| 1 | Replacement of 33KV Feeder No. - 2 Overhead Line emanating from 132/33 KV S/S Surajpur, Noida. |
| 2 | Safe carriage of following stock material, from any of the Store Center of PVVNL to work siteincluding Loading from Store and safe unloading at site for Item No. 3 to 16 |
| 3 | 3x300 SQMM 33KV XLPE AL. CABLE |
| 4 | 33KV O/D CABLE JOINTING KIT FOR 3x300 MM2 XLPE |
| 5 | STP POLE 13 Mtr SP-70 |
| 6 | EARTHING OF POLE BY MS ROD OF 20x2500 mm. AND 6 SWG EARTHING WIRE etc. |
| 7 | 33KV V-TYPE STEEL CROSS-ARM |
| 8 | ACSR PANTHER CONDUCTOR |
| 9 | ACSR DOG CONDUCTOR |
| 10 | 33KV LINE ISOLATOR |
| 11 | STRUCTURE OF LINE ISOLATORE |
| 12 | CONTROL CABLE 4x2.5 sqmm |
| 13 | CONTROL CABLE 2x2.5 sqmm |
| 14 | 33KV VCB 1250A |
| 15 | CT 400/200/1A |
| 16 | 33KV CONTROL PANEL FOR SINGLE FEEDER |
| 17 | Errection of above Following material and Supply and errection of the DE-CENTRALISED material for completing the works as per RESPO. |
| 18 | The excavation of foundation pit in mix soil/normal soil/soft soil & hard rock as per site condition and its back filling and leveling etc. The size of the pit will be (750x450)mm and having depth of 1/6th of the full length of the support. Erection of support, complete with providing & fixing of all G.I.Clamps size of 75x10mm, 65x8mm, G.I.Nut bolt & washer, P.G.Clamp, Stone Pad, Al. Binding wire, \"E\" bracket 75x10mm, and other accessories as per drawing. The work includes carriage and handling of supports from sectional store to pit site as well as any fabrication work if required & fixing of cross bracing sets 4.3mtr long, from G.I.Angle 65x65x6mm. The work includes cutting holes and providing G.I.Bolt of 16x40mm size, in the middle of the cross bracing with 01No. spring washer of proper size as per drawing/ as per schedule.Double Pole Structures(a)ST POLE 11MTR LONG |
| 19 | The excavation of foundation pit in mix soil/normal soil/soft soil & hard rock as per site condition and its back filling and leveling etc. The size of the pit will be (750x450)mm and having depth of 1/6th of the full length of the support. Erection of support, complete with providing & fixing of all G.I.Clamps size of 75x10mm, \"F\" bracket 75x10mm, G.I.Nut bolt & washer, Stone Pad Al. Binding wire and other accessories as per drawing. The work includes carriage and handling of supports from sectional store to pit site as well as an fabrication work if required.Single Pole(a) PCC POLE- 8.5MTR LONG |
| 20 | Grouting of supports in CC 1:3:6 (Cement, sand & 20mm stone grift). Grouting will be done in the block of size (450x450)mm x1/6th of full length of the support, upto ground level, 300mm plinth above the ground level with C.C. 1:3:6 (Cement, Course sand and Stone grift) with muffing as per RESPO. Work includes back filling and proper ramming.Single Pole and Double Pole(a)ST 11MTR LONG AND PCC POLE 8.5MTR |
| 21 | FIXING OF 33KV VTYPE CROSS ARM AS PER SITE REQUIREMENT |
| 22 | FIXING OF 33KV LINE ISOLATOR WITH FABRICATION OF STRUCTURE AFTER MAKING FOUNDATION WITH COMPLETE WORK IN ALL RESPECT. |
| 23 | CONNECTING OF CONTROL CABLE 4X2.5SQMM AS PER SITE REQUIREMENT |
| 24 | CONNECTING OF CONTROL CABLE 2X2.5SQMM AS PER SITE REQUIREMENT |
| 25 | INSTALLATION, FIXING AND COMMISSIONING OF NEW 33KV VCB1250AMP. WITH MAKING OF FOUNDATION AND COMPLETE WORK AND CONNECTIONS IN ALL RESPECT. |
| 26 | INSTALLATION AND FIXING OF CT 400/200/1AMP. AS PER SITE REQUIREMENT WITH CONNECTING CONNECTIONS IN ALL RESPECT. |
| 27 | INSTALLATION, FIXING AND COMMISSIONING OF 33KV CONTROL PANEL FOR SINGLE FEEDER WITH MAKING OF FOUNDATION AND COMPLETE CONNECTIONS IN ALL RESPECT. |
| 28 | Supply of 140mm OD PN-4-PE-80 Grade UV Stabilized HDPE Pipe.(PVVNL GTP APPROVED) |
| 29 | Drilling of dia 220 mm in two parallel bores for Double Curcuit by trenchless method by horizontal boring machine at a depth of 1.50 mtrs to 2.50 mtrs. (as requirement at site) below the ground level with complete work in all respect as per RESPO. |
| 30 | Laying ofHDPE Pipe PE-80, PN-4, DN-140mm dia by HDD trenchless method for 33KV, 3x300sq.mm XLPE cable as per site requirement. (PVVNL GTP APPROVED HDPE PIPE SHALL BE SUPPLIED WITH INSPECTION.) |
| 31 | Laying and commissiong of 33KV 3X300sqmm XLPE CableDouble Ckt. in HDPE Pipe dia after digging HDD trenchless methodboring including complete connections at both ends after providing and crimping of lugs of proper size for completion of work.as per site requirement. |
| 32 | Digging of pits of size 4 mtr x 4 mtr x 1.5 mtr for cable loop and making risers at double pole and re-filling of pits in proper manner with required material at kacha/pakka and hot mix road. (All Work and materialin the scope of contractor) |
| 33 | Laying and commissiong of 33KV 3x300sqmm XLPE CableDouble Ckt. in HDPE Pipe after digging trenchof dia 220 mm in two parallel bores for Double Curcuit by manual method at a depth of 1.50 mtrs to 2.50 mtrs. (as requirement at site) below the ground levelfor laying cable and refilling of trench including connections at both ends after providing and crimping of lugs of proper size for completion of work and Providing & Laying of Ist Class Bricks, along the length on both side of 33KV XLPE Cable in Cable Trench (minium 18No. Bricks/Mtr per Cable) and Stone Slab of size 450x600x50mm on top of the each Cable, Providing 150 thickness mm River sand for cushion beneath and 150mm above the cable and Back filling of excavated earth in the cable trench upto the ground level and ramming properly. |
| 34 | Preparation and Fixing of 33 KV Power Cable ends:Making and Fixing of 33 KV XLPE Heat shrinkable outdoor jointing kits suitable for 3x300sqmm XLPE Cable after duly plumbing and taping of cable, providing, fixing and crimping of proper size good quality lugs with complete connention in all respect. |
| 35 | Driving of MSearth rod of size20x2500 mm in earth andjointing through G.I. wire of 6 SWG between support and earth electrode by providing proper size of bolts and nuts for pole earthing. Supply Erection, fixing, grouting of stay rod in cement, sand and brick ballastin ration 1:4:8 in Block 600*600*300 mm with binding & nuzzlingincluding providing & fixing of stay insulator complete in all respect with grouting. |
| 36 | Laying, connecting, spreading, lifting and final sagging of Panther conductor in accordance with Line chart includidng binding and fixing of all accessoriesas per site requirement with complete work in all respect. |
| 37 | Laying, connecting spreading, lifting and final sagging of 3 OR 4phases ACSR Dog conductor in accordance with Line chart includidng binding and fixing of all accessories in 03Nos OR 04 Nos. Conductor in parallel as per site requirement. |
| 38 | Providing and Fixing of GI Pipe 6\" Dia as per site requirement. |
| 39 | Providing and Fixing of PG Clamp Panther to Panther. |
| 40 | Providing and Fixing of Ms Holding Clamp as per site requirement. |
| 41 | GI Pipe Earthing of VCB, CT and Control Panel as per RESPO. |
| 42 | Providing and Fixing of MS Nut Bolt as per site requirement. |
| 43 | Road Cutting and Road Restoration Charges for the above work. |
| 44 | Removal and Dismentaling of old and used conductor from the site and safe carriage of its from the site to Any store centre of PVVNL including loading and unloading both ends. |
| 45 | Removal and Dismentaling of old and damaged ST Pole from the site and safe carriage of its from the site to Any store centre of PVVNL including loading and unloading both ends. |