| 1 | Site Development (Site Clearance)a. Cleaning of unwanted materialb.Cleaning of waste water and rubbish ANNEXURE 1 |
| 2 | Geotechnical Survey Equipment charges per day Standard Penetration tests (SPT) were conducted in these boreholes and relevant soil samples were collected. Soil tests were carried outin the laboratory to ascertain the allowablebearingcapacityofencounteredstrata.To conducttestsondifferent samplesinthelaboratoryas such as grain size Analysis, Atterberg limit, density, Consolidation test , shear properties, natural moisture and determining the engineering characterstics ANNEXURE 2 |
| 3 | TS 3 Bin Civil Workswill be paid as per ietm work ANNEXURE 3 |
| 4 | UG Sump ANNEXURE 4 |
| 5 | RCC Drain ANNEXURE 5 |
| 6 | RFRC Road (CC platform for Approach) ANNEXURE 6 |
| 7 | Leachate Collection Pit ANNEXURE 7 |
| 8 | Supply, Fabricate and erection of Structural shed with AZ-150/SDP incuding turbo vent and sky light PEB STRUCTURE ANNEXURE 8 |
| 9 | Epoxy Paint on floor for leachate drainout : Supply and applyingepoxypaint overlevellingcourseon cleaned surfce including all materials, labour charges, etc., complete finished item and as directedbyengineer-in-charge ANNEXURE 9 |
| 10 | Entrance & Exit Gate - 7.00m wide ANNEXURE 9 |
| 11 | S/C for Supply and fixing of Ventilated GI rolling shutter with neat finishing and fireproofing and installation Providing and fixing Automatic rolling shutter power-driven with pull&pushtypeprovisionforrollingshuttersof approved make out of 18 gauge, 75 mm wide cold rolled steellathsofconvexcorrugation,with sideguidesand bottom rail, with interlocking arrangements of steel laths bymeansofalternateclips,suspensionshaftwithHigh tensioncoiltypespringstwonumbers,mountedon specially designed pipe shaft, with bracket plates, guide channels,ballbearingarrangements,forinside&and outside locking with push & and pull operations complete with all necessary fixtures and tools at site as required bythe client.ANNEXURE 9 |
| 12 | Supply and Fixing of Name Board and MS Fabrication workwith flexible board with all necessaryitems. ANNEXURE 12 |
| 13 | Water supply, hand wash, drinking water submersable pump ANNEXURE 9 |
| 14 | SecuritypostSupplyandfixingofSecuritypostwith necessary furniture will be installed at the required locationand as instructed by client. ANNEXURE 9 |
| 15 | Tool Room - Civil works ANNEXURE 9 |
| 16 | S/C for Entrance Arch ANNEXURE 16 |
| 17 | Electrical panel Room- Civil Works ANNEXURE 9 |
| 18 | S/C of Approach road for vehicle movement ANNEXURE 6 |
| 19 | Externalelectricalworksincludinggettingpower supply (HT) from the department with proper approvals, deposits, etc as per actuals. Internal Electricalworks, Lightening arrestor, earthpits,solar lights,etc., ANNEXURE 19 |
| 20 | S/C for CC Cameras including with all accessories 8 nos camera and DVR including TV ANNEXURE 9 |
| 21 | Toilet blocks including soak pit and septic tank.ANNEXURE 21 |
| 22 | Supply and laying of plants and horticulture works including grass with necessary requirements ANNEXURE 22 |
| 23 | Office block ANNEXURE 9 |
| 24 | S/c for Barricating the site area with View Cutter ANNEXURE 9 |
| 25 | S/E OF TRACK PLATE |