 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 146 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 147 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 148 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 149 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 150 | Providing and laying mechanically mixed and vibrated Cement Concrete in foundation upto a depth of 1.5 metres below ground level and 1.50 metres above Ground/Bed level as per MoRTH Specification : Clause 1000 & 1700 P.C.C. 1:3:6 mix with crushed stone aggregate 20 mm nominal size. |
| 151 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 152 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 153 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 154 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 155 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 156 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 157 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 158 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 159 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 160 | Stone masonry work in cement mortarwith mechanical mixer for foundation (any level) complete including all scaffolding etc. but excluding pointing and plastering as per drawing and technical specification as per MoRTH Specification : Section 1000,1400 In CM 1:4 Random rubble masonry |
| 161 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 162 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 163 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 164 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 165 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 166 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 167 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 168 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 169 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 170 | Providing and laying cement concrete coping 1:2:4 mix, complete as per specifications, 75 mm thick |
| 171 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 172 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 173 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 174 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 175 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 176 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 177 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 178 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 179 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 180 | Providing Cement pointing 1:2 flush Raised and cut pointing on stone work in CM 1:2 (1 cement : 2 sand) as per MoRTH Specfication : Clause 1000 & 1300 |
| 181 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 182 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 183 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 184 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 185 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 186 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 187 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 188 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 189 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 190 | Construction of Pedestal of size 5.50\" x 5.50\" x 1.25\" in stone masonary in CM 1:6 as per design and drawing complete with 25 mm thick plaster in CM 1:4 plaster and weather coat paint |
| 191 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 192 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 193 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 194 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 195 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 196 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 197 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 198 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 199 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 200 | Supply & Fixing of one side polished Black granite stone 20 mm thick of size 3\" x 2\" with engraved and gold colour painted letter ( upto 200 letter) & border as per direction of engineer in charge on existing pedestals including transportation |
| 201 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 202 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 203 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 204 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 205 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 206 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 207 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 208 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 209 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 210 | P& F Mukhya Mantri Sadak Yojana logo for roads funded by State road fund having M.S. Definition plate of 1.6mm thickness frame to steel hollow dsection of 75mm x 75mm, 2.5m long stove enamelled paint with hold fast including paint logo as per approved design and colours. The logo shall be made out of 1.6mm thick circular plate fix on 1200mm x 150mm rectangular steel base plate 1.6mm thick, the base of circular shall be plain at the junction of base plate. The size of definition plate shall be 1500x600mm and embedding the posts by M-15 mix C.C. block 300x300x600 mm including lettering / writing and painting etc. complete in all respect |
| 211 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 212 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 213 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 214 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 215 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 216 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 217 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 218 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 219 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 220 | Supply of direction and place identification sign boards made out of 2mm thick sheet framed to angle iron 40 x 40 x 5 mm and two vertical posts of angle size 65 x 65 x 6 mm, 3 m long with hold fasts, stove enamelled paint and reflective letters,numerals,symbols etc. complete of size : 1200 x 750 mm |
| 221 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 222 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 223 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 224 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 225 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 226 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 227 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 228 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 229 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 230 | S & F in position precast R.C.C. stone (M-15 mix) of standard IRC design including finishing in cement sand mortar 1:3, painting with enamel paint, printing letters and numerals etc. complete (MoRTH specifications clause : 800) |
| 231 | Ordinary Kilometer Stone |
| 232 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 233 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 234 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 235 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 236 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 237 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 238 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 239 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 240 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
| 241 | 200 m stone |
| 242 | Jagner road to samahd km 0/0 to 4/500 (Permanent Restoration) |
| 243 | Milswa to kheriya Billonch o/o to 1/750 (Permanent Restoration) |
| 244 | A/R to Kheriya Jat KM 0/0 to 3/18 (Permanent Restoration) |
| 245 | Kheriya Mod To Bhawanpura 0/0 to 2/00 (Permanent Restoration) |
| 246 | Madapura Road To Nagala Bosoli KM 0/0 to 3/900 (Permanent Restoration) |
| 247 | Pichuna to nagla peetu upto nagla chhatri km 0/0 to 4/100 (Permanent Restoration) |
| 248 | Raseelpur To ratua KM 0/0 to 1/850 (Permanent Restoration) |
| 249 | Sakkarpur to Ibrahimpur km 0/0 to 2/0 (Permanent Restoration) |
| 250 | Supra to Nagla Bosoli 0/0 to 1/200 (Permanent Restoration) |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedCorrigendum-2 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender