| 1 | [11.67.1]Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface : 1. Water thinnable cement primer [Through Rate] |
| 2 | [11.73.2]Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer`s specifications including appropriate priming coat, preparation of surface, etc. complete. 2. On concrete work [Through Rate] |
| 3 | [4.14.1]Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 1. All kinds of soil. [Through Rate] |
| 4 | [6.1.1]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 1. 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 5 | [6.16]Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor four level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III): 3 graded stone aggregate 20 mm nominal size). [Through Rate] |
| 6 | [6.30.16.1]Centering and shuttering including strutting, propping etc. and removal of form for 16.1. Edges of slabs and breaks in floors and wallsUnder 20 cm wide [Through Rate] |
| 7 | [6.33.3]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 3. Cold twisted bars [Through Rate] |
| 8 | [9.2]Hoisting R.C.C. battens and placing in position up to floor IV level [Through Rate] |
| 9 | Providing and fixing GI barbed wire fencing including cost of material labour complete in all respect |